Case Number
Advocates
Judges
Acts
  • SECTION 5 LIMITATION ACT
  • Financial Institutions Act, 1993
  • Act, 1963, Section 5 Condonation
  • Section 85. 13 Mad 269, Approved.
  • P.C (5 of 1908), Order 9, Rule 13
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • SECTION 5 LIMITATION ACT
  • Financial Institutions Act, 1993
  • Act, 1963, Section 5 Condonation
  • Section 85. 13 Mad 269, Approved.
  • P.C (5 of 1908), Order 9, Rule 13
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

The writ petitioners are defendants in O.A. No. 1774 of 1998 before the Debts Recovery Tribunal (DRT), Chennai. The first respondent (a Bank) filed O.A. No. 1774 of 1998 seeking recovery of Rs. 20,71,776/- with interest and sale of the schedule property. An ex parte order was passed by the DRT on 8-4-1999 declaring the Bank entitled to a Recovery Certificate against defendants 1 to 4 for Rs. 20,71,776/- with 12% simple interest from the date of application and directing issuance of a Recovery Certificate.

The petitioners subsequently filed various applications to set aside the ex parte order and to restore applications that had been dismissed for non-prosecution. In particular, M.A. Nos. 338 and 339 of 2002 (to condone delay and stay operation) were dismissed for non-prosecution; M.A.SR Nos. 1274 and 1277 of 2006 were filed to condone a delay of 1006 days in restoring those M.A.s but were dismissed by the DRT on 11-10-2006. The petitioners appealed to the Debt Recovery Appellate Tribunal (DRAT), Chennai; in M.A. Nos. 205 and 206 of 2006 the DRAT dismissed the appeals by common order dated 10-5-2007.

The present writ petition seeks issuance of a writ of certiorari and mandamus to call for and quash the DRAT order dated 10-5-2007 in M.A. Nos. 205 & 206 of 2006 and, consequentially, to prevent confirmation of the auction held on 11-10-2006 in DRT No. 103 of 1999. The record shows that a third party was the successful bidder at public auction for Rs. 29,10,000/- and a sale certificate was issued in her favour on 13-03-2007.

Legal Issues Presented

  1. Whether the DRAT's common order dated 10-5-2007 dismissing M.A. Nos. 205 and 206 of 2006 (which arose from the DRT's dismissal of M.A.SR Nos. 1274 and 1277 of 2006) is vitiated by failure to apply principles of natural justice and by incorrect refusal to condone a delay of 1006 days.
  2. Whether the delay of 1006 days in filing the applications to restore M.A. Nos. 338 and 339 of 2002 should be condoned in the interest of substantial justice.
  3. Whether the writ petitioners should be permitted an opportunity to contest the recovery proceedings and to settle the Bank's claim despite prior ex parte orders and auction steps.

Arguments of the Parties

Writ Petitioners / Appellants / Defendants

  • They contended that the DRAT's common order dated 10-5-2007 dismissing the appeals violated established principles of natural justice.
  • They argued that the DRAT failed to consider that one of the guarantors is a senior lady citizen and that the property concerned belongs to her, and that she (and others) were willing and ready to settle the matter.
  • They submitted that a sum of Rs. 10,00,000/- (and later the record mentions Rs. 15 lakhs already paid) had been deposited with the Bank but this fact was not reflected in the DRAT's order.
  • They maintained that the circumstances leading to the ex parte decree of 8-4-1999 were not properly considered by DRAT and DRT, and therefore the delay of 1006 days in filing applications to restore prior M.A.s should have been condoned.
  • They stated specific factual reasons for delay, including the second petitioner being the managing partner engaged in business and frequently moving, which affected prompt steps to prosecute restoration applications; they also expressed readiness to settle and offered to pay costs (in court, they offered to pay Rs. 25,000/- as a condition of being allowed to prove the case on merits).

The opinion does not contain a detailed account of the Bank's legal arguments opposing condonation or upholding the impugned orders; the Bank's position is recorded primarily as the claimant entitled to recovery and the recipient of the costs awarded by the court.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ram Nath Sao @ Ram Nath Sahu & others v. Gobardhan Sao & others, 2002 (1) CTC 769 Interpretation of "sufficient cause" under Section 5 Limitation Act — should receive a liberal construction to advance justice; courts should not adopt a fault-finding or pedantic approach when no negligence or mala fide is imputable. The court relied on this principle to emphasize that explanations for delay should be liberally considered and that condonation should be the rule rather than the exception when bona fides are shown; this supported condoning the 1006-day delay here.
N. Balakrishnan v. M. Krishnamurthy, 1998 (2) CTC 533; 1998 (7) SCC 123 Guidelines for exercise of discretion under Section 5 — "sufficient cause" construed liberally; acceptability of explanation is key; length of delay not decisive; absence of mala fide favors condonation; courts should balance prejudice and may award compensation to opposite party. The court invoked these guidelines to justify condoning the delay despite its length, noting absence of proven mala fide and ordering the petitioners to pay Rs. 25,000/- to the Bank as costs to account for prejudice/expenses.
Malkiat Singh & another v. Joginder Singh & others, 1997 (3) CTC 619; AIR 1998 SC 258 Setting aside ex parte decree where defendants were not at fault (e.g., counsel reported no instructions and did not inform defendants) — ex parte decree liable to be set aside when defendants act promptly on obtaining knowledge. The court relied on the reasoning that defendants cannot be deemed careless where circumstances show they were prevented from participating, supporting the view that the ex parte decree and subsequent dismissals warranted reconsideration.
Kailash v. Nanhku & others, 2005 (3) CTC 355; 2005 (4) SCC 480 Adversarial system: ordinarily no party should be denied opportunity to participate in proceedings; provisions relating to participation should be construed to avoid denying participation. The court used this principle to stress the importance of allowing parties to participate and to justify a pragmatic, justice-oriented approach rather than a technical denial of opportunity.
Dinabandhu Sahu v. Jadumoni Mangaraj & others, AIR 1954 SC 411 Even under Section 5 Limitation Act, words "sufficient cause" merit liberal construction to advance substantial justice where no negligence or want of bona fides is imputable. The court cited this authority to reinforce that condonation of delay was appropriate on the facts and that the words "sufficient cause" must be construed liberally to avoid injustice.

Court's Reasoning and Analysis

The court conducted a fact-sensitive analysis grounded in established authorities on condonation of delay and the right of a party to participate in adversarial proceedings. Key steps in the court's reasoning, as stated in the opinion, are:

  1. The court heard counsel and noted the petitioners' willingness to pay costs (they offered Rs. 25,000/-) and their readiness to settle the matter; the petitioners also asserted that Rs. 15 lakhs had already been paid towards the debt.
  2. The court emphasized that refusal to condone delay can result in meritorious matters being prematurely terminated and that courts should avoid a pedantic or hyper-technical approach where such an approach would defeat substantial justice.
  3. Applying precedents (Ram Nath Sahu; N. Balakrishnan; Malkiat Singh; Kailash; Dinabandhu Sahu), the court stressed that the expression "sufficient cause" under Section 5 of the Limitation Act must be liberally construed, especially where no negligence, inaction, or mala fide is imputable to the defaulting party.
  4. On the facts, the court accepted the petitioners' specific averments — notably that the second writ petitioner (managing partner) was frequently engaged in business and moved often, which contributed to delay, and that the petitioners were willing to settle and pay the balance amount — as sufficient cause for the 1006-day delay in filing M.A.SR Nos. 1274 and 1277 of 2006 to restore the earlier applications.
  5. The court considered that the DRT and DRAT had not taken a sufficiently liberal or justice-oriented view and that, given the petitioners' bona fide efforts and willingness to settle, interference with their orders was warranted.
  6. Balancing the interests of finality and fairness, the court ordered condonation but also imposed a monetary cost to the Bank (Rs. 25,000/-) to account for prejudice/expenses the Bank may have incurred as a result of the delay and the need to re-open proceedings.
  7. Finally, the court directed that the petitioners be given an opportunity to contest the DRT proceedings diligently and to settle by paying the balance due; parties were directed to bear their own costs for the writ petition overall (except the directed payment to the Bank).

Holding and Implications

Holding: Writ Petition Allowed; the orders of the Debt Recovery Appellate Tribunal dated 10-05-2007 in M.A. Nos. 205 & 206 of 2006 and the Debts Recovery Tribunal-I order dated 11-10-2006 in M.A.SR Nos. 1274 & 1277 of 2006 are set aside.

Direct implications and directions (as expressly stated in the opinion):

  • The court condoned the delay of 1006 days for filing M.A.SR Nos. 1274 and 1277 of 2006 to restore M.A. Nos. 338 and 339 of 2002, finding sufficient cause on the facts presented.
  • The petitioners are directed to pay Rs. 25,000/- to the first respondent Bank as costs within 10 days from receipt of a copy of the order.
  • The writ petitioners are allowed to contest the proceedings before the Debts Recovery Tribunal-I, Chennai diligently and to attempt settlement by paying the balance amount due to the Bank.
  • Having regard to the facts and circumstances, the parties are directed to bear their own costs (other than the Rs. 25,000/- payable to the Bank).

Broader implications: The opinion applies established Supreme Court principles favoring liberal construction of "sufficient cause" and preserving parties' opportunity to be heard; however, the court did not state that it was laying down any new legal precedent. The decision's primary effect is to reopen the specific recovery proceedings between the parties and to require payment of costs to compensate the Bank; no declaration of novel law is made in the text.

    Ravi Enterprises, Rep By Its Partner, T.S Ravi, No. 892, T.H Road, Thiruvottiyur, Chennai-600 019. 2. T.S Ravi 3. Smt. T.S Sumathy 4. Smt. T.S Sulochana Petitioners v. Indian Bank, Thiruvottiyuur Branch, T.H Road, Thiruvottiyur, Chennai-600 019. 2. The Chairperson, Debt Recovery Appellate Tribunal, Chennai. 3. K. Lakshmi S

    1. The petitioners have filed the present Writ Petition praying for an issuance of a Writ of Certiorarified Mandamus calling for the records of the second respondent viz., the Chairperson, Debt Recovery Appellate Tribunal, Chennai in regard to the order dated 10-5-2007 passed in M.A No. 205 of 2006 and M.A No. 206 of 2006 and quash the same and consequently, not to confirm the auction held on 11-10-2006 in DRT. No. 103 of 1999 on the file of Debts Recovery Tribunal-I in respect of the schedule mentioned property.

    2. The writ petitioners are the defendants in O.A No. 1774 of 1998 before the Debts Recovery Tribunal, Chennai. The first respondent-Bank has filed O.A No. 1774 of 1998 against the writ petitioners/defendants for recovering a sum of Rs. 20,71,776/- with interest at 19.89% per annum with quarterly rests from the date of Application till the date of realisation with costs and for sale of the Plaint schedule property. The writ petitioners/defendants 1 to 4 were set ex parte and an order was passed on 8-4-1999 by the Debts Recovery Tribunal, Chennai declaring that the first respondent-Bank is entitled to the Recovery Certificate against the writ petitioners/defendants 1 to 4 for a sum of Rs. 20,71,776/- till date of Application and with 12% simple interest from the date of Application till the date of realisation with costs which includes the Advocate fees and a Recovery Certificate was ordered to be issued thereto, with a direction to communicate the copy of the order to all the parties.

    3. In M.A Nos. 205 and 206 of 2006 filed by the writ petitioners/appellants, a common order was passed on 10-5-2007 by the second respondent viz., the Chairperson, Debt Recovery Appellate Tribunal dismissing both the Appeals. As a matter of fact, M.A Nos. 205 and 206 of 2006 arise out of the common orders passed by the Debts Recovery Tribunal-I, Chennai on 11-10-2006 in M.A.SR Nos. 1274 and 1277 of 2006 to condone the delay of 1006 days in filing these Applications to restore M.A Nos. 338 and 339 of 2002. The Debts Recovery Tribunal-I, Chennai has dismissed M.A.SR Nos. 1274 and 1277 of 2006 on 11-10-2006 without costs finding that the writ petitioners/petitioners defendants have not properly explained the delay of 1006 days.

    4. The learned counsel for the writ petitioners/appellants/defendants urges that the common order of the second respondent viz., Debt Recovery Appellate Tribunal dated 10-5-2007 passed in M.A Nos. 205 and 206 of 2006 in dismissing the Appeals is against the well established principles of natural justice and that the second respondent viz., Debt Recovery Appellate Tribunal has not taken into consideration of the fact that the property belongs to a senior lady citizen, one of the guarantors and who is ready and willing to settle the matter and that a sum of Rs. 10,00,000/- deposited with the first respondent Bank by the writ petitioners/defendants does not find a place in the order passed by the second respondent/DRAT on 10-05-2007 and that the facts and circumstances leading to the passing of the ex parte decree on 8-4-1999 in O.A No. 1774 of 1998 have not been taken into consideration by the second respondent/DRAT and therefore pray for setting aside the common order passed in M.A Nos. 205 & 206 of 2006 dated 10-5-2007 and to allow the Writ Petition.

    5. The case of the writ petitioners/appellants/defendants is that they filed I.A No. 949 of 1999 to set aside the ex parte order passed against defendants 1 and 2 and further that I.A Nos. 1063 and 1064 of 1999 were filed to set aside the ex parte decree and that the ex parte decree was passed on 8-4-1999 in O.A No. 1774 of 1998 and that when the certificate of recovering Officer Debts Recovery Tribunal-I, dated 14-01-2001 was served on the second petitioner to the effect that the property would be brought to public auction on 26th December 2001 at 3.00 p.m M.A Nos. 338 and 339 of 2002 were filed to condone the delay in filing the Petition and to stay the operation, but the said M.A Nos. 338 and 339 of 2002 were dismissed for non-prosecution and only on 9-9-2006 the dismissal of M.A Nos. 338 and 339 of 2002 came to the knowledge and that the petitioners are ready to settle the matter and that they should be given an opportunity and in the interest of justice the delay of 1006 days in filing the Application to restore M.A Nos. 338 and 339 of 2002 are to be allowed.

    6. It is a specific case of the writ petitioners/appellants/petitioners/defendants that the Debts Recovery Tribunal-I, Chennai and the Debt Recovery Appellate Tribunal, Chennai in their orders in M.A.SR Nos. 1274 and 1277 of 2006 dated 11-10-2006 and M.A Nos. 205 and 206 of 2006 dated 10-5-2007 have not applied the principles of natural justice in proper perspective and they ought to have condoned the delay of 1006 days in filing the Application M.A.SR Nos. 1274 and 1277 of 2006 to restore M.A Nos. 338 and 339 of 2002 and allowed the Appeals and since they have not taken a liberal view in the matter, this has resulted in miscarriage of justice.

    7. The learned counsel for the writ petitioners relied on the Hon'ble Supreme Court decision reported in Ram Nath Sao @ Ram Nath Sahu and others v. Gobardhan Sao & others, 2002 (1) CTC 769, whereunder it is observed as follows:

    “Limitation Act, 1963, Section 5 — Condonation of delay — Sufficient cause — Meaning of — Approach of Courts while considering Petition to condone delay — Expression “sufficient cause” in connection with delay in filing Application to set aside abatement or other similar provision should receive liberal construction so as to advance justice when no negligence, inaction or want of bona fide is imputable to party — Whether explanation for delay would constitute sufficient cause will depend upon facts of each case — Courts should not proceed with tendency of finding fault with “cause” shown and reject petition in over jubilation of disposal drive — Acceptance of explanation furnished should be rule and refusal exception more so when no negligence, inaction or want of bona fide can be imputed to defaulting party — However Courts should not lose sight of fact that by not taking steps within prescribed time valuable right as accrued to other party which should not be lightly defeated by condoning delay in a routine manner — Explanation for delay should not rejected taking pedantic and hyper-technical view or when stakes are high or where arguable points of facts and law are involved — Courts have to strike balance between the effect of order on parties to lis.

    (Para 12)

    Words and Phrases — “Sufficient Cause” — Meaning of — Expression “sufficient cause” in connection with delay in filing Application to set aside abatement or other similar provision should receive liberal construction so as to advance justice when no negligence, inaction or want of bona fide is imputable to party — Whether explanation for delay would constitute sufficient cause will depend upon facts of each case — Courts should not proceed with tendency of finding fault with cause shown and reject petition in over jubilation of disposal drive — Acceptance of explanation furnished should be rule and refusal exception more so when no negligence, inaction or want of bona fide can be imputed to defaulting party”.

    8. He also relied on N. Balakrishnan v. M. Krishnamurthy., 1998 (2) CTC 533: 1998 (7) SCC 123, wherein it is observed as follows:

    “Limitation Act, 1963, Section 5 — Condonation of delay — Discretion of Court — How to exercise — Guidelines stated — Words “sufficient cause” should be construed liberally — Acceptability of explanation for the delay is the sole criterion, length of delay not relevant — In absence of anything showing mala fide or deliberate delay as a dilatory tactic, Court should normally condone the delay — However, while doing so Court should also keep in mind the consequent litigation expenses to be incurred by the opposite party and should compensate him accordingly — Where a Court condones delay in positive exercise of discretion, superior Court and more particularly the revisional Court should not normally disturb the same — But where request for condonation of delay is refused, it would be open to the superior Court to come to its own finding on the basis of explanation for the delay given by the party — Delay on the part of defendant-appellant of 883 days in approaching the Court against dismissal of his Application to set aside ex parte decree passed against him — Non-action on the part of his advocate explained as cause for the delay — Appellant also complaining about conduct of the advocate before Consumer Forum and getting Rs. 50,000/- as compensation — Appellant's explanation for the delay accepted and delay condoned by Trial Court — But in Revision High Court setting aside the order of Trial Court on ground that appellant was negligent and was not careful enough to meet the advocate to verify the stage of the proceedings for a long time — Held, High Court in Revision erred in interfering with the exercise of jurisdiction by Trial Court in condoning the delay when appellant's conduct did not as a whole warrant castigating him as an irresponsible litigant having regard to present busy and preoccupied life.

    Limitation Act, 1963 — Object of fixing time-limit — Not meant to destroy rights — It is founded on public policy fixing a life span for the legal remedy for the general welfare”.

    9. Yet another decision Malkiat singh and another v. Joginder Singh and others, 1997 (3) CTC 619: AIR 1998 SC 258, was relied on the side of writ petitioners wherein it is held as follows:

    “Civil P.C (5 of 1908), Order 9, Rule 13 — Ex parte decree — Setting aside of — Defendants engaging counsel to defend Suit filed against them — Suit proceeded ex parte and ex parte decree passed on counsel reporting no instructions — Neither counsel reporting this fact to defendants nor Court issued notice to them — Defendants getting knowledge of ex parte decree only when they approached the counsel — Application to set aside decree filed by defendants within 4 days of knowledge — Defendants cannot be said to be careless/negligent — Ex parte decree liable to be set aside”.

    10. It is to be noted that the third respondent was the successful bidder in public auction for a sum of Rs. 29,10,000/- and that the sale certificate was issued in her favour on 13-03-2007.

    11. In Kailash v. Nanhku and others, 2005 (3) CTC 355: 2005 (4) SCC 480 at 483, it is observed that “a provision relating to participation of a party in any proceedings, in an adversarial system, held, should be so construed that ordinarily no party is denied the opportunity of participating in the process of justice dispensation — Civil Procedure Code, 1908 — Orders 1, 7, 8, 9, 17, 18, 22, 23, 35 and 41”.

    12. It is useful to refer to the decision Dinabandhu Sahu v. Jadumoni Mangaraj and others, AIR 1954 SC 411 at 412, wherein it is laid as follows:

    “Held that even if the matter had to be judged under Section 5 of the Limitation Act, it would have been a proper exercise of the power under that Section to have excused the delay. The words “sufficient cause” should receive a liberal construction so as to advance substantial justice when no negligence nor inaction nor want of bona fides is imputable to the appellant. The order condoning delay was on the facts a proper one to pass under the Proviso to Section 85. 13 Mad 269, Approved”.

    13. We have heard the learned counsels and noticed the rival contentions. The learned counsel for the writ petitioners at the time of advancing his arguments informed this Court that the petitioners are willing to pay a cost of Rs. 25,000/- if an opportunity is given to them to prove their case on merits.

    14. We are of the view that refusal to condone delay can result in a meritorious matter being thrown at the early stage and cause of justice being defeated. Moreover, the law Courts should not prefer to adopt a pedantic approach and on the other hand a pragmatic approach has to be made to deliver substantial justice overriding technical considerations as far as the present case is concerned. Furthermore, a party does not stand to benefit by adopting delay. Per contra, he runs a grave risk. It cannot gainsaid that judiciary is respected because it is capable of removing injustice and is expected to do so. Admittedly, the claim of the first respondent-Bank is for Rs. 20,71,776/- together with interest at the rate of 19.89% p.a with quarterly rests from the date of the Application till the date of realization, etc. The learned counsel for the writ petitioners informs this Court that already a sum of Rs. 15 lakhs was paid and the petitioners/appellants/defendants are willing to pay the rest of the amount and to settle the matter. It cannot be denied that the Debt Recovery Tribunal has power to recall the Recovery Certificate even after its issuance on the basis that the matter was settled between the creditor/Bank and the borrower/guarantor. No wonder the recovery of due is an essential function of any Bank. At this juncture, it cannot be lost sight of that the preamble of the Recovery of Debts due to Banks and Financial Institutions Act, 1993 speaks of expeditious adjudication and recovery of debts due to banks and financial institutions. Moreover, merely because an Application for setting aside the ex parte order having been allowed to go for wilful default and also allowed the Restoration Petition also dismissed for default, it cannot said by any means that the writ petitioners lack bona fides in their endeavour to set aside the ex parte order. In short, the length of delay is immaterial, in our considered opinion.

    15. In the light of the foregoing discussions and in view of the specific averment of the second writ petitioner/second defendant, being the Managing Partner of the first defendant firm i.e, the sole individual engaged in business activity and to move quite often from place to place in order to secure business, etc., and since he is ready to settle the matter consciously and judicially and taking note of all attendants circumstances together, we are of the considered view that the writ petitioners have furnished sufficient cause in M.A.SR Nos. 1274 and 1277 of 2006 filed to condone the delay of 1006 days to restore M.A Nos. 338 and 339 of 2002 and therefore, we are inclined to interfere with the orders passed in M.A Nos. 205 and 206 of 2006 dated 10-5-2007 passed by the second respondent and also that of the order of the Debts Recovery Tribunal-I, Chennai dated 11-10-2006 passed in M.A.SR Nos. 1274 and 1277 of 2006 and accordingly, set aside their orders in the interest of justice. However, we direct the writ petitioners/appellants/defendants to pay a sum of Rs. 25,000/- to the first respondent Bank as costs within 10 days from the date of receipt of a copy of this order.

    16. With the above observations, we allow the Writ Petition. The writ petitioners/appellants/defendants are given the opportunity to contest the proceedings before Debts Recovery Tribunal-I, Chennai diligently in the manner known to law and to settle the matter in issue by paying the balance amount due. Having regard to the facts and circumstances, the parties are directed to bear their own costs.