Smart Summary

Factual and Procedural Background

The matter concerns two connected proceedings recorded in the opinion. First, CM No. 3268/2008 sought condonation of a two-day delay in filing an appeal; that application was allowed and the delay was condoned. Second, LPA No. 108/2008 is the present appeal challenging the order of the learned Single Judge dated 9th January, 2008, which dismissed the writ petition filed by the appellant.

The writ petition challenged an order dated 13th August, 2007 by which the Municipal Corporation of Delhi (MCD) respondents debarred the appellant from participating in MCD tenders for two years. The debarment followed alleged non-execution of de-silting work allotted to the appellant under work orders dated 13th June, 2007 and 14th June, 2007. The Single Judge dismissed the writ petition, holding that the appellant had failed to commence work as required and had been given opportunities (including a show cause notice and personal hearing); the Single Judge nevertheless permitted the appellant to invoke arbitration in accordance with law. The appellant appealed against that dismissal; both sides were heard on the appeal.

Legal Issues Presented

  1. Whether the two-day delay in filing the appeal should be condoned.
  2. Whether the order dated 13th August, 2007 debarring the appellant from tendering with MCD for two years was legally sustainable.
  3. Whether the appellant was properly informed of the corrigendum (dated 1st June, 2007) that revised the completion period from two months to 25 days.
  4. Whether the debarment order of 13th August, 2007 was a speaking order and complied with principles of natural justice (i.e., whether the appellant was given adequate notice and opportunity to be heard).

Arguments of the Parties

Appellant's Arguments

  • The appellant contended that the original Short Tender Notice dated 30th May, 2007 specified two months as the time for completion and that the work orders issued to him were contrary to those terms because the MCD unilaterally reduced the completion period to 25 days.
  • The appellant asserted that he was never intimated of the corrigendum dated 1st June, 2007 (which stipulated 25 days) and therefore was not aware of any change before receipt of the work orders dated 13th and 14th June, 2007.
  • The appellant argued that the debarment order of 13th August, 2007 was not a speaking order.

Respondent's Arguments

  • The respondents relied on a corrigendum dated 1st June, 2007 (issued before the tender closing date) that re-stipulated the time for completion as 25 days from the date of issue of the work order, and they placed that corrigendum on the record.
  • They pointed out that the appellant was the sole tenderer, that correspondence (including the corrigendum and negotiation letters) was sent to the address provided by the appellant and was received, and that the work orders expressly required completion within 25 days.
  • The respondents emphasized that the appellant failed to commence work, was issued a show cause notice dated 20th June, 2007 (and given personal hearing on 29th June, 2007), did not submit a reply, and thereafter the competent authority, after processing the matter, passed the debarment order dated 13th August, 2007.
  • They maintained that the debarment decision was preceded by due process (show cause notice, opportunity to reply and personal hearing) and therefore did not infringe principles of natural justice.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court addressed the proceedings in sequence. On the interlocutory application (CM No. 3268/2008), the court examined the materials and found "sufficient cause" for a two-day delay in filing the appeal, allowed the application, condoned the delay and took the appeal on record.

On the substantive appeal (LPA No. 108/2008) the court reviewed the Single Judge's findings and the original administrative records. Key factual and documentary findings relied upon by the court included:

  • The Short Tender Notice dated 30th May, 2007 originally stated two months as the completion period, but a corrigendum dated 1st June, 2007 (issued before the tender closing date of 4th June, 2007) re-stipulated the completion period to 25 days from the date of issue of the work order. That corrigendum was part of the record and issued pursuant to a decision recorded in the note sheet.
  • The Executive Engineer's note of 7th June, 2007 recorded the 25-day completion period and recorded that negotiations had been conducted with the appellant because his quoted rates were high.
  • The appellant was the sole tenderer, was invited for negotiation on 7th June, attended, and the contract was awarded by order dated 14th June, 2007 with the 25-day completion period.
  • Upon the appellant's failure to commence work, a show cause notice dated 20th June, 2007 was issued, calling for a reply within three days. The appellant did not reply. The appellant was given personal hearing (29th June, 2007) and was warned that the work was urgent and should be started immediately to avoid disciplinary action.
  • By letter dated 22nd June, 2007 an opportunity to start the work was again afforded to the appellant to enable him to avoid disciplinary action; the appellant expressed inability to start within 25 days and contended that two months were required as per the tender notice.
  • After processing the file and proposing disciplinary action (including forfeiture of earnest money and a two-year debarment), the competent authority issued the debarment order dated 13th August, 2007.

Applying these facts, the court concluded that:

  • The corrigendum was issued before the tender closing date and formed part of the record; the 25-day completion term was repeatedly recorded in the file and communicated in correspondence to the appellant at the address he had provided.
  • Since the appellant was the only tenderer and all correspondence was conducted with him at his given address (including the negotiation letter and subsequently issued work orders), the appellant's contention that he was unaware of the corrigendum and the 25-day stipulation was not accepted by the court.
  • The respondents had issued a detailed show cause notice, afforded a personal hearing, and recorded reasons before passing the debarment order; consequently the court found no violation of natural justice and held that the order was a speaking order for the purposes of administrative action.
  • Given these findings, the court found no error in the Single Judge's dismissal of the writ petition and found the present appeal to be without merit.

Holding and Implications

Core Rulings:

  • The application for condonation of delay (CM No. 3268/2008) was allowed; the two-day delay in filing the appeal was condoned and the appeal was taken on record.
  • The appeal (LPA No. 108/2008) challenging the Single Judge's order was dismissed.

Implications:

  • Direct effect: The appellant's condonation application succeeded, but the substantive challenge to the debarment order failed and the debarment-related administrative action and the Single Judge's dismissal remain intact.
  • No broader legal precedent is announced by the court in this opinion; the decision upholds the administrative process followed by the respondents (corrigendum issuance, show cause notice, personal hearing and reasoned order) and finds no breach of natural justice on the facts presented.

    B.S Constructions Co v. The Commissioner Of Mcd & Ors

    Dr. Mukundakam Sharma, C.J:—

    CM No. 3268/2008

    By this application the appellant prays for condonation of delay in filing the appeal. There is a delay of two days in the filing the appeal. On going through the application we find that the appellant has been able to make out a case of sufficient cause for condonation of delay. Accordingly, we allow the application and the delay in filing the appeal is condoned. The appeal is taken on record.

    The application stands disposed of.

    LPA No. 108/2008

    This order shall dispose of the appeal which is filed by the appellant challenging legality of the order dated 9th January, 2008 passed by the learned Single Judge dismissing the writ petition filed by the appellant.

    2. The writ petition was filed by the appellant being aggrieved by the order of the respondents dated 13th August, 2007, whereby the appellant was restrained/debarred from participating in the tender process of the MCD for a period of two years on account of non-execution of the work of de-silting, which was allotted to the appellant under work orders dated 13th June, 2007 and 14th June, 2007. The learned Single Judge heard the counsel for the parties and after going through the records found that the appellant was called upon to start work and to complete the same within 25 days, but that he did not do so on the pretext that he would need at least two months' time to complete the work. The learned Single Judge however did not accept the aforesaid plea taken up by the appellant and on perusal of the original records observed that the appellant was called upon to start work and complete the same within 25 days. Even a show cause notice dated 20th June, 2007 was issued and the appellant-contractor was also called for personal hearing, which was held on 29th June, 2007, at which stage the appellant-contractor was warned that the work in question is of urgent nature and work should be immediately started to avoid disciplinary action against the appellant-contractor. The learned Single Judge held that the since the appellant-contractor did not start work, there was no merit in the writ petition, which was dismissed, giving an opportunity however to the appellant to invoke the arbitration clause in accordance with law.

    3. Being aggrieved by the aforesaid findings recorded by the learned Single Judge, the present appeal is filed on which we have heard the learned counsel appearing for the parties and have also gone through the records.

    4. Our attention was drawn to the Short Tender Notice dated 30th May, 2007 wherein it was mentioned that the time for completion of the work was two months. The respondent has taken up a stand that in the meantime a corrigendum was issued on 1st June, 2007, wherein it was specifically stipulated that time for completion of the work under the Short Tender Notice dated 30th May, 2007 would be 25 days from the date of issue of the work order. The said corrigendum is reproduced below for reference:

    “Due to time bound work the time of completion of Short Notice NIT No. EE-XXX/TC/2007-2008/4 dated 30.5.07 due on 04.06.07 shall be 25 days from the date of issue of work order.”

    5. The appellant on the other hand has taken up a plea that he was never intimated about the aforesaid corrigendum and was not made aware of any change in the stipulation in the Short Tender Notice before issuance of and receipt of separate work orders dated 13th June, 2007 and 14th June, 2007. In the said work orders which were issued to the appellant, it was specifically mentioned that the appellant was to complete the aforesaid work within 25 days. The plea which was taken up before the learned Single Judge was that the said work orders were contrary to the terms of the Short Tender Notice as the time for completion of work was unilaterally reduced by the MCD from two months to 25 days.

    6. In the light of the aforesaid submissions of the learned counsel for the parties, we have also perused the original records. In the Short Tender Notice which was issued on 30th May, 2007 it was mentioned that the last date for receipt of tender was 4th June, 2007. However the stipulation of time for completion of the work in the said Short Tender Notice was two months. The respondent had in fact also issued a corrigendum on 1st June, 2007, i.e before the tender closing date, with the stipulation that the time for completion of the work under the Short Tender Notice dated 30th May, 2007 would be 25 days from the date of issue of the work order. The said corrigendum is a part of the record and was” issued pursuant to a decision recorded in the note sheet. In the noting of the Executive Engineer-XXX dated 7th June, 2007 also the time for completion of the entire work is mentioned as 25 days. It is also recorded in the said noting that negotiation was conducted with the appellant-contractor as the rates quoted by him were high. The said file was processed at different stages and by order dated 14th June, 2007 a decision was taken to award the contract in question in favour of the appellant.

    7. At the risk of repetition, it is necessary to reiterate at this stage that although as per approved/draft notice inviting tender, the time for completion was two months, due to urgency of the work, time for completion was re-stipulated as 25 days, for which a necessary corrigendum was issued under letter dated 1st June, 2007. Thereafter, it was found that the appellant was the only tenderer who had submitted tender. On opening of the tender submitted by the appellant it was found that the rates quoted were high and consequently, a letter was sent to the appellant requesting him to attend the office of the Superintending Engineer on 7th June, 2007 for negotiations for reduction of the quoted rates. The appellant attended the said meeting. Thereafter, the work was awarded to the appellant after taking a decision in that regard, under order dated 14th June, 2007, with the period of completion of the work as 25 days.

    8. As the appellant-contractor did not start any work immediately after the issuance of the work order, a show cause notice was issued to the him under letter dated 20th June, 2007, directing him to submit reply within three days from the date of the issue of the said show cause notice. The appellant however did not submit any reply to the said show cause notice. It was therefore concluded by the respondent that the appellant-contractor was not interested in the execution of the said contract and therefore some action was required to be taken against the appellant-contractor for the default. A proposal was given to the concerned authority to forfeit the earnest money of the appellant-contractor and also not to accept any business from the appellant for a period of two years. Finally, order dated 13th August, 2007 was passed to the effect that the appellant-contractor is debarred from tendering in MCD for a period two years.

    9. The pleas taken before us are that the appellant was not served with the corrigendum and that the order passed on 13th August, 2007 is not a speaking order. Both the aforesaid issues were also urged before the learned Single Judge who, after considering the same, passed a detailed speaking order and the said contentions were rejected by giving reasons for the same. Records placed before us indicate that before taking action to debar the appellant from participating in the tender process for a period of two years as stated above, a show cause notice was issued to the appellant. Even thereafter, by letter dated 22nd June, 2007, an opportunity was granted to the appellant to start the work so as to enable him to avoid disciplinary action, to which no heed was paid by him and he expressed his inability to start the work, stating that the time of 25 days to complete the work is insufficient and that he should have been given two months' time as given in the notice inviting tender. The appellant was also given personal hearing on the aforesaid show cause notice and thereafter he was also informed that the case has been processed for disciplinary action against his firm for his failure to execute the work. Before issuing the order debarring the appellant from participating in the tender process, the respondent was satisfied from the records that the appellant has deliberately avoided the execution of the work, taking an unwarranted plea for the same. The competent authority having found that the plea taken by the appellant was unjustified, passed the aforesaid order after giving a reasonable opportunity to the appellant to rebut the contentions raised in the show cause notice issued to the appellant. Therefore, we are of the considered opinion that there is no violation of the principles of natural justice in the aforesaid action taken by the respondent after giving due notice and after giving full opportunity to the appellant to rebut the allegations made against him.

    10. The contention that the appellant was not aware of the corrigendum stipulating that the work is to be completed within 25 days from the date of acceptance of the tender and issuance of work order also cannot be accepted, for, the appellant was the only tenderer and whatever correspondence was done was only with him. His matter was processed and even on the first date when his matter was processed, it was specifically mentioned in the note sheet that the work is to be completed within 25 days. Copies of the letters and the corrigendum were also sent to the appellant at the address provided by the appellant. Even the letter requesting him to attend the negotiations for reduction of the quoted rates was received by him at the same address. Subsequent work orders issued to him, which admittedly were received by him, were also sent at the same address and, therefore, the plea that he did not know the revised stipulation that the completion time for the work was 25 days, cannot be accepted.

    11. The appellant was given a detailed show cause notice and was granted personal hearing and, thereafter the order was passed for which reasons are also recorded in the records. Therefore, the contention that no speaking order was passed by the respondent to debar the appellant from participating in the tender process for a period of two years also cannot be accepted.

    12. In view of the above discussion, we find no infirmity in the impugned judgment and order passed by the learned Single Judge. The appeal has no merit and is dismissed.