Structured Summary of the Opinion (Venugopal, J.)

Factual and Procedural Background

The plaintiff sought specific performance of an agreement of sale dated 14 December 1973 for a vacant piece of land described in the plaint schedule belonging to the first defendant. The plaintiff paid Rs. 1,000 as an advance and agreed a term that the first defendant would sign and submit building plans to the Corporation so the plaintiff could commence construction without delay. The plaintiff prepared building plans, applied for water connection and made alterations suggested by the first defendant. The first defendant did not sign or forward the plan to the Corporation nor execute the sale deed within the three months specified in the agreement, and the plaintiff, after notice, filed suit for specific performance.

Defendants 2 to 4 are the children of the first defendant. In their written statement the defendants pleaded, among other matters, that the plot agreed to be sold was not an independent plot but part of No. 17/1 Kilpauk Garden Road; they raised concerns about whether the Corporation would sanction subdivision or permit construction on a plot described in the pleadings (the pleading uses the phrase "measuring less than 1#fr1/2> grounds"); and they relied on Clause 8 of the agreement which provided for return of the advance if sanction was not obtained within three months. The defendants contended the plaintiff had defaulted in obtaining sanction and that the suit for specific performance was misconceived.

The trial court framed three issues: (1) entitlement to specific performance, (2) whether the defendants breached by not signing the plan for sanction, and (3) other reliefs. The trial court found the first defendant had a duty to sign and submit the plan, rejected the defendants' suggestion that plans were prepared after suit, held the first defendant committed breach by not signing/forwarding the plans, and decreed specific performance with directions as to plans, deposit of balance consideration and execution of the sale deed pending sanction.

The defendants appealed the trial court decree to this Court. The appellants also sought to place before this Court the plan they had submitted to the Corporation and the Corporation's orders as additional evidence by C.M.P. No. 6272 of 1979.

Legal Issues Presented

  1. Whether the plaintiff is entitled to specific performance of the agreement of sale.
  2. Whether the defendants breached the agreement by not signing and forwarding the building plan for sanction.
  3. Whether the obligation to obtain sanction of the plan by the Corporation makes the contract a contingent contract unenforceable until such sanction, or whether the contract is enforceable and the vendor's failure to act constitutes a breach.
  4. Whether additional evidence (the plan submitted by appellants and the Corporation's orders) should be admitted and whether subsequent refusal of the Corporation, if shown, would render the contract frustrated.

Arguments of the Parties

Appellants' (Defendants') Arguments

  • The contract of sale (Ex. A1) was conditional or contingent on the sanction of the building plan by the Corporation; the sanction was a condition precedent and the contract could not be enforced until that event occurred.
  • If the sanction event became impossible (e.g., Corporation refusal), the contract would be void or frustrated and not enforceable.
  • The plan submitted by the appellants to the Corporation and the Corporation's orders should be received as additional evidence (C.M.P. No. 6272 of 1979) to show that sanction was refused.
  • The sanction requirement was said to be for the mutual benefit of both parties and not subject to unilateral waiver by the respondent.
  • It was suggested at trial that the plans Exs. A2 and A3 were prepared after filing of the suit (an allegation the trial court rejected).

Respondent's (Plaintiff's) Arguments

  • The first defendant had a contractual duty under Ex. A1 to sign and submit the building plan prepared by the respondent to the Corporation; the defendants' failure to do so amounted to breach.
  • The approval requirement was, in part, for the respondent's benefit and could be waived by her; the contract should be enforced and the defendants compelled to perform their obligations (including submission of plans).
  • The plaintiff produced evidence (including the plans Exs. A2 and A3 and testimony of P.W.2) to show the plans were prepared and tendered before institution of the suit.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Mrs. Chandnee Widyavathi Maddon v. Dr. C.L. Katial, 1964 2 S.C.J. 824 = A.I.R. 1964 S.C. 978 The Supreme Court held that an agreement of sale which provided that the vendor should obtain necessary permission was not a contingent contract making the agreement unenforceable; where the vendor failed to obtain or withdrew the required application, the vendor had breached obligations and the court could enforce performance (including directing application to competent authority). This Court relied on that decision to hold that a contract of sale subject to sanction of a municipal corporation is not inherently a contingent contract; the vendor's duty to forward plans for sanction is enforceable and the appellants' failure to forward Exs. A2 and A3 constituted breach entitling the respondent to specific performance (subject to modification described in the decree).

Court's Reasoning and Analysis

The Court proceeded by examining the contractual obligations in Ex. A1, the trial court's findings and the evidentiary record. The reasoning unfolded in the following steps:

  1. The Court accepted the trial court's finding (not challenged on appeal) that the building plans Exs. A2 and A3 were prepared by the respondent and were tendered to the first appellant before the institution of the suit. The trial court's acceptance of P.W.2's evidence on this point was left undisturbed.
  2. Given the contractual clauses, the Court held the first respondent's (vendor's/appellants') immediate obligation in the sequence of reciprocal promises was to sign and forward the plans to the Corporation for sanction. The obligation to forward the plan is expressly provided by the agreement (Cl. 4 of Ex. A1).
  3. Relying on the cited Supreme Court authority, the Court reasoned that a sale contract framed subject to obtaining municipal sanction does not automatically become a contingent contract incapable of enforcement. Instead, where one party's performance (here, forwarding the plans to the Corporation) is a prerequisite under the contract, the failure of that party to perform is itself a breach which the court may remediate.
  4. Consequently, the appellants' contention that the contract was inchoate or unenforceable until the Corporation sanctioned the plan was rejected: the contract remains enforceable and the appellants' failure to forward the respondent's plans constituted a breach entitling the respondent to relief.
  5. The Court addressed the appellants' attempt to introduce as additional evidence the plan the appellants themselves submitted to the Corporation and the Corporation's orders (C.M.P. No. 6272 of 1979). It held these documents were neither admissible nor relevant to the central question because, under Ex. A1, the appellants had not forwarded the respondent's plan to the Corporation as required; thus, the appellants' plan and the Corporation's orders thereon could not be relied upon to defeat the respondent's entitlement based on the appellants' breach.
  6. The Court further explained why the fact that a plan submitted by the appellants may have been refused by the Corporation does not automatically mean the respondent's plan would meet the same fate: (a) the reasons for refusal were not shown; (b) a returned plan can be amended and resubmitted if it failed to comply with rules; and (c) it cannot be anticipated in advance that the respondent's plan would be treated identically.
  7. However, the Court found one aspect of the trial court's decree unsustainable: the trial court directed execution of the sale deed pending sanction of the plan. Clause 4 of Ex. A1 explicitly states the sale shall be carried out only if the plan is sanctioned by the Corporation. The Court held that ordering execution of the sale deed before sanction contradicted this contractual term, and therefore modified the decree to require that the sale deed be executed only after the plan is sanctioned by the Corporation.
  8. On all other points (including the finding of breach and entitlement to specific performance subject to the modification regarding timing of execution), the trial court's decree was confirmed.

Holding and Implications

Core Holding: The appeal is allowed in part. The trial court's decree granting specific performance is confirmed except that the direction requiring the defendants to execute the sale deed pending sanction of the plan is modified: the sale deed must be executed by the defendants only after the plan is sanctioned by the Corporation.

Direct consequences for the parties:

  • The Court upheld the trial court's finding that the appellants committed breach by not forwarding the respondent's plans (Exs. A2 and A3) to the Corporation, entitling the respondent to a decree for specific performance on that short ground.
  • The trial court's directions that the respondent should send the plans to the first defendant, that the first defendant should sign and submit them for sanction, and that the respondent should deposit the balance of sale consideration into court (as ordered) were, in effect, sustained, but the sale deed must be executed only after sanction of the plan by the Corporation in accordance with the contract.
  • The appellants' petition to receive the plan submitted by them and the Corporation's orders (C.M.P. No. 6272 of 1979) was dismissed.
  • No costs were awarded; the appeal was allowed in part and otherwise dismissed in the sense that other parts of the decree were confirmed.

Broader implications: The opinion applies the principle from the cited Supreme Court authority that obligations to obtain municipal or governmental sanction embodied in a sale agreement do not automatically render the contract unenforceable as a contingent contract; instead, the party obliged to act must perform and its failure may render it liable for breach. The opinion itself does not purport to lay down a novel precedent beyond applying that principle to the facts before the Court.

Disposition: Appeal allowed in part; trial court decree modified only to the extent that the sale deed must be executed after sanction of the plan; C.M.P. No. 6272 of 1979 dismissed; no costs.

    S.K Manavalan And Others. v. B.S Mary

    Venugopal, J.:

    1. The defendants are the appellants and the plaintiff is the respondent. The plaintiff filed a suit for specific performance of a contract of sale on the following averments. The plaintiff was on the look out for a house or a plot, of land for building a house as she was not happy in the house she was residing at Thiagappa Mudali St., Kilpauk. A vacant piece of land described in the plaint schedule belonging to the first defendant was offered for sale. The plaintiff entered into an agreement of sale on 14th December 1973 and paid an advance of Rs. 1,000 to the first defendant for purchase of the suit property. As the plaintiff wanted to start the construction without delay, she wanted the plan to be submitted immediately by the first defendant and this was agreed to and incorporated as a term in the agreement of sale. Thereupon the plaintiff applied for getting connection for water supply and also prepared a building plan and sent it to the first defendant. The first defendant suggested some alterations and the plaintiff believing that the suggestion made by the first defendant were bona fide, carried them out and prepared another plan. In the meantime, the plaintiff came to know that the first defendant was negotiating the sale of the property. Since the first defendant did not sign the plan and forward the same to the Corporation as agreed and execute the sale deed within the period of three months agreed to in the agreement of sale, the plaintiff after notice has filed a suit for specific performance of the contract of sale.

    2. Defendants 2 to 4 are the sons and daughter of the first defendant. The defendants in their written statement have raised the following pleas: what was agreed to be sold under the agreement of sale, dated 14th December 1973 was not an independent and separate piece of land, but part of No. 17/1 Kilpauk Garden Road, Madras, Even at the time of agreement of sale the defendants pointed out to the plaintiff the difficulties in the way of selling the suit property and wanted the plaintiff to make sure whether the Corporation of Madras would sanction the plan for construction of a building on a plot of land measuring less than 1#fr1/2> grounds, contrary to the rules and whether they would permit the sub-division of the plot without leaving a gap of 12ft. For entrance to the rear portion, it was agreed that for the benefit of both parties the sanctioning of the plan by the Corporation of Madras should be made a condition precedent for sale of the plot. It was then agreed that the plaintiff should prepare a plan and hand it over to the defendants for being submitted to the Corporation of Madras for sanction and the sale deed had to be executed only if the plan was sanctioned. Cl. 8 of the agreement provided that if the plaintiff fails to get the sanction within the three months from the date of agreement, the advance of Rs. 1000 paid should be returned. The plaintiff, through her husband, made enquiries in the Corporation and came to know that the plan will not be sanctioned since the sub-division of the property may not be granted and that she cannot construct the building with the plan sanctioned in favour of another person. It was the plaintiff who has committed the default and knowing that she has defaulted, has issued a suit notice to the defendants. Even otherwise, since the sanction of the plan was not obtained within three months from the date of agreement, the plaintiff at best would be entitled to refund of advance, and the suit for specific performance is misconceived.

    3. The trial court framed the following three issues—

    1. Whether the plaintiff is entitled for the specific performance of the agreement of sale?

    2. Whether the defendants have committed breach of the terms of agreement of sale by not signing the plan for sanction?

    3 To what other reliefs the parties are entitled to?

    The trial court recorded the following findings—

    1. It was the duty of the first defendant to sign the plan and submit It to the Corporation, Without doing so, It Is not open to the first defendant to say that the Corporation of Madras would not sanction the plan. The plea that before the sanction of the plan, the plot should be sub-divided is not borne out by the agreement of sale Ex. A.1

    2. The suit property should be first sub-divided before the plan can be submitted to the Corporation, is a plea Introduced for the first time only at the tine of the trial and not referred to in Ex. A.1

    3. The suggestion that the building plans. Exs a 2 and a 3 were prepared after the filing of the suit and produced before the first defendant on 29th December 1973, was rejected by the trial court.

    4. The first defendant did not perform his part of the contract by signing the building plan, without sending the plan to the Corporation the first defendant cannot Imagine difficulties in the sanction of the plan. The first defendant has committed a breach of the contract by not signing the plan prepared by the plaintiff and forwarding the same to the Corporation for sanction.

    4. On these findings the trial court decreed the suit with the following directions-

    (a) The plaintiff should send the necessary plans to the first defendant by registered post within ten days from the date of decree. On receipt of the plans the first defendant should sign and submit them to the Corporation for sanction.

    (b) Pending sanction of the plan by the Corporation the defendants should execute the sale deed in favour of the plaintiff in respect of the suit property within two months from the date of decree and the plaintiff should deposit the balance of sale consideration in court within six weeks from the date of the decree.

    (c) On such deposit, defendatts should give vacant possession of the suit property to the plaintiffs.

    5. Aggrieved against the decree and judgment of the trial court the defendants have filed the above appeal before this Court. It is contended for the appellants that the contract of sale, Ex. A1 should be performed and completed subject to sanction of plan by the Corporation and it is a contingent contract, the contingent event being the future event of the sanction of plan by the Corporation and the contract cannot be enforced by law unless and until that event has happened, and if the happening of the event becomes impossible, the contract becomes void. In the case of Mrs. Chandnee Widyavathi Maddon v. Dr. C.L Katial . 1964 2 S.C.J 824=A.I.R 1964 S.C 978. the agreement to sell the house property built on leasehold plot belonging to the Government provided that the vendor should obtain the necessary permission of, the Chief Commissioner to the transaction. Though the vendor made an application to the appropriate authorities, later she withdrew the application and failed to fulfil her part of the obligation under the agreement. In a suit for specific performance it was contended that the contract was not enforceable being of a contingent nature and the contingency not having been fulfilled, the agreement was inchoate. Rejecting the contention the Supreme Court held that the contract is enforceable and not a contingent contract. It was further held that in the contract of sale it was for the defendant vendor to make the necessary application for obtaining the permission from the Chief Commissioner and since such as application made was withdrawn, she has failed to perform her part of the contract and the court has to enforce the terms of the contract and enjoin upon the defendant vendor to make the necessary application to the Chief Commissioner. From the decision of the Supreme Court cited above it can be seen that a contract of sale subject to the sanction of plan by the Municipal Corporation, is not a contingent contract, Capable of being enforced only when the plan is sanctioned. A contract is a bundle of reciprocal promises and the obligation of the parties had to be performed in the same sequences as set out in the contract. One of the parties to contract cannot require compliance with the obligation by the other party without in the first instance performing his own part of the contract which in the sequence of obligations is performable by him earlier. CM of Ex. A1 provides that the plan designed by the respondent should be submitted to the Corporation for sanction by the appellants. This being the term of contract between the parties it has to be necessrily enforced by court. In the chronological sequence the first obligation to be performed by the appellants under Ex. A1 is to forward the plans to the Corporation for sanction. As per Cl.4 of Ex. A1 it is incumbent on the appellant to submit the plans Exs. A2 and A3, prepared by the respondent for sanction by the Corporation. In asmuch as the appellants have failed to forward Exs. A2 and A3 to the Corporation, they have committed breach of contract. During the course of trial it was suggested that Exs. A2 and A3 were prepared after the filing of the suit and they were not prepared and produced before the filing of the suit. The trial court accepting the evidence of P.W 2, the licensed suiveyer, rejected the suggestion and held that Exs. A2 and A3 were prepared and submitted by the respondent to the first appellant for being forwarded to the Corporation before the institution of the suit. The correctness of this finding is not challenged in appeal. It, therefore, follows that the first appellant, in not submitting Exs. A2 and A3 to the Corporation has committed breach of contract and on this short ground the respondent is entitled to a decree for specific performance of the contract. The contract does Dot become void or ineffective merely because the first appellant has failed to forward to the Corporation Ex. A2 and Ex. A3 prepared by the respondent. Without forwarding the game to the Corporation as per the terms of the contract it is not open to the appellants to contend that the contingent event, viz,, the sanction of the plan has not fructified and consequently the contract has become void.

    6. It was contended by the learned counsel for the respondent that the approval of the building plan by the Corporation was exclusively for the benefit of respondent and if so, by waiver she can get rid of the condition. Counsel for appellants contended that sanction of the plan is a condition precedent, Intended for the mutual benefit of both parties and it cannot be the subject matter of waiver by respondent. This question will arise for consideration only when the first appellant has forwarded the building plan to the Corporation as required under Ex. A1 and the Corporation refused to sanction the same. Until that stage is reached the consideration of the issue is premature and need not be gone into at this stage.

    7. It was next contended for the appellants that subsequent to the decree, the first appellant forwarded the building plan to the Corporation and the Corporation refused to sanction the plan and if the supervening event is taken into account the contract has failed for want of sanction by the Corporation and no decree for specific performance can be passed on a contract which has become frustrated.

    8. The appellants have filed C.M.P No. 6272 of 1979 to receive the plan submitted by the Corporation and the orders passed thereon as additional evidence. As per Ex. A1 the plan prepared by the respondent should be forwarded to the Corporation for sanction. Since such a plan has not been forwarded to the Corporation the plan submitted by the appellants and the order of the Corporation passed thereon, is neither admissible, nor relevant for the purpose of this plea and the petition to receive the additional evidence has therefore, to be rejected.

    9. The plea that even if any building plan prepared by the respondent is forwarded to the Corporation, that will also meet with the same fate as the plan submitted by the first appellant is bereft of merit for the following three reasons—(1) It is not known why the plan submitted by the appellant was not approved by the Corporation. (2) If the plan was returned for noncompliance of any rules or procedure or any other reason the plan can always be resubmitted after compliance. (3) It cannot be anticipated that the building plan prepared by the respondent would also receive the same fate and treatment as the building plan prepared by the first appellant and forwarded to the Corporation.

    10. The trial court has decreed that pending sanction of plan by the Corporation of Madras, the defendants should execute the sale deed in favour of the plaintiff in respect of the suit property, Cl. 4 of Ex. A1 in unmistakable terms provides that the sale shall be gone through only if the plan is sanctioned by the Corporation. In view of this specific term in the contract, the trial court is not justified in directing the defendants to execute the sale deed pending sanction of the plan by the Corporation. The sale deed should be executed by the defendants-appellants only after the plan is sanctioned by the Corporation. To this extent the decree of the trial court is modified. In all other respects the decree of the trial court is confirmed. In the result, the appeal is allowed in part. No costs.

    11. C.M.P 6272 of 1979 for the reasons stated above stands dismissed.