Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Smart Summary

Judicial Opinion — Summary

Factual and Procedural Background

Respondent No. I, Kameshwar Dubey (the "workman"), was employed as a Khalasi (casual labour) from 20-12-1969 and was orally dismissed on 29-5-1974. The workman instituted Suit No. 233 of 1975 against the Union of India (through the General Manager, Northern Railway, Baroda House, New Delhi) seeking a declaration that his dismissal was illegal, void, inoperative, mala fide and a nullity and that he continued in railway service and was entitled to service benefits. On 13-10-1981 Shri Z.S. Lohat, Sub Judge I Class, granted the decree declaring the dismissal void and directing reinstatement/entitlement to service benefits. The Union of India unsuccessfully appealed: RCA No. 13/82 (dismissed 27-9-1983), a second appeal (RSA 32 of 1984 dismissed 8-8-1984) and an SLP (dismissed 20-1-1986).

On 3-6-1985 the workman filed a petition under S.15 of the Payment of Wages Act, 1936. The authority Shri M.K. Seth, by order dated 7-8-1985 (ex parte), directed the Union to pay Rs. 80,591.42 for wages/allowances and Rs. 1,00,000 as compensation for deduction of wages. Attempts by the Union to set aside or challenge the authority's order were largely unsuccessful: an application to set aside the ex parte direction was dismissed on 3-1-1986; objections under S.47 CPC were dismissed on 29-4-1986. The Union filed appeals under S.17 of the Act (28-4-1986) before Shri Lokeshwar Prasad, Addl. District Judge; a stay order on 6-5-1986 required deposit of the amount with a direction that it not be released pending further order.

The workman sought immediate release of deposited funds after the appellate authority (Lokeshwar Prasad) dismissed the appeals on 28-3-1987 as incompetent; an application for release was dismissed on 2-4-1987 by successor authority Shri Asharif Lal. The workman then filed Civil Writ No. 1042/87 in the High Court which resulted in an order dated 27-5-1987 directing payment of the deposit to the workman. The Union filed Civil Writ No. 1705/87 seeking quashing of the appellate authority's order dated 28-3-1987 plus an application (C.M. 2404/87) for stay in respect of realization of deposited Rs. 1,80,591.42. On 27-5-1987 the Court made a partial restraint order: withholding the Rs. 1,00,000 compensation but permitting payment of Rs. 80,591.42 (wages and allowances) to the workman; it was later noted that a separate Division Bench had ordered release of the entire amount in Civil Writ No. 1042/87 on the same day.

Legal Issues Presented

  1. Whether the amount paid to the workman under the direction of the authority (Shri M.K. Seth) constituted "wages deducted" or merely "delayed wages" for the purposes of S.15 of the Payment of Wages Act, 1936, because the available remedies and permissible compensation differ substantially between the two categories.
  2. Whether the Union of India could rely on the contention that the workman failed to implead the actual paying authorities (e.g., Chief Project Manager, Railway Electrification, Mathura or General Manager, Western Railway, Bombay) such that notices sent to the General Manager, Northern Railway were not properly connected and remained in transmission.

Arguments of the Parties

Appellant (Union of India) — Principal Contentions

  • The Act contemplates only those deductions from wages which are recognized specifically by certain sections (referred to in the opinion as "Ss. 7 to 2, 12A and 13" — as put forward by the learned counsel for the petitioner); implicitly, therefore, the payments in question did not qualify as "deductions" under S.15.
  • The workman had not impleaded the officers who were actually responsible for payment under S.3 of the Act (the Chief Project Manager, Railway Electrification, Mathura or the General Manager, Western Railway, Bombay), so notices addressed to the General Manager, Northern Railway could not be effectively connected and may have remained in transmission between offices.

Respondent (Workman) — Position as Reflected in the Opinion

  • The workman maintained that his dismissal was illegal (suit result in his favour), that he remained in service and was entitled to arrears of wages and service benefits. He pursued relief by suit, by petition under S.15 of the Payment of Wages Act, and by writ remedy when appropriate.
  • The workman served multiple notices on the Union requesting reinstatement and payment of arrears after the decree, and sought release of deposited funds when appellate orders were resolved against the Union.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Delta Forging Work v. Manik Karmakar, 1977 LAB. I.C. 207 Supports the view that the classification of an amount as "deducted" or "delayed" wages depends on the employer's intention; 'deduction' is to be read broadly. The Court relied on this authority to support a broad meaning of "deduction" and the test of employer's intention when deciding that the Union's conduct amounted to denial of liability (i.e., deduction).
K.P. Mushran v. B.C. Patil, AIR 1952 Bom. 235 Used to support the general proposition on the nature of deductions/delays in wage claims and the employer's intention. Cited as supporting authority for the Court's approach on distinguishing deducted wages from delayed wages.
Upper India Coupar Paper Mills Co. Ltd. v. J.C. Mathur, AIR 1959 All. 664 Holds that the word "deductions" in S.15 is used in a wide sense to include withholding of part or the whole of wages and encompasses the entire deficiency alleged by an employee. The Court adopted this expansive interpretation of "deduction" to reject the Union's narrow construction of the term.
Anant Ram and others v. District Magistrate, Jodhpur and another, AIR 1956 Raj. 145 Reinstatement after dismissal implies that wages for the intervening period were wholly or partly deducted by the employer (i.e., the employer withheld wages for that period). The Court cited this case to illustrate that reinstatement plus non-payment of wages implies deduction; applied to the present facts where the workman was reinstated (by decree) and unpaid for the relevant period.

Court's Reasoning and Analysis

The Court framed the decisive legal question as whether the sums paid to the workman under the authority's direction constituted "wages deducted" or merely "delayed wages" under S.15 of the Payment of Wages Act. The distinction matters because sub‑section (3) of S.15 permits, where wages are deducted, imposition of compensation up to ten times the wages deducted, whereas for delayed wages the statutory maximum compensation is only Rs. 25.

The Court articulated the governing test: the classification depends on the employer's intention. If the employer intends to deny liability to pay or denies the employee's right to receive wages, the situation is one of "wages deducted"; if the employer concedes liability and the right but delays payment, it is a case of "delayed wages." The Court observed that this approach is supported by earlier decisions (Delta Forging Work, K.P. Mushran, Upper India Coupar Paper Mills, and Anant Ram).

Applying these principles to the facts, the Court found that:

  • The workman was not paid wages from his removal on 29-5-1974 until the payment order dated 27-5-1987.
  • After the decree in his favour and subsequent dismissal of the Union's appeals, the workman repeatedly sent notices to the General Manager, Northern Railway requesting reinstatement and payment of arrears (notices dated 16-10-81, 14-10-81, 12-12-81, 29-5-82, 28-2-84, 4-4-84, 23-1-85 and 14-7-1986), yet the Union failed to reply or to make payment.
  • The Union sought deposit and a stay in appellate proceedings and secured an order that deposited funds not be released, an action the Court inferred was taken at the Union's instance — which further indicated an intention to withhold payment rather than to acknowledge a delayed payment obligation.
  • The Union's writ seeking wholesale quashing of the authority's and appellate orders did not indicate any concession of the workman's right to wages or the Union's liability — reinforcing the Court's conclusion of denial of liability.

On the point about non-impleading the actual paying authorities, the Court noted that the Union had not pleaded this point in its written statement in the original suit (as conceded by Union's counsel) and that the Union could have raised the issue in reply to the notices. Given the absence of any reply to the workman's notices, this technical objection was rejected.

Consequently, the Court concluded that the facts showed an intention by the Union to deny liability and the workman's right to wages; therefore the payments ordered by the authority were rightly treated as "wages deducted" and the authority's imposition of compensation (Rs. 1,00,000) under sub-sec. 3 of S.15 was justified.

Holding and Implications

Holding: The writ petition filed by the Union of India fails and is dismissed with costs. The Court ordered that the compensation amount of Rs. 1,00,000 be released in favour of the workman forthwith.

Implications:

  • Direct effect on the parties: The Union of India must pay the compensation (Rs. 1,00,000) ordered by the authority to the workman without further delay; earlier deposited amounts already directed to be paid (Rs. 80,591.42) were treated separately under prior orders.
  • The Court applied established precedents about the interpretation of "deduction" under S.15 and the employer's intention test; the opinion does not purport to create new legal precedent beyond its application of existing authorities to the facts.

No other points were urged and the writ petition is dismissed with costs; the compensation amount of Rs. 1,00,000 is ordered released to the workman.

    Union Of India Petitioner v. Kameshwar Dubey And Others S

    Jagdish Chandra, J. (Rule D.B):— Respondent No. I Kameshwar Dubey (hereinafter to be referred to as ‘workman’ was a railway employee employed as Khalasi (casual labour) with effect from 20-12-1969 and was dismissed from service by an oral order dated 29-5-1974. He brought a suit being Suit. 233 of 1975 against the petitioner-Union of India through the General Manager, Northern Railway, Baroda House, New Delhi for a declaration that his dismissal was illegal, void, inoperative, mala fide and a nullity and that he continued to be in service of the railway as if he was not dismissed at all and was further entitled to all other benefits of the service. The decree for the aforesaid declaration was granted on 13-10-1981 by Shri Z.S Lohat, Sub Judge Ist Class as a result of which his dismissal from service was held as void and was further held to have continued in service and also entitled to all the service benefits. This decree was passed after contest by the petitioner.

    3. The first appeal (RCA No. 13/82) of the petitioner Union of India through General Manager, Northern Railway against the aforesaid judgment and decree dated 13-10-81 of Shri Z.S Lohat, SJIC was dismissed on 27-9-1983 by Shri J.B Goel, Addl. District Judge, Delhi. Even the second appeal of the petitioner was dismissed by the High Court vide order dated 8-8-1984 in RSA 32 of 1984. Even the SLP of the petitioner against the said decree and judgment was dismissed by the Supreme Court on 20-1-1986.

    4. After having failed to be reinstated in service and not being paid his arrears of wages and other service benefits despite the aforesaid litigation ending every time in his favour, the workman filed a petition under S. 15 of the Payment of Wages Act, 1936 (in short the Act) against the petitioner on 3-6-1985 and Shri M.K Seth the authority under the Act made a direction on 7-8-1985 to the petitioner Union of India to pay to the workman within one month of the order a sum of Rs. 80,591.42 on account of wages and allowances besides another sum of Rs 1 lac as compensation for deduction of wages. This direction of the authority Shri N.K Seth was ex parte as the petitioner-Union of India did not put up appearance despite service. The application of Union of India for setting aside the aforesaid ex-parte direction of the authority Shri M.K Seth was dismissed on 3-1-1986 by Shri M.K Seth as highly frivolous and not maintainable at all. The petitioner Union of India then filed objections under S. 47 of the Code of Civil Procedure on 15-4-1986 against the recovery of the amount and payment of the same to the workman but those objections were dismissed on 29-4-1986.

    5. Appeals under S. 17 of the Act against the judgment dated 7-8-1985 and the order dated 3-1-1986 both passed by the authority Shri M.K Seth were filed by the Union of India on 28-4-1986 before Shri Lokeshwar Prasad, then Additional District Judge, Delhi.

    6. On the stay application filed along with the appeal of Union of India under S. 17 of the Act, order was passed on 6-5-1986 directing deposit of the amount within a week with a further order that the amount shall not be released to the decree-holder workman till further orders.

    7. The workman moved an application on 1-4-1987 for immediate release of the amount deposited as the appeals against the order of the authority Shri M.K Seth had been dismissed on 28-3-1987 by Shri Lokeshwar Prashad. Addl. District Judge on the ground that the appeals were not competent before him as he had no jurisdiction to entertain the same, but that application was dismissed on 2-4-1987 by the successor authority Shri Asharif Lal. The civil writ No. 1042/87 was filed in the High Court by the workman against Shri Asharif Lal, authority under the Act for the quashing of the order dated 2-4-87 and the writ petition was disposed of on 27-5-1987 with the direction that the amount laying in deposit be paid to the workman forthwith and that order was passed as the learned counsel appearing for the authority under the Payment of Wages Act conceded that the impugned order dated 2-4-1987 was illegal inasmuch as the interim order dated 6-5-1986 passed by Shri Lokeshwar Prashad no longer stood once the appeal in which it was passed, stood disposed of. The present writ before use being Civil Writ No. 1705/87 had been filed in the meantime by Union of India through General Manager, Northern Railway, Baroda House, New Delhi seeking to quash the order dated 28-3-87 by Shri Lokeshwar Prashad, Addl. District Judge (Appellate Authority under the Payment of Wages Act) along with an application being C.M 2404/87 for stay in respect of the realising of deposited amount of Rs. 1,80,591.42 by the workman and on that application partial restraint order was passed by us on 27-5-1987 whereby it was directed that the compensation amount of Rs 1 lac awarded by the authority Shri M.K Seth to the workman be not paid to the workman whereas the remaining sum of Rs 80,591.42 which was due to the workman on account of wages and allowances was ordered to be paid to him forthwith, and it was not brought to our notice by the counsel for the petitioner Union of India that the order of release for the entire amount including he compensation amount of Rs. lac had been passed on that very day, i.e 27-5-1987 by another Division Bench of this Court in favour of the workman in Civil Writ No. 1042 of 1987 filed by the workman.

    The main question falling for determination in this petition whether the wages in question paid to the workman under the direction of the authority Shri M.K Seth was on account of wages deducted or wages delayed, because if it is a case of wages deducted then under sub-sec. 3 of S. 15 of the Act the authority could, in addition to the payment of wages, also direct the payment of such compensation as the authority thinks fit not exceeding ten times the wages deducted but if it were the case of delayed wages the amount of compensation which the authority could order besides the delayed wages, could not exceed twenty-five rupees. As in the case in hand the authority has held the amount of wages as deducted wages, compensation to the tune of Rs. 1 lac was also awarded by the authority under sub-sec. 3 of S. 15 of the Act besides the wages, to the petitioner, and it is on account of the huge amount of compensation that the question of wages being deducted wages or delayed wages assumes great importance. The determination of this question necessarily depends upon the intention of the employer. If his intention is to deny the liability to pay the wages or the deny the right of the workman to receive the same, it would be a case of ‘wages deducted’. But if the employer concedes his liability to pay the wages to the workman and does not dispute the workman's right to the same, the case would be one of ‘delayed payment’. This view of ours finds support from the decision of a Division Bench of Calcutta High Court reported as Delta Forging Work v. Manik Karmakar 1977 LAB. I.C 207(1) and K.P Mushran v. B.C Patil, AIR 1952 Bom. 235(2) (DB).

    9. The learned counsel for the petitioner Union of India contended that the Act contemplated only those deductions from wages which were recognised by Ss. 7 to 2, 12A and 13 of the Act and not the ones in the case in hand. This contention cannot be accepted and the word ‘deduction’ has to be taken as having been used in the Act in the wider sense meaning ‘to take away’ denying the liability to pay the wages to the employee [vide—Delta Forging's case (supra)]. The meaning of the word ‘deduction’ appearing in S. 15 of the Act had also come up for consideration in the case of Upper India Coupar Paper Mills Co. Ltd. v. J.C Mathur, AIR 1959 All 664(3) before the Lucknow Bench of Allahabad High Court wherein it was held as follows:—

    Deductions may relate to the specific heads mentioned in the particular sections of the Act or they may be deductions resulting from other causes. They may be the result of withholding of part of the Wage or of the entire amount of wages. The word ‘Deductions’ in Section 15 appears to be used in a wide sense so as to include the entire deficiency which the employee alleges, as a result of the withholding of the same by the employer whether partially or wholly.”

    10. In Anant Ram and others v. District Magistrate, Jodhpur and another, AIR 1956 Raj. 145(4)(S) it was held as under:—

    “. . . . . In the cases before are the applicants were dismissed on one date, and were reinstated on a later date. They were not paid their wages for the period between the dismissal and the re-instatement. Their claim is for wages for this period. Their reinstatement clearly implies that the Authority deducted their wages wholly or in part for the period between dismissal and re-instatement,. . . . . .”.

    11. As already point out above, in the case in hand the workman was not paid his wages for the period since his removal from service on 29-5-1974 and it was only on 27-5-1987 that this Court ordered the payment of the wages amounting to Rs. 80, 591.42 to be made to the workman and this payment order was made after the passing of the decree by Shri Z.S Lohat, Sub Judge and the dismissal of the two appeals of Union of India and the direction of the authority Shri M.K seth under the Payment of Wages Act and the appeal against the order of the authority and the filing of the writ petitions. Even though the petitioner-Union of India deposited the amount under the orders of Lokeshwar Parshad, Addl. District Judge in appeal against the order of the authority, it was further ordered that the deposited amount was not to be paid to the workman till further orders and this order of non-payment must have been made only at the instance of the petitioner-Union of India. It would be further seen from the order dated 7-8-1985 of the authority Shri M.K Seth M.K Seth that a number of notices were given by the workman to the petitioner-Union of India (through General Manager, Northern Railway, Baroda House, New Delhi) requesting for his re-instatement and payment of the arrears of wages to him after the passing of the decree in his favour by Shri Z.S Lohat, Sub-Judge but the petitioner Union of India did not care to give any reply to any of these notices, nor made the payment. These notices are dated 16-10-81, 14-10-81, 12-12-81, 29-5-82, 28-2-84, 4-4-84 and 23-1-85. He also gave the notice dated 14-7-1986 to the Union of India for the said purpose but to no effect. These notices were given on different stages of the litigation, i.e after the decree of the learned sub judge, after the dismissal of the first appeal of the petitioner, after the dismissal of the second appeal of the petitioner and after the direction from the authority. The total omission on the part of the petitioner-Union of India to pay the wages to the workman was clear indication on its part to deny its liability to pay the same to the workman as also the denial of the workman's right to receive those wages from the petitioner and this already clear position of the Union of India stands further clarified from the order of Shri Lokeshwar Parshad, Addl. District Judge (the Appellate Authority under the Act) whereby the amount deposited in pursuance of the stay application of the petitioner was ordered not to be released to the workman till further orders and, as already pointed out above, such direction must have been passed only at the instance of the petitioner. Even in the prayer clause of the present writ petition dated 25-5-1987 the petitioner while seeking the quashing of the orders dated 7-8-1985 and 28-3-1987 passed respectively by the authority and the appellate authority under the Act, does not even hint at its conceding the right of the workman to receive his wages, nor its liability to pay the same. The prayer for the whole-sale quashing of these two orders leaves no doubt in the position taken up by the petitioner regarding the denial of its liability to pay the wages to the workman and his right to receive the same from it, and when that is the animus of the petitioner-Union of India there is no escape from the conclusion that this is a case of deducted wages and not of mere delayed wages with the result that the authority under the Payment of Wages Act was fully justified in holding these wages as ‘deducted wages’ and consequently directing the petitioner to pay the same together with the compensation amount of Rs. 1 lac to the workman.

    12. The next contention raised on behalf of the petitioner Union of India is that the workman did not implead either the Chief Project Manager, Railway Electrification. Mathura or the General Manager, Western Railway Bombay the person responsible for making payment in terms of S. 3 of the Act with the result that the notices sent to the office of the General Manager, Northern Railway could not be connected and the same remained in transmission from one office to another. This contention cannot be accepted because it would be seen that no such plea was taken by the petitioner in the written statement filed in the suit in the court of Sh. Z.S Lohat, Sub Judge, Delhi, as conceded at the Bar during the course of arguments by Shri Dutt learned counsel for the petitioner, even though that suit was filed by the workman against Union of India through the General Manager, Northern Railway, Baroda House, New Delhi. This plea could have been taken in reply to any of the various notices sent by the workman to the General Manager, Northern Railway and in the face of no reply to any of the various notices sent by the workman, this plea of the petitioner cannot be accepted.

    13. No other point was urged and in view of the above discussion the writ petition fails and is dismissed with costs.

    The compensation amount of Rs. 1 lac be released in favour of the workman forthwith.