Smart Summary

Judicial Opinion Summary: Appeal against Single Judge's dismissal (Arbitral award challenge)

Factual and Procedural Background

(All points below are drawn exclusively from the provided opinion.)

The appellant challenged an order of the learned Single Judge dated 21.3.2001 which dismissed the appellant's petition. The dispute between the parties was governed by an agreement containing an arbitration clause. Pursuant to that clause, the matter was referred to arbitration and a retired Director General, CPWD, was appointed as Arbitrator. The Arbitrator issued an award dated 27.11.1990. One of the claimant's claims before the Arbitrator was Claim No. 7, which was for Rs. 16,50,000 as reimbursement for increase in market prices after the stipulated date of completion.

The key factual points considered by the Arbitrator (as reproduced in the opinion) include:

  • Start date of work: 21.2.1981; contractual completion date: 20.2.1982.
  • The claimant asserted the work was completed in January 1984; the respondent asserted the work was never completed.
  • The claimant alleged various breaches by the respondent and sought damages; the respondent maintained a hindrance register recording specific delays and the periods of hindrance.

The Arbitrator, after considering delays recorded in the hindrance register and the parties' conduct, restricted the claimant's Claim No. 7 from Rs. 16,50,000 to Rs. 3,50,000. The Single Judge examined the arbitration award and the documents before the Arbitrator and dismissed the appellant's petition; the present appeal challenges that dismissal, focusing on the reasoning given (or alleged lack of reasoning) for the Rs. 3,50,000 award under Claim No. 7.

Legal Issues Presented

  1. Whether the Arbitrator's award of Rs. 3,50,000 under Claim No. 7 is vitiated by the Arbitrator's alleged failure to give reasons for arriving at that figure, in circumstances where the arbitration clause required the Arbitrator to give reasons.
  2. Whether the learned Single Judge was correct in upholding the Arbitrator's award and dismissing the appellant's petition despite noting that the Arbitrator did not set out detailed reasons for the precise figure awarded.

Arguments of the Parties

Appellant's Arguments

  • Reliance on counsel Mr. Bhuchar's submission limiting the appeal to the portion of Claim No. 7 granting Rs. 3,50,000.
  • The primary contention was that the Arbitrator did not provide any reasons for concluding that the appellant (claimant before arbitrator) was entitled to only Rs. 3,50,000 under Claim No. 7.
  • Because the arbitration clause specifically provided that the Arbitrator was to give reasons, the absence of reasons for that specific figure vitiates the award and the Single Judge's approval of the award on that point should be set aside.

The opinion does not set out specific counter-arguments advanced by the respondent in the court below or in the appeal; the court's narrative focuses on the appellant's contention and the Arbitrator's and Single Judge's reasoning.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court's analysis proceeded by examining (a) the Arbitrator's award language and the materials before the Arbitrator, and (b) the impugned order of the Single Judge who had earlier considered the same materials.

Key points in the court's reasoning, as stated in the opinion:

  • The Single Judge had noted that no reason was immediately discernible for the precise figure of Rs. 3,50,000 in the Arbitrator's award, but the Single Judge nevertheless analysed the documents and the Arbitrator's findings and discussed the underlying reasons in detail in the impugned order.
  • The opinion reproduces Claim No. 7 and the Arbitrator's analysis, which shows that the Arbitrator considered:
    • the contractual start and completion dates;
    • disputed completion dates between the parties;
    • entries in the respondent's hindrance register listing specific hindrances and their periods (for example, non-availability of foundation drawings, delays in certain decisions, short supply of cement, holds because of DESU not laying cables, etc.);
    • evidence of claimant's own delays (for instance, delayed arrangement for water delaying lean concrete work) and slow general progress;
    • the absence of a cement shortage according to the cement register.
  • On this basis the Arbitrator concluded that while the respondent was responsible for some initial delay (e.g., delay in supplying drawings and decisions), the respondent was not responsible for the entire period of delay claimed by the claimant. Accordingly, the Arbitrator reduced the claimant's demand and awarded only Rs. 3,50,000 for delay attributable to the respondent.
  • The court expressly accepted the principle (as applied here) that an Arbitrator need not disclose the detailed mental process or reasons to the same extent as a judge when delivering a reasoned award. It is sufficient if the Arbitrator indicates a trend or provides an outline that shows the basis on which the award figure was reached.
  • The Arbitrator in this case was a former Director General of CPWD and, on the court's view, was well placed to assess the matters on the basis of experience combined with the materials before him; the Arbitrator's limiting of the claim from Rs. 16,50,000 to Rs. 3,50,000 was a considered exercise based on those materials.
  • The learned Single Judge had examined the documents placed before the Arbitrator and the reasons discussed in the impugned order; the appellate court found no infirmity in that approach or in the conclusion reached by the Single Judge.

Holding and Implications

APPEAL DISMISSED.

Holding (core ruling): The appellate court dismissed the appeal and upheld the learned Single Judge's order that had approved the Arbitrator's award restricting Claim No. 7 to Rs. 3,50,000. The court found no infirmity in the Single Judge's reasoning and concluded that the Arbitrator's award was not vitiated by the lack of a detailed account of the precise mental arithmetic or calculation that led to the Rs. 3,50,000 figure.

Implications (direct effect): The immediate consequence is that the Single Judge's order stands and the Arbitrator's award of Rs. 3,50,000 under Claim No. 7 remains effective between the parties. The opinion does not discuss broader precedential consequences; accordingly, only the direct effect on the parties is recorded here and the disposition does not purport to establish any new legal precedent beyond the application of the principles described in the court's reasoning.

Appeal dismissed.

    D.D.A v. Bhagat Construction Co. Pvt. Ltd. .

    Vijender Jain, J.—This appeal has been filed impugning the order passed by the learned Single Judge whereby the petition of the appellant was dismissed on 21.3.2001 Pursuant to an arbitration Clause in the agreement the matter was referred to the arbitration by appellant and a retired Director General, CPWD was appointed as the Arbitrator. The Arbitrator gave its award dated 27.11.1990

    2. Mr. Bhuchar, learned Counsel for the appellant has limited his argument on the grant of Rs. 3,50,000 under the claim No. 7 by the Arbitrator said finding of the Arbitrator has been approved in the impugned order passed by the learned Single Judge. The main argument of learned Counsel for the appellant is that the Arbitrator has not given any reason for coming to the conclusion that under claim No. 7 the appellant was to pay a sum of Rs. 3,50,000. In nutshell the argument of the learned Counsel for the appellant is that in the arbitration clause it was specifically provided that the Arbitrator was to give reasons, non-giving of reasons by the Arbitrator in arriving at the figure of Rs. 3,50,000 has vitiated the award and, therefore, the finding on that score by the learned Single Judge is to be set aside.

    3. We have perused the impugned order. The learned Single Judge has noted that no reason is discernible for arriving at the figure of Rs. 3,50,000, however, in the impugned order itself the reasons for arriving at such figure by the Arbitrator has been discussed in detail by learned Single Judge. We may also reproduce the claim No. 7 and how the Arbitrator arrived at the finding and what were the circumstances which led to the said finding:

    “Claim No. 7: Claim for Rs. 16,50,000/- toward reimbursement of increase in market prices after the stipulated date of completion.

    The date of start of work was 21.2.1981 and the date of completion as per the agreement was 20.2.82 According to the claimant the work was completed in January 1984, but according to the respondent the work was never completed. The claimant has claimed damages due to various breaches committed by the respondent. From the hindrance register maintained by the respondent it is seen that there were following hindrance in the work:

    S.No Particulars Period of hindrance 1. Non availability of foundation Drgs. 21.2.81 to 11.4.81 2. Decision reg. Plinth level 21.2.81 to 22.5.81 3. Decision about supply of earth filling 13.5.81 to 13.8.81 4. Non-availability of structural Drgs. 16.6.81 to 15.9.81 5. Supply of SCI pipes 2.6.81 to 1.1.82 6. Rectification of work 13.9.82 to 18.10.82 7. Short supply of cement 21.2.81 to 1.5.83 8. Development works held up of blocks because of not laying cables by DESU. 21.2.82 to 31.12.83

    There was an initial delay in the supply of the foundation drawings to the claimant on 11.4.81, but the claimant did not make any arrangement for water till 28.5.81 and the laying of the lean concrete could be started only from 28.5.81 This shows that there was delay, partly on account of claimant also due to his not making the necessary arrangements. It is also seen that although there was some delay in issue of the structural drawings, but after the structural drawings were issued, the claimant took considerable time in laying the RCC slabs. Also the general progress of the work was slow and the cement register shows that at no stage there was any shortage of cement. The respondent is responsible for the initial delay in the supply of drawings and other decisions, as indicated in the hindrance register and, therefore, the work could not be completed in the stipulated period. The respondent is not responsible for the full delay as alleged by the claimant and I, therefore, hold that the claimant be paid a sum of Rs. 3,50,000/- only on account of the delay by the respondent in giving drawings and decisions.”

    4. From the above, it would be clear that the Arbitrator who was well versed in the matter before him as a former Director General of CPWD on the basis of his experience took into consideration the various aspects and that is why instead of awarding a sum of Rs. 16,60,000 as claimed by the claimant restricted the said claim to Rs. 3,50,000. Arbitrator has not to disclose the basis or the mental process for arriving at such figure. Even otherwise Arbitrator when called upon to give a reasoned award is still not required to write a detailed judgment as the Judges do. It is sufficient that he has indicated his trend and given outline to indicate the basis on which he has arrived at such figure. The learned Single Judge has gone through in details those documents which were produced before the Arbitrator which were the basis of arriving at the said figure in the award. We find no infirmity in the impugned order. Dismissed.

    Appeal dismissed.