Smart Summary

Structured Summary of Opinion — P.N. Khanna, J.

Factual and Procedural Background

The petitioner, Compagnie de Saint Gobain (a French company), entered into a contract by a letter of instructions dated 10 October 1957 with Nangal Fertilizer Chemicals Private Limited (predecessor-in-interest of the respondent, Fertilizer Corporation of India Limited) for construction of the Nangal Fertilizer group of plants. The letter contained an arbitration clause providing that disputes would be settled by arbitration in conformity with the International Chamber of Commerce (ICC) Rules and that the venue of arbitration would be New Delhi, India.

Disputes arose and the petitioner made an arbitral request to the ICC Court in Paris on 19 June 1964. The respondent filed a counter-claim. An arbitral tribunal was constituted under ICC Rules. The tribunal sat in New Delhi, Paris (for some witness evidence), New Delhi again and finally in Mussourie. After changes in membership (resignation and death), Lord Devlin was ultimately constituted as sole arbitrator by agreement of the parties and made an award dated 29 September 1969, communicated by the ICC Secretariat on 16 October 1969.

The award granted sums in favour of the respondent. The respondent sought execution in France; certain bank accounts and trade-marks of the petitioner were attached in France and the petitioner furnished bank guarantees. The petitioner challenged those French orders in the French courts and, while those proceedings were pending, filed the present application in this Court under section 33 of the Arbitration Act, 1940, seeking (a) a declaration that the award had no legal effect or existence and was not enforceable, or (b) suspension of the award until it was filed and made a rule of the Court in India.

The petitioner alleged four grounds of nullity in the petition (only two of which were pressed): (1) the award was made out of time and after the arbitrator had become functus officio; and (2) the award had not been filed in Court as required by the Arbitration Act. The respondent contested jurisdiction, submitted that the award was not governed by Indian law and that French courts had already acted on the award.

Legal Issues Presented

  1. Whether the award of 29 September 1969 is governed by the Indian Arbitration Act, 1940, or by foreign-award legislation / international convention (notably the New York Convention as implemented by the Foreign Awards (Recognition & Enforcement) Act, 1961).
  2. Whether this Court (the Delhi High Court on its original side) has jurisdiction to entertain the petition under section 33 of the Arbitration Act, 1940.
  3. Whether the award was made after the time allowed (i.e., was the award made out of time under ICC Rules such that it became functus officio and therefore a nullity), and whether the Court should exercise its discretion under section 28 of the Arbitration Act to enlarge the time for making the award.
  4. Whether an award not filed in Court is a nullity and has no legal effect until it is made a rule of Court (raised by the petitioner on the enforceability point).

Arguments of the Parties

Petitioner's (Appellant's) Arguments

  • The award is a nullity because it was made out of time — the arbitrator had become functus officio; Article 23 of the ICC Rules gave 60 days from signing the statement defining terms of reference and the award was made after that period.
  • Section 28(2) of the Arbitration Act makes void any provision permitting arbitrators to enlarge time except with the consent of all parties; extensions purportedly granted by the Court of Arbitration are ineffective without party consent.
  • The award has not been filed in Court and therefore, petitioner contended, it is a nullity and has no legal existence or enforceability until filed and made a rule of Court.
  • The petitioner did not press two of the four pleaded grounds at the hearing (specifically abandoned the contention on certain matters and did not elaborate ground (3)).
  • The petitioner submitted that the Court should refuse to exercise its discretion to enlarge time (under section 28) because petitioner would be prejudiced: it had no opportunity to file objections to the award earlier and the time for procedural steps had lapsed.

Respondent's Arguments

  • The award was not governed by Indian law and the Arbitration Act, 1940 did not apply; the award was a foreign award made outside India (the Court of Arbitration in Paris approved the award and the ICC Secretariat communicated it from Paris), and French courts had already executed the award.
  • The Court should avoid deciding the Indian application so as to prevent conflict with decisions of the French courts, which had already acted on the award and in respect of which bank guarantees were available to the respondent.
  • Under ICC Rules (Articles 26–28) the Court of Arbitration in Paris plays a role in approving the award and the award is communicated from Paris, so for Indian courts the award should remain a foreign award (relying on decisions such as M/s Lachman Das Sat Lal v. Parmeshri Dass and Kamani Engineering case).
  • The time for making the award was extended legitimately under ICC Rules and by mutual consent of the parties — petitioner had participated throughout and waived objections to dates and procedure; therefore the Court should exercise its discretion under section 28 to enlarge time and validate the award made on 29 September 1969.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
M/s Lachman Das Sat Lal and another v. Parmeshri Dass and another, AIR 1958 Punjab 258 Held that an award made and signed at Karachi was a foreign award; used to support that place where award signed can determine its character as foreign. The Court recorded the precedent was relied upon by respondent to argue that the award was foreign; the Court examined facts and concluded that the present award was made in India and thus Lachman Das did not control results here.
Societe De Traction et D’ Electricite Societe Anonyme v. Kamani Engineering Company Ltd., (1964) 3 SCR 116 Observation that the scheme of arbitration under ICC Rules is different from scheme under ss.3–38 of the Arbitration Act. The Court noted Kamani was relied on by respondent but explained Kamani did not decide inlimitation of the Arbitration Act where other statutory provisions applied; Court relied on section 47 analysis to hold Arbitration Act applied here.
M/s Dhanrajmal Gobindram v. M/s Shamji Kalidas & Co., (1961) 3 SCR 1020 Principles for determining proper law of contract and inference that parties' expressed intentions determine applicable law; arbitration clauses indicating arbitration in a country lead to inference that law of that country applies. The Court applied the principle to the present facts: parties expressly provided the contract would be governed by laws of India and arbitration venue was India, so Indian law governs.
Inder Chand Jain v. Pooran Chand Bansi Dhar, AIR 1959 Punjab 614 Explains how to determine whether the Court before which Ss.32 and 33 are filed has jurisdiction: ascertain subject matter of reference and whether part of cause of action arose within jurisdiction. The Court considered this headnote and analyzed facts (contract conclusion and correspondence in Delhi) to conclude that there was sufficient nexus for jurisdiction in Delhi.
Hari Shanker Lal v. Shambhu Nath, AIR 1962 SC 78 Section 28 permits the court to extend time for making award even after the award has been made; an award made before extension may be treated as made within extended time if the court later extends time. The Court relied on this authority to hold that time could be enlarged retrospectively and treated the award of 29-9-1969 as made within time when the Court exercised its discretion to enlarge time to that date.
Kanhayalal Dugar v. Askaran Kishanlal, AIR 1957 Cal. 658 Affirms the court's power under section 28 to extend time is discretionary and not limited; courts may preserve awards after expense and time expended where no meritorious objection is shown. The Court cited this case as persuasive authority in exercising its discretion to extend time, considering the long proceedings and absence of meritorious objection by petitioner.
Ram Sahai v. Babu Lal, AIR 1965 Allahabad 217; Seo Narain Lal v. Prabhu Chand, AIR 1958 Patna 262 (FB); Sait Pamandas Sagnaram v. T.S. Manikyam Pillai, AIR 1960 AP 59 (FB); O. Mohamed Yusuf Levai Saheb v. S. Hajee Mohammed Hussain Rowther, AIR 1964 Madras 1 (FB); Sardool Singh v. Hari Singh, AIR 1968 Punjab & Haryana 204 (FB) These decisions were cited for the proposition that an award not made a rule of Court may have no operative enforceability and cannot prejudice parties until it is made a decree. The Court acknowledged these decisions cited by petitioner but explained the Supreme Court later authoritative decisions (Uttam Singh Duggall and Satish Kumar) limit the proposition; thus it did not rely on them to invalidate the award.
M/s Uttam Singh Duggall v. Union of India, CA No.162 of 1962 (decided 11 Oct 1962) Held that after an award is pronounced, rights and liabilities of parties in respect of the claims can be determined on the basis of the award; an award, if regular, is conclusive on the merits unless impeached in appropriate proceedings. The Court treated this authority as decisive: an award possesses vitality and is final and binding on parties even if not yet made a rule of Court; applied to hold the award in question is final and binding.
Bhajabari Saha Banikya v. Behary Lad Basak, IL 33 Cal. 881 Passage quoted in Uttam Singh describing award as final adjudication of parties' choice and generally conclusive unless impeached. The Court quoted the Uttam Singh approval of this remark to support the proposition that an award has legal force and is not mere waste paper.
Satish Kumar v. Surinder Kumar & others, AIR 1970 SC 833 Held that an award has some legal force and is not mere waste paper; awards that are final and binding create rights though enforceability may require further steps. The Court relied on this Supreme Court authority to conclude that the award in this case is final and binding on the parties; enforcement in India still requires making it a decree of the Court.

Court's Reasoning and Analysis

The Court proceeded in a stepwise manner to address jurisdiction, applicable law, the timeliness of the award, and the award's legal effect:

  1. Applicable law and character of the award:

    The Court examined the contract (paragraph 18 of the letter of instructions) which expressly stated that "the contract will be governed by the laws of India" and the arbitration clause specifying New Delhi as the venue. Considering ICC Rules (notably Articles 7, 16, 18 and 27), the Court found that although some evidence was recorded in Paris at the respondent's request, the parties had agreed that such recording in Paris would not constitute a change of venue. The final arguments and the conduct of Lord Devlin occurred in India. The award was not shown to have been signed in Paris and, on balance, the award was to be treated as made in India. Therefore the Arbitration Act, 1940 applied.

  2. Applicability of the 1961 Act / New York Convention:

    The Court analyzed the New York Convention (the 1961 Act) and observed that Article 1 applies to awards not made in the territory where recognition/enforcement is sought. Here recognition was sought in France while the award was made in India; hence the 1961 Act (as domestic legislation) did not displace the Arbitration Act in India. The Court noted that the New York Convention might apply in French proceedings (for French authorities the award made in India is a foreign award), but that has no effect on the applicability of the Arbitration Act in India.

  3. Jurisdiction of the Delhi High Court:

    The Court considered the objection that Delhi lacked jurisdiction. It observed that section 120 of the Code of Civil Procedure excludes the applicability of section 20 of the CPC to the High Court in original civil jurisdiction, and that under the Delhi High Court Act there is wider original civil jurisdiction. The Court examined contract documents which showed the original tender was accepted by the respondent in Delhi by letter dated 10 October 1957 and final acceptance (with agreed revisions) was communicated from New Delhi dated 3 June 1958. The contract was therefore concluded at New Delhi and a part of the cause of action arose there. The Court concluded there existed sufficient nexus to entertain the petition.

  4. Whether the award was out of time and whether extension of time should be granted:

    The petitioner argued that Article 23 of the ICC Rules limited the time for making the award to 60 days from signing the statement of terms of reference and that the award dated 29 September 1969 was out of time. The petitioner relied on section 28(2) of the Arbitration Act to argue that enlarging time without consent was void. The respondent relied on ICC Rules and party conduct to justify time extension.

    The Court observed that section 28(1) grants the Court the power to enlarge time "if it thinks fit" whether the time has expired or not and that an extension can be given after the award has been made (citing Hari Shanker Lal). The Court weighed factual considerations: long and complex proceedings, voluminous material, active participation by the petitioner throughout, no evidence of respondent-caused delay, the petitioner having waived dates and continued participation, and the arbitrator's detailed 162-paragraph award. On these grounds and guided by discretionary principles in authorities such as Kanhayalal Dugar, the Court exercised its discretion to enlarge the time until 29 September 1969 (the date the award was made) and held the award was therefore made within the time allowed by law.

  5. Legal effect of an un-filed award:

    The petitioner contended an award not made a rule of Court is a nullity. The Court reviewed prior High Court decisions cited by the petitioner, but relied on Supreme Court authorities (Uttam Singh Duggall and Satish Kumar) which hold that an award, if regular and final, creates rights and is conclusive on the merits until impeached in appropriate proceedings; awards have legal force and are not mere waste paper, though enforcement in India may require further steps to make the award a decree of the Court. The Court therefore treated the award as final and binding on the parties, subject to the formal requirement that to enforce it in India it must be filed and made a rule of Court.

  6. Procedural formalities under ICC Rules:

    The petitioner suggested Article 26 approval by the Court of Arbitration may not have been completed. The Court treated such formalities as domestic procedure of the ICC and presumed they had been complied with, noting the award was communicated by the ICC Secretariat in accordance with Article 28.

Holding and Implications

Holding: The Court held that the award dated 29 September 1969 is final and binding on the parties. The Court exercised its discretion under section 28 and enlarged the time for making the award to 29 September 1969, thereby validating the award as made within the time allowed by law. The Court also held that the Indian Arbitration Act, 1940 applies to the award and that the application under section 33 is maintainable in this Court.

Implications:

  • The award is declared final and binding on the parties; it is not invalid for being made beyond time once the Court has enlarged time to the date of the award.
  • To enforce the award in India further steps will be required (i.e., filing and making the award a rule of the Court) if enforcement in India is sought; the award nevertheless creates rights and has legal force between the parties.
  • The New York Convention / 1961 Act (Foreign Awards Act) does not displace the Arbitration Act in India for an award made in India and where recognition/enforcement is being considered in Indian courts; the Convention may be relevant to foreign courts (e.g., France) where the award is treated as a foreign award.
  • The Court disposed of O.H.P. 98/70 (the respondent's application for enlarging time) by granting the extension to 29-9-1969. There was no order as to costs in the circumstances of the case.
  • No broader pronouncement displacing prior Supreme Court authorities was made; the decision applies the Arbitration Act and Supreme Court authorities to the facts before the Court.

Order: The Court ordered accordingly and disposed of the respondent's application for enlargement of time.

    Compagnie De Saint Gobain Petitioner v. Fertilizer Corporation Of India Ltd.

    P.N Khanna, J.:— The petitioner-company, Compagnie de Saint Gobain, is a company incorporated under the laws of France with its registered office in Paris. It entered into a contract with Nangal Fertilizer Chemicals Private Limited, the predecessor-in-interest of the present respondent, Fertilizer Corporation of India Limited, which is a Government Company registered under the Companies Act, 1956 having its registered office in New Delhi, for the construction of Nangal Fertilizer group of plants. The contract was contained in a letter dated October 10, 1957, issued by the said respondent-company called “letter of instructions”, which was followed by some subsequent correspondence between the parties. In arbitration clause (para 23) in the said letter read as follows :

    “Except as otherwise provided, all disputes and differences between the purchaser (the respondent) and yourselves (the petitioner) shall be settled by amicable arbitration in confirmity with regulations of the International Chamber of Commerce. The venue of arbitration shall be New Delhi in India.”
    Certain disputes having arisen between the parties, the petitioner on June 19, 1964 made an arbitral request to the Court of the International Chamber of Commerce, Paris, for the adjudication of its claim made up of Dollars and rupees in all amounting to Rs. 1,52,40,401.67. The respondent company contested the petitioner's claim; and filed a counter-claim made up of dollars and rupees amounting in all to Rs. 2,70,18,167.00 or alternatively Rs. 1,58,28,803.00, which, however, was disputed by the petitioner.
    In accordance with the rules of the International Chamber of Commerce, Paris, herein referred to as ‘ICC Rules’, the Court of Arbitration, of the said Chamber herein referred to as ‘the Court of Arbitration’, constituted an arbitral tribunal consisting of Mr. Sverre Daelhi, former Judge of the High Court of Norway, as the Chairman, Professor B. Goldman, nominee of the petitioner-company, and Mr. K.K Shende, nominee of the respondent-company, as the two other members.
    The said Tribunal held its first three sittings in New Delhi and drew its terms of reference (issues in the case) which were agreed to by the parties and approved by the Court of Arbitration in accordance with Article 19 of the Said ICC Rules. Sittings of the Tribunal were then held in Paris for recording evidence for some of the petitioner's witnesses. Further sittings were held from time to time in New Delhi and finally in Mussourie (India). After the arguments on the counter-claim were concluded, Mr. Sverre Daelhi resigned on November 28, 1967, Rt. Hon'ble Lord Devlin of England was appointed in his stead as the Chairman of the Tribunal. On October 11, 1968 Mr. K.K Shende, a member of the Tribunal, died. A protocol was signed between the parties agreeing that notwithstanding the death of Mr. Shende the arbitration would continue and that the decision recorded by him before his death and sent to the Court of Arbitration would be taken on record. Professor B. Goldmen was requested to record his decision also in writing; and Lord Devlin was requested to make the award. Lord Devlin heard arguments of the parties in Delhi from 14th to 25th April, 1969. A further protocol was signed by the parties on April 25, 1969, specifically agreeing that Lord Devlin shall have jurisdiction to give his final award, thus constituting him the sole arbitrator.
    Lord Devlin submitted his award dated September 29, 1969 to the Court of Arbitration which was communicated from Paris, to the parties by the Secretary General of the said court, by his letter dated October 16, 1969. According to it a sum of Dollars 179,438 and Rs. 56,65,978.00 were awarded in favour of the respondent-Corporation against the petitioner. As the award amount was not paid and the petitioners did not have any property in India, the respondent took out execution of the award through the French Court. Certain bank accounts and trade-marks of the petitioner were attached. On the petitioner challenging the said attachment, the French Court ordered it to furnish bank guarantees instead, which were furnished.
    Another proceeding was filed by the petitioner in the French Court seeking vacation of the order of execution. While this was pending, the present application was filed in this court under section 33 of the Arbitration Act, praying for an order declaring that the aforesaid award of Lord Devlin had no legal effect or existence and was not enforceable or in the alternative for the suspension of the award till it was filed and made a rule of the Court under the Arbitration Act, 1940. According to the petitioner's allegations, the present award becomes enforceable under the French law, in accordance with Article V(1)(e) of the “New York Convention of the year 1958 on the Recognition and Enforcement of Foreign Arbitral Awards”, by an order of the President of the Civil Court, without an enquiry into the merits of the case, if the award has become binding on the parties or has not been set aside or suspended by a competent authority of the country in which or under the law of which the award was made. The petitioners apprehended that the respondent would take advantage of the jurisdiction of the French Civil Court in enforcing the award without the same being made a rule of the Court. It was for this reason that the petitioner considered it necessary to move this court under section 33 of the Arbitration Act, 1940, for adjudicating upon the validity and the effect of the said award.
    The award, it has been stated in the petition, is a nullity on the following grounds:
    (1) That it is made out of time and after the arbitration became functus officio;
    (2) That the award has not been filed in the Court as required by the Arbitration Act, and is, therefore, a nullity;
    (3) That it is not enforceable because the amounts due under the Award have not been finally determined;
    (4) That it deals with matters in respect of which there is no arbitration agreement or a reference.
    The learned counsel for the petitioner did not elaborate ground No. (3) at all and stated at the bar that he would not press, for the present, the fourth ground. He confined his challenge to the award on the first two grounds only.
    An objection was raised by Mr. B. Sen, the learned counsel for the respondent, that the award was not governed by the Indian law and the Arbitration Act, X of 1940 was not applicable. The French Courts, it was further submitted, having already executed the award and dismissed the petitioner's application, this court should not decide this application in order to avoid a possible conflict of decisions, more especially as under the orders of the Paris Court the respondent has already received the amount of its claim granted to it under the award in as much as the Bank guarantees furnished by the petitioner are available to it and can be enforced at its will at any time without resort to any further proceedings in court. In respect of the first objection Mr. Sen relied upon Articles 26, 27 and 28 of the ICC Rules, which read as follows :
    “Article 26—Award to be passed by the Court of Arbitration. Before completing the award, the arbitrator shall submit the same to the Court of Arbitration. The Court may lay down modifications as to its form and if need be, draw the arbitrator's attention even to points connected with the merits of the case but with due regard to the arbitrator's liberty of decision. No award shall under any circumstances be issued until approved as to its form by the court of Arbitration.
    Article 27 :—Pronouncement of the award. The arbitral award shall be deemed to be made at the place of arbitration proceedings and on the date of signature by the arbitrator.
    Article 28 :—Notifing the parties of the award. 1. When the award has been made, the Secretariat shall communicate the arbitrator's signed text to the parties, provided the arbitration costs have been fully paid to the International Chamber of Commerce by the parties or by one of them.
    2. × × × × × × × ×
    According to Mr. Sen, the Court of Arbitration is the final authority, whose approval is a condition precedent to the completion of the award, which is issued by the Secretariat of the Chamber from Paris. The award is actually made thus out of India, although a deeming provision has been made in Article 27 whereby the award is deemed to be made at the place of arbitration proceedings. In the present case, the place of arbitration proceedings was agreed to be in India in the first instance, New Delhi having been specifically mentioned to be the venue of arbitration proceedings. By mutual consent, the parties agreed subsequently that the proceedings shall take place in New Delhi, Paris and Mussourie (India). It could not, therefore, be said that India is the only place where the arbitration proceedings took place. The arbitration proceedings also took place in Paris and as the award was fact made in Paris, the deeming provision in Article 27 would not make any difference. For the Indian Courts, the award urged Mr. Sen, would remain a foreign award. He relied on M/s Lachman Das Sat Lal and another v. Parmeshri Dass and another, AIR 1958 Punjab 258(1), where it was held that the award made and signed at Karachi was a foreign award. Mr. Sen also submitted that the scheme of the Arbitration Act was entirely different from the scheme contemplated under the ICC Rules and for the proposition he relied upon the judgment of the Supreme Court in Societe De Traction et D’ Electricite Societe Anonyme v. Kamani Engineering Company Ltd. (1964) 3 SCR 116(2) where commenting on the ICC Rules, it was observed that “the scheme of arbitration contemplated by these Rules 18 different from the scheme contemplated by ss. 3 to 38 of the Arbitration Act”. In these circumstances, the learned counsel submitted that application under section 33 of the Arbitration Act was misconceived and untenable. The arguments of Mr. Sen, however, rest on a faulty premise. His contention that the award was made outside India and is not governed by the indian arbitration act has no basis.
    Para 18 of the letter of instructions specifically provides that “the contract will be governed by the laws of India”. The arbitration clause in para 23 of the said letter states that “the venue of all arbitration shall be New Delhi in India”. Article 7 of the ICC Rules provides that the Court of Arbitration does not by itself settle disputes. It appoints and confirms the nomination of arbitrators. Although the Court of Arbitration, Paris, has to approve the form of the award before it is completed, the award nonetheless remains that of the arbitrator, whose liberty of decision is not prejudiced. According to Article 16, the arbitration proceedings are governed by the ICC Rules and in the event of no provision in the rules, those of the law of procedure chosen by the parties, or failing such choice, those of the law of the country in which the arbitrator holds the proceedings. Article 18 provides that the proceedings before the arbitrator shall take place in the country determined by the Court of Arbitration unless the parties shall have agreed in advance upon the place of arbitration, which in the present case was agreed to be India. According to Article 27, the arbitral award shall be deemed to be made at the place of the arbitration proceedings, and on the date of signature by the arbitrator.
    It is not disputed that before the nomination of Lord Devlin, as the sole arbitrator, the arbitration proceedings took place in New Delhi and Mussourie. Evidence of some of the petitioner's witnesses was recorded in Paris also; but this was done at the request of the respondent, who in their application for the purpose, expressly stated that “in the event of the Tribunal itself recording the evidence in Paris, it is to be understood that such an act will not constitute a change of venue of the arbitration proceedings, which is at New Delhi, according to the Tribunal by its order dated April 14, 1965 observed: “Since the parties have now consented to record the evidence of their witnesses by the Tribunal itself in Paris, on the condition that by itself it shall not imply a change of venue of the proceedings, we hereby modify our first order of recording the evidence in Paris on commission or letter of request and decide to record such evidence by the Tribunal itself”. The venue of arbitration, therefore, remained in India. The final arguments in any case were heard in India. So far as Lord Devlin, who was ultimately agreed to be the sole arbitrator, is concerned, he conducted the entire proceedings in India only. The award itself does not a appear to have been signed in Paris and must be presumed to have been made in India. It was accordingly an Indian award to which the provisions of the indian Arbitration Act, 1940 apply.
    Section 47 of the Arbitration Act, 1940 reads as follows :
    “Subject to the provisions of section 46 and save in so far as is otherwise provided by any law for the time being in force, the provisions of this Act shall apply to all arbitrations and to all proceedings thereunder.
    Provided that an arbitration award otherwise obtained may with the consent of all the parties interested be adjust into consideration as a compromise or adjustment of a suit by any court before which the suit is pending.”
    The provisions of section 46 have no relevancy for our present purposes. The Act, therefore, applies to all arbitrations, of whatsoever nature and all proceedings thereunder save as is otherwise provided by the law for the time being in force. Unless, therefore, any law provides otherwise, the Arbitration Act, 1940 will govern the arbitration in this case.
    According to Mr. Sen, the award of Lord Devlin is governed by the Arbitration (Protocol & Convention) Act, 1937, herein called ‘the 1937 Act,’ or by the Foreign Awards (Recognition & Enforcement) Act, 1961, herein called the 1961 Act’, and that these are the laws which provide otherwise. These two enactments which are more or less analogous in terms were passed by the Indian Legislature to give effect to certain International Protocols and Conventions, framed to meet the widely expressed desire in the commercial circles throughout the world to accord recognition and protection to arbitration agreements and awards. The first was the Geneva Protocol of Arbitration Clauses (1923) and the International Convention on the Execution of the Foreign Arbitral Awards (1937). These were signed at Geneva on behalf of India subject to certain reservations limiting India's obligation under the instruments to commercial contracts. For the purpose of giving effect to this protocol and for enabling the said Convention to become operative in India the 1937 Act was passed. On June 10, 1958, came the Convention on the Recognition & Enforcement of Foreign Arbitral Awards, at New York, to which India was a party. In order to give effect to the New York Convention the 1961 Act was passed. According to the definition of ‘foreign award’ given in section 2 of the 1961 Act it means an award made on or after 11th day of October, 1967. According to section 10 the aforesaid 1937 act ceased to have effect in relation to Foreign Awards to which the said 1961 Act applied. The award in the present case having been made on September 29, 1969 the 19 act would, if applicable, be the only relevant provision, requiring attention to see if it provides otherwise than as provided in the arbitration Act, 150.
    Turning to the New York Convention, given in the Schedule to the 1961 Act, it is plain that it applies according to its Article 1, to such arbitral awards, only, which are not made in the territory of a State, where the recognition and enforcement of such awards are sought. In the present case, the award, having been made in India, its recognition and enforcement were sought not in India, but in France. The Convention under the Indian law would be applicable only if the award was not made in India and its recognition and enforcement were sought here. This not being the case, the New York Convention in the Schedule to the 1961 Act has no application to this award in India. The New York Convention may be applicable to this very award in France, as for the purpose of Courts in France, it having been made in India, is a foreign award. This petition was accepted by the Paris Court, as appears from annexure ‘A’ filed by the respondent along with its sub-rejoinder, which is a translation of the order of the First Vice-President of the French Court, on the petitioner's application for cancellation of the attachment of its Bank accounts. It is mentioned in the said court order that the award was made in India and that the parties were in agreement on the applicability of the New York Convention of June 10, 1958. The award was thus recognised in Paris, to be an award made in India and thus a foreign award.
    The 1961 Act under the circumstances, has no application. There being no other law in force, which provides otherwise, the Arbitration Act 1940 remains applicable to the award of Lord Devlin. The 1961 Act, even if it was applicable, contains no provisions for declaring the effect validity or the existence of an award. Even Article V(i)(e) of the Convention given in the Schedule to the 1961 Act provides that the award has to be set aside or superseded, if so required, by a competent authority of the country, in which or under the law of which, that was made. The matters for which there is no provision in the 1961 Act or the Convention, have thus to be dealt with by the ordinary law of the land under the law of which the award was made. The provisions of section 33 of the Arbitration Act, therefore, are not ousted under any circumstance.
    In Kamani's case (1964) 3 SCR 116(), relied upon by Mr. Sen the Supreme Court had no occasion to go into the question of the applicability of the 1937 Act, as it was not disputed that the proposed arbitration under the Rules of the International Chamber of Commerce was governed by the Protocol on Arbitration Clauses agreed to at Jeneva on September 24, 1923; and the Protocol in the First Schedule given in the 1937 Act, passed to give effect to the same, was applicable regarding the applicability of the Arbitration Act, 1940, it was observed by the Supreme Court in that case that section 47 of the Arbitration Act made the provisions of the Arbitration Act applicable to all arbitrations and to all proceedings subject, however, to the provisions of section 46 and so far as was otherwise provided in law for the time being in force. Under this section, therefore, the court was of the view that “the legislature has clearly made the provisions of the Arbitration (Protocol & Convention) Act, 1937 applicable to consensual arbitration, under the Arbitration Act, 1940, when the conditions prescribed for the application of that Act are attracted, even if the scheme of Arbitration recognised thereby is inconsistent with sections 3 to 38 of the Arbitration Act, 1940”. It was only by virtue of the applicability of the Arbitration Act, 1940 itself that the 1937 Act was held to apply to the proceedings under the ICC Rules, which was admitted to be otherwise applicable in the circumstances of that case.
    In M/s Lachman Das Sat Lal's (AIR 1958 Punjab 258)(), also relied upon by Mr. Sen, a Bench of the Punjab High Court consisting of Bishan Narain J. and A.N Grover J. (as he then was), was of the view that it was open to the parties “to agree that any dispute arising between them shall be submitted to arbitration at any place and in any particular country in any part of the world”. As arbitration proceedings in that case took place in Karachi in pursuance of the arbitration agreement, the award was made and signed at Karachi, it was held that the said award was a foreign award. According to the ratio of that decision, it is the intention of the parties, which determined the place or the country where the proceedings are to take place and consequently the award is to be made. The Supreme Court applying Indian law in M/s Dhanrajmal Gobindram v. M/s Shamji Kalidas & Co. (1961) 3 SCR 1020 (3), observed : “Whether the proper law is the lex loci contractus or lex loci solutionis is a matter of presumption; but there are accepted rules for determining which of them is applicable. Where the parties have expressed themselves, the intention so expressed overrides any presumption. Where there is no expressed intention, then the rule to apply is to infer the intention from the terms and nature of the contract and from the general circumstances of the case. In the present case, two such circumstances are decisive. The first is that the parties have agreed that in case of dispute the Bombay High Court would have jurisdiction……………If Courts of a particular country are chosen, it is expected, unless there be either expressed intention or evidence, that they would apply in their own law to the case………. The second circumstance is that the arbitration clause indicated an arbitration in India. Of such arbitration clause in agreements, it has been said on more than one occasion that they lead to an inference that the parties have adopted the law of the country in which arbitration is to be made.” In the case before me, the parties had expressly agreed, in para 18 of the letter of instructions, as stated above, that “the contract will be governed by the laws of India”. The proceedings took place in India. It is, therefore, a clear case governed by Indian Laws. The Arbitration Act is not excluded by the 1961 Act, or by any other law. The objection of Mr. Sen, therefore, has no merit. It is an Indian award governed by the Arbitration Act, 1940 and the present application under section 33 of the Act is maintainable.
    The other objection of Mr. Sen that the courts in Paris being seized of the matter, the courts in India should not entertain the present application, is equally devoid of force. The Court in Paris, being the court of a country, the laws of which do not apply to this award, will not determine the existence, validity or effect of this award. They on the other hand, will recognise and enforce the award under the new York Convention, unless the petitioner can establish that the award is not binding on the parties, or has been set aside or suspended by a competent court in India; vide sub-clause (c) of clause (1) of article V of the New York Convention. The courts in India alone are competent to decide the application under section 33 of the Arbitration Act filed on behalf of the petitioner-company; and the question of a conflict of the decision in India with that in Paris does not arise.
    Another objection was raised by Mr. Sen that this court has no jurisdiction to entertain this application even if an application under section 33 of the Arbitration Act, 1940 is competent. According to him, all questions relating to the validity effect or existence of an award or an arbitration agreement between the parties to the agreement, have to be decided under section 31(2) of the Arbitration Act, 1940, by the court in which the award may be filed and by no other court. According to section 31(1) of the said Act, an award can be filed in any court having jurisdiction in the matter to which the reference relates. According to section 2(c) of the Act, ‘Court’ means a civil court having jurisdiction to decide the questions forming the subject matter of the reference, if the same had been the subject matter of a suit. The learned counsel submitted that the matter in controversy between the parties relates to a turnkey job for the construction of Nangal Fertilizer Group of Plants, at Nangal, which is beyond the Union Territory of Delhi. The subject matter of the dispute, according to him, is not within the jurisdiction of this court. From the language of section 2(c) and section 31(1) of the Arbitration Act, the jurisdiction according to the learned counsel, has been made dependent not upon the residence or place of business of the parties; but on the subject-matter of the reference. Under the circumstances, the learned counsel submitted, this court has no jurisdiction to entertain the present petition. He relied on Inder Chand Jain v. Pooran Chand Bansi Dhar, AIR 1959 Punjab 614(4), where the head-note reads as follows :
    “In order to determine the question whether the Court before which applications under Ss. 32 and 33 are filed has jurisdiction to entertain them, it must be ascertained what the questions are, which form the subject matter of the reference to arbitration and then supposing those questions bad arisen in a suit, which is the court which would have jurisdiction to entertain the suit, whether in fact any part of the cause of action in the suit, which the opposite party might have instituted arising out of the subject matter of reference arose within the jurisdiction of the court before which the applications are filed.”
    Mr. Sen submitted that the question of residence or place of business of the respondent mentioned in sub-sections (a) or (b) of section 20 of the Code of Civil Procedure, has no relevance for the present purposes. It is the cause of action arising in whole or in part referred to sub-clause (c) of that section, which would be the determining factor. As no part of the cause of action has arisen in Delhi in the present case, there is no matter to which the reference relates over which this court has jurisdiction.
    It may, however, be observed that section 120 of the Code of Civil Procedure specifically excludes the applicability of section 20 of the High Court in the exercise of its original civil jurisdiction. In other words, the scope of the jurisdiction of the High Court on its original side is not dependent merely on the cause action in the case. The jurisdiction appears to be much wider. Sub-section (2) of section 5 of the Delhi High Court Act, 1966 lays down that notwithstanding anything contained in any law for the time being in force, the High Court of Delhi shall also have in respect of the said Territories (Territories for the time being included in the Union Territory of Delhi), ordinary original civil jurisdiction in every suit the value of which exceeds Rs. 50,000/-. This would mean that the Delhi High Court would have jurisdiction in the matter to which the reference relates, if it has some nexus with the said territories. The residence or place of business in the Union Territory of Delhi of the respondent or defendant in a case dealing with the matter to which the reference relates, coupled with the fact that the entire correspondence dealing with such matter took place with the Delhi office alone, would be a sufficient nexus of such kind to give jurisdiction to this court. The jurisdiction is not because of the residence or of the location of the place of business of the respondent, but because of the subject matter of the reference which has a nexus or connection with the territory concerned through such residence or the location of the place of business of the respondent and because of the entire material correspondence having taken place with the Delhi office. But, this question need not detain our attention any further, as Mr. Pai at the end of his arguments, filed contract documents, which show that the original tender submitted by the petitioner was accepted by the respondent by its letter dated October 10, 1957, in Delhi. The petitioner, however, was requested to intimate its acceptance of the terms and conditions set out therein. The petitioner in reply, while conveying its acceptance suggested a revision of certain terms in some foot-notes and asked for its acceptance by the respondent. There appears to have followed some correspondence intended to clarify certain terms of the contract. The last letter was dated June, 3, 1958, written by the respondent from New Delhi, whereby it conveyed its agreement to the revised text of the foot-note which had been submitted to it by the petitioner. This letter was thus the final acceptance in New Delhi of the terms of the contract. The contract, therefore, was concluded at New Delhi. A part of the subject matter of the reference matured and, therefore, a part of the cause of action arose in New Delhi. There does exist sufficient nexus, under the circumstances, between the subject matter to which the reference relates and the Union Territory of Delhi. This court, therefore, has jurisdiction to entertain the present application and the objection of Mr. Sen is not tenable.
    Dealing with his contention that the award was a nullity, Mr. Pai submitted that the arbitrator had become functus officio when he made his award dated September 29, 1969. The time limit under Article 23 of the I.C.C Rules within which the award could be made, was 60 days from the date on which he signed the statement defining his terms of reference. The arbitrator could be deemed to have done this latest by April 25, 1969, while he made his award on September 29, 1969, along after the said sixty days had expired. Extensions granted by the court of Arbitration relied upon by Mr. Sen, are of no consequence, submitted Mr. Pai, in view of sub-section (2) of section 28 of the Arbitration Act, which reads as follows:
    “Any provision in an arbitration agreement whereby the arbitrators or umpire may, except with the consent of all the parties to the agreement, enlarge the time for making the award, shall be void and of no effect.”
    According to him, the court of arbitration and the arbitrator are parts of the same arbitration scheme; and the order of the court of arbitration enlarging the time for making the award can be taken as the order of the arbitrator; but this being without the consent of the parties was void and of no effect in view of section 28(2) of the Arbitration Act. Even if the Court of Arbitration was taken to be independent of and separate from the arbitrator, the enlargement of time, which is the function of the court under section 28(2) of the Arbitration Act, cannot be granted by a person acquiring authority for such purpose by agreement of the parties as that would be hit by section 28 of the Contract Act, being an agreement in restraint of legal proceedings. It is, however, not necessary to enter into this discussion as under section 28(1), “the Court may, if it thinks fit, whether the time for making the award has expired or not and whether the award has been made or not, enlarge from time to time, the time for making the award.” The court, it will be seen, has suo motu power to move in the matter. An application was, however, made at the end of arguments on behalf of the respondent, praying for suitable extension of time for making the award up to the day on which the said award was made. It is not disputed that time can be extended even after the award has been made. Subba Rao J. of the Supreme Court speaking for himself and B.P Sinha C.J and Madholkar J. in the case of Hari Shanker Lal v. Shambhu Nath, AIR 1962 SC 78(5), observed : “Section 28 of the Act enables the court to extend the time for making of the award; extension of time may be given even after the award has been factually made. So till the time is extended an award cannot be made, though, when extended, the award factually made may be treated as an award made within the time so extended. To put it differently, if time was not extended by court, the document described as an award would be treated as non est.”
    Mr Pai submitted that the discretion of the court should not be exercised in favour of enlarging the time as prayed in this case, as that would be unfair to the petitioner. His request to the arbitrator to file the award in court was not acceded to. He, therefore, had no opportunity to file objections to it. The award being out of time is non est, as was held by the Supreme Court in Hari Shanker Lal's case (AIR 1962 SC 78). The petitioner in the bona fide belief that the award is a nullity took no further steps to have the award filed in court to enable it to file objections under section 30, Arbitration Act. Now, the time for the petitioner to make an application in court under section 14 of the Arbitration Act, has expired, and if the time is enlarged by the court, the petitioner may be faced with difficulty in filing objections and may be highly prejudiced. The enlargement of time is a matter of discretion which should not be exercised in the respondent's favour in view of the above circumstances, submitted Mr. Pai.
    It was urged on behalf of the respondent that the award was made within the time allowed by the Court of Arbitration in accordance with ICC Rules, agreed upon by the parties, as governing the arbitration. The award, was, thus, made in time as extended in accordance with the agreement of the parties, it was at their specific request that the arbitrator after conclusion of the argument proceeded to make the award. The petitioner had all along been participating in the arbitration proceedings which started in 1964 or 1965; and never questioned the arbitratior's power to proceed, although the enlargement of time had not been granted by the Court. The dates for proceeding in the case were being fixed from time to time, admittedly by the consent of the parties. The proceedings had dragged on over several years and the parties had incurred considerable time and expense. The court should exercise its discretion for enlarging time as prayed, urged the learned counsel.
    The contentions of Mr. Sen are not without force. There was voluminous documentary material, oral evidence and various other complicated issues which had to be tackled. The arbitrator had spent considerable thought over the matter and had written a well considered award supported by a statement of reasons, running into 162 paragraphs and a resume of the arbitrator's findings. The delay in writing the award therefore, is not unreasonable. The respondent has not been shown to have delayed or hampered the proceedings. Nor does it appear in any manner to be responsible for the delay in the making of the award. The petitioner, in fact, participated in the proceedings throughout; and always waived objections to further dates being fixed even though the proceedings had continued over serveral years. Even when Mr. K.K Shende, one of the arbitrators died, the parties had expressed their keenness to see the arbitration through. The petitioner thus took a chance of a decision favourable to it. And now when the award has gone against it, its objection to the enlargement of time are wholly unjustified. Its non-filing of an application under section 14, Arbitration Act earlier, for filing of the award in court has no relevance for the present purposes. The petitioner itself knew as stated in para 19 of the petition that under the French law the award is much exercisable by order of the court without enquiring in the merits of the case, if the award has become binding and has not been set aside by a competent authority of the court in which or under the law of which the award was made. It is the petitioner's case that the award was made in India under the Indian law. It was, therefore, for the petitioners to take timely steps to have the award declared a nullity, it thought it was so, more especially as it was aware that could be enlarged by the court even after the award had been made. The petitioner not having moved the court under section 14, earlier cannot plead its own neglect, for invoking the exercise of court's discretion against the grant of time. The petitioner has now filed an independent application under section 14, Arbitration Act, in respect of which nothing said in this judgment, will have any effect; nor should it be taken as an expression of opinion affecting that application. The said application shall be tried on its own merits, and the petitioner will be granted appropriate relief, if found entitled to any. But, that has no relevance for the purpose of extending or not extending time for making the award.
    Mr. Pai submitted that the time should not be enlarged in this case also because the petitioner has very serious objections to the award on merits. But it was for the arbitrator to decide the merits of the case; and in case the court can go into the award under section 30 of the Arbitration Act after its being filed in court, the petitioner will have an opportunity to urge its objections, after its application under section 14 is granted and the award is allowed to be filed in court. Without the award being before the court, nothing can be said about the petitioner's objections on the merits.
    The learned counsel have cited a number of judgments for and against the grant of the prayer for enlargement of time; but all of them are based on the fact of each individual case. There can be no doubt that the enlargement of time for making the award is entirely within the discretion of the court. In Kanhayalal Dugar v. Askaran Kishanlal, AIR 1957 Cal. 658(6), it was observed that the court's power under section 28 to extend time are entirely discretionary and are not limited. The court can enlarge time for making the award even after the award has been made and even after the time has expired. It was also held that one of the persuasive consideration before the court would be, “that after all the time, expense and trouble in going into arbitration and actually having the award, regarding which there is no meritorious objection, it is proper to enlarge the time and make the award, the fruit of so much time, labour and expense, effective and not to frustrate it by refusing time.” Looking to all the facts and circumstance stated above, I am satisfied that it is a fit case where time for making the award should be extended. I, therefore, enlarge the time until 29-9-1969, the date on which the award was made in this case. The award was, therefore, made within the time allowed by law; and is not invalid on the ground of being made beyond time.
    Coming to the merits of the case, Mr. G.B Pai the learned counsel for the petitioner-company submitted that an award, which has not been made a rule of the court and has not become a decree of the court, is a nullity and as such has no existence in law and remains a dead letter. The learned counsel cited a number of decisions of various courts, viz. Ram Sahai v. Babu Lal, AIR 1965 Allahabad 217(7), Seo Narain Lal v. Prabhu Chand, AIR 1958 Patna 262 (FB)(8), Sait Pamandas Sagnaram v. T.S Manikyam Pillai, AIR 1960 AP 59 (FB)(9), O. Mohamed Yusuf Levai Saheb v. S. Hajee Mohammed Hussain Rowther, AIR 1964 Madras 1 (FB),(10) and Sardool Singh v. Hari Singh, AIR 1968 Punjab & Haryana 204 (FB)(11). In all these cases was held that no party can be prejudiced by the mere existence of an award, which does not become operative and enforceable until it has been filed in court and the court adjudicating upon its validity passes a judgment and a decree in accordance therewith.
    It is not necessary to go into the merits of the aforesaid decisions, as this question was considered by the Supreme Court in M/s Uttam Singh Duggall v. Union of India, CA 162 of 1962 authoritatively decided on 11th October, 1962(12). It was held that “after an award has been pronounced, the rights and liabilities of the parties in respect of the said claims can be determined only on the basis of the said award. After an award is pronounced, no action can be started on the original claim which had been the subject matter of the reference. The court approvingly quoted from the observation of Mookerjee J. of the Calcutta High Court in the case of Bhajabari Saha Banikya v. Behary Lad Basak; IL 33 Cal. 881, at 888(13), as follows: “The award is in fact, a final adjudication of a court of the parties own choice, and until impeached upon sufficient grounds in an appropriate proceedings, an award, which is on the face of it regular is conclusive upon the merits of the controversy submitted, unless possibly the parties have intended that the award shall not be final and conclusive………in reality, an award possess all the elements of vitality even though it has not been formally enforced and it may be relied upon in a litigation between the parties relating to the same subject matter”. This view was approved and affirmed by the Supreme Court in Satish Kumar v. Surinder Kumar & others; AIR 1970 SC 833(14). It was held that an award has some legal force and is not a mere waste paper. Further, if the award is final and binding on the parties, it can hardly be said that it is a waste paper, unless it is made a rule of the court. Mr. Justice Hegde, in a separate judgment, agreeing with the majority, observed that “the award does create rights in that property, but those rights cannot be enforced until the award is made a decree of the Court”. The award under consideration, thus creates rights and is final and, therefore, binding; although in case it is sought to be enforced in India, some further steps may be required to be taken for that purpose.
    Mr. Pai submitted that the award in the present case was not final as it was signed and completed by Lord Devlin before submitting it to the Court of Arbitration. According to Article 26 of the ICC Rules, the award is required to be approved by the Court of Arbitration before it can be completed by the arbitrator. This according to the learned counsel appears not to have been done. But, the award was admittedly communicated to the parties by the Secretariat of the International Chamber of Commerce, in accordance with Article 28 of the ICC Rules. The formalities required under Article 26 being matters of domestic procedure, must be presumed to have been fully complied with. The objection of the learned counsel, therefore, has no force.
    Mr. Pai also referred to Article 29 of the ICC Rules and submitted that the arbitral award is stated to be final; but nothing is stated about its binding effect. This article being a specific provision in the contract between the parties, indicates, according to him, an intention of the parties different from para 7 of the first Schedule of the Arbitration Act, which would have made the award not only final but binding also. But, section 3 of the Arbitration Act applies the provisions set out in the first Schedule to every arbitration agreement, unless a different intention is expressed. Nothing having been said about its binding nature, the award would become binding under the provision to that effect in clause 7 of the first Schedule. Further, sub-clause (2) of Article 29 says that the parties undertake to carry out the award without delay, showing thereby the unmistakable intention of the parties to remain bound by the award. If the award is final, it implies that the award is binding on the parties; and the contentions of Mr. Pai to the contrary has no basis.
    In the result, the award dated 29th September, 1969 of Lord Devlin, is declared to be final and binding on the parties; although further steps may be required to be taken to make it a decree of the court, if it is sought to be enforced in India. In the circumstances of this case, there will be no order as to costs. This will dispose of O.H.P 98/70 filed by the respondent for enlarging time for making the award.
    A.B.S Order accordingly.
    Use AI to get other relevant cases.

    Comments

    Compagnie De Saint Gobain Petitioner v. Fertilizer Corporation Of India Ltd.
    (Aug 28, 1970)