Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
Smart Summary

Factual and Procedural Background

Petitioner 1 is a proprietary concern engaged in manufacturing and supplying polyesters and yarns, with Petitioner 2 as its proprietor. Respondent 1 is the Administrator of the Electricity Department of Dadra & Nagar Haveli (U.T) and appellate authority under the Electricity Act, 2003. Respondent 2 is the Executive Engineer of the Electricity Department, with Respondents 3 to 5 serving as Deputy and Junior Engineers, and Respondent 6 is the Union of India.

In 2007, Respondent 2 issued a demand notice to the petitioners revising electricity bills for the period July 2003 to July 2007, due to a change in the CT ratio and multiplication factor used in metering, resulting in an increased bill amounting to Rs. 2,60,17,001/-. The petitioners replied through their advocate and received a subsequent bill in January 2008 inclusive of arrears totaling Rs. 2,77,34,867.43.

Aggrieved, the petitioners filed Writ Petition No. 4406 of 2008 challenging the revised bill. The Division Bench of this court disposed of the writ petition in June 2008, directing the petitioners to challenge the bill by way of an appeal. Subsequently, the petitioners filed Electricity Appeal No. 11 of 2008 before Respondent 1, which was dismissed by a reasoned order dated 12/9/2008. This led to the present writ petition.

Legal Issues Presented

  1. Whether the claim raised by the respondents for the revised electricity bills for the period July 2003 to July 2007 is barred by the limitation period under Section 56(2) of the Electricity Act, 2003.
  2. Whether under the provisions of Section 26(6) of the Indian Electricity Act, 1910, the limitation on recovery of electricity charges applies when the under-billing is due to clerical or multiplication factor errors rather than faulty meters.
  3. The proper interpretation of the phrase "when such sum becomes first due" in the context of limitation under Section 56(2) of the Electricity Act, 2003.

Arguments of the Parties

Petitioners' Arguments

  • The claim for the revised amount first became due in July 2003, but the demand notice was issued only on 3/10/2007, thus exceeding the two-year limitation period under Section 56(2) of the Electricity Act, 2003.
  • Accordingly, the petitioners submitted that the revised bill is time-barred and should be quashed and set aside.

Respondents' Arguments

  • Reliance was placed on precedents including U.A Thadani v. B.E.S.T Undertaking and Brihanmumbai Municipal Corporation v. Yatish Sharma & Ors., which support that limitation does not apply where under-billing arises from clerical mistakes.
  • Since the under-billing was due to an oversight in applying the correct multiplication factor, the two-year limitation period under Section 56(2) does not bar recovery.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
U.A Thadani v. B.E.S.T Undertaking, 2000 Vol. 102 (2) Bom.L.R 502 Limitation does not apply to recovery of electricity charges under-billed due to clerical or human errors, not faulty meters. Supported the court's view that the limitation period under Section 56(2) does not bar recovery of amounts under-billed due to multiplication factor errors.
Brihanmumbai Municipal Corporation v. Yatish Sharma & Ors., 2007 (3) Bom.C.R 659 Clarified the interpretation of "when such sum becomes first due" under Section 56(2) of the Electricity Act, 2003. Helped the court conclude that the demand notice date, not the consumption date, determines when the sum becomes first due.
Bharat Barrel & Drum Manufacturing Company Private Limited v. The Municipal Corporation for Greater Bombay, AIR 1978 Bom. 369 Section 26(6) of the Indian Electricity Act, 1910 does not restrict claims to six months if under-billing arises from multiplication factor changes rather than faulty meters. Used to distinguish claims arising from clerical errors from those involving faulty meters and to justify recovery beyond six months.
H.D Shourie v. Municipal Corporation Of Delhi & Anr., AIR 1987 Delhi 219 Interpretation of "due" in electricity charges means due after a valid bill is issued, not immediately upon consumption. Followed to hold that limitation runs from the date of the demand notice, not from the date of consumption.

Court's Reasoning and Analysis

The court analyzed the limitation provision under Section 56(2) of the Electricity Act, 2003, which bars recovery of sums due after two years from the date the sum first became due, except where the sum is continuously shown as recoverable arrears. The petitioners argued that the sums became due in July 2003, making the 2007 demand time-barred.

However, the court relied on precedents distinguishing claims arising from clerical or multiplication factor errors from those involving faulty meters under Section 26(6) of the Indian Electricity Act, 1910. The court noted that the six-month limitation under Section 26(6) applies only to disputes about meter correctness, not to billing errors like multiplication factor mistakes.

Further, the court adopted the reasoning from the Delhi High Court and the Yatish Sharma case that the phrase "when such sum becomes first due" means the date when a valid bill or demand notice is issued, not the date of consumption. Since the petitioners received the demand notice in November 2007, the limitation period began then, rendering the claim timely.

Accordingly, the court found no bar to recovery under Section 56(2) and upheld the appellate authority's dismissal of the petitioners' appeal.

Holding and Implications

The court dismissed the petition, holding that the claim for the revised electricity bills was not barred by limitation under Section 56(2) of the Electricity Act, 2003.

The direct effect is that the respondents are entitled to recover the revised bill amounts from the petitioners. The decision does not set any new precedent but reaffirms existing principles distinguishing billing errors from meter faults and clarifies the commencement of limitation from the date of valid billing.

To access the original judgment, please Sign In or Subscribe.

    M/S. Rototex Polyester & Anr. Petitioners v. Administrator, Administration Of Dadra & Nagar Havli (U.T) Electricity Department, Silvassa & Ors. S

    JUDGMENT.:- (Per Smt. Ranjana Desai, J.)

    1. Rule. The respondents waive service. By consent of the parties, taken up for final hearing and disposal forthwith.

    2. Petitioner 1 is a proprietary concern, having its registered office at 6/8, Old Hanuman Lane, 1st Cross Lane, 1 floor, Room No. 19, Kalbadevi Road, Mumbai - 400 002. Petitioner 2 is the proprietor of petitioner 1. Respondent 1 is the Administrator of Administration of Dadra & Nagar Havli (U.T), Electricity Department, Silvassa. Respondent 1 is the appellate authority under the Electricity Act, 2003. Respondent 2 is the Executive Engineer of the Electricity Department, Dadra & Nagar Haveli (U.T). Respondents 3 to 5 are the Deputy Engineers and Junior Engineer respectively of Respondent 1. Respondent 6 is the Union of India.

    3. Petitioner 1 is in the business, inter alia, of manufacturing and supplying of various types of polyesters and yarns. Petitioner 1 has various types of machineries and equipments in the factory premises. By demand notice dated 3/10/2007, respondent 2 informed the petitioners that the CT ratio of their metering installation was changed from 25/5 to 50/5 vide office report dated 11/7/2003. The demand notice further stated that in this report, it has been mentioned that the multiplication factor has changed from “500” to “1000” with effect from 11/7/2003. The demand notice further stated that by oversight, the department has issued bills for the period July, 2003 to July, 2007 with “500” as multiplication factor for reading of “1000” till July, 2007 and, hence, all the bills for this period are revised with “1000” as multiplication factor. The detailed statement of revised bill was enclosed to the demand notice. The total amount of revised bill was Rs. 2,60,17,001/-. The petitioners were requested to pay the bill amount of the revised bills for the period July, 2003 to July, 2007 within 15 days of receipt of the said demand notice.

    4. By letter dated 12/11/2007, the petitioners gave reply to the said demand notice through their advocate. The petitioners received energy bill dated 11/1/2008. The said bill was inclusive of arrears of revised bill for the period from July, 2003 to July, 2007. The total amount of the said bills comes to Rs. 2,77,34,867.43. The said bill was issued by the office of respondent 2.

    5. Being aggrieved by the said bill, the petitioners filed Writ Petition No. 4406 of 2008 challenging the said revised bill. On 9/6/2008, the Division Bench of this court, (Bilal Nazki & S.S Shinde, JJ.) disposed of the said writ petition observing that the bill issued by the respondents can be challenged by way of an appeal. Liberty was granted to the petitioners to file an appeal in accordance with law. It appears that pursuant to this order, the petitioners preferred an appeal being Electricity Appeal No. 11 of 2008 before respondent 1. By a reasoned order dated 12/9/2008, respondent 1 dismissed the said appeal. Hence, this writ petition.

    6. We have heard, at some length, learned counsel appearing for the petitioners and learned counsel appearing for the respondents.

    7. Learned counsel for the petitioners urged that assuming that the said amount is due from the petitioners, the said amount first time became due in July, 2003, but the claim for July, 2003 to July, 2007 is raised only on 3/10/2007 and, therefore, under Section 56(2) of the Electricity Act, 2003, the claim raised by the respondents is time barred. He submitted that therefore the revised bill is liable to be quashed and set aside.

    8. As against this, learned counsel for the respondents drew our attention to the judgments of learned Single Judge of this court in U.A Thadani v. B.E.S.T Undertaking, 2000 Vol. 102 (2) Bom.L.R 502 and in Brihanmumbai Municipal Corporation v. Yatish Sharma & Ors., 2007 (3) Bom.C.R 659 and submitted that the present case is squarely covered by the said judgments. He submitted that inasmuch as there is wrong billing due to clerical mistake, limitation period of two years does not apply to this case.

    9. Section 56 of the Electricity Act, 2003 provides for disconnection of supply in default of payment. We are concerned in this case with Section 56(2) and hence, it is necessary to quote it.

    “56. Disconnection of supply in default of payment -

    (1) xxx xxx xxx

    (2) Notwithstanding anything contained in any other law for the time being in force, no sum due from any consumer, under this section shall be recoverable after the period of two years from the date when such sum became first due unless such sum has been shown continuously as recoverable as arrears of charges for electricity supplied and the licensee shall not cut off the supply of the electricity.”

    10. Sub-section (2) of Section 56 provides for limitation of two years. It introduces the concept of “the date when such sum becomes first due”. In short, a sum which is due can be recovered within a period of two years from the date it became first due and not thereafter. The only sum which is left out of this is the sum which is shown continuously as recoverable as arrears of charges of electricity.

    11. Section 26 of the Indian Electricity Act, 1910 deals with meters. Sub-section (6) thereof is material. It reads thus:

    “26. Meters:-

    (1) xxx xxx xxx

    (2) xxx xxx xxx

    (3) xxx xxx xxx

    (4) xxx xxx xxx

    (5) xxx xxx xxx

    (6) Where any difference or dispute arises as to whether any meter referred to in sub-section (1) is or is not correct, the matter shall be decided, upon the application of either party, by an Electrical Inspector; and where the meter has, in the opinion of such Inspector ceased to be correct, such Inspector shall estimate the amount of the energy supplied to the consumer or the electrical quantity contained in the supply, during such time, not exceeding six months, as the meter shall not, in the opinion of such Inspector, have been correct; but save as aforesaid, the register of the meter shall, in the absence of fraud, be conclusive proof of such amount or quantity:

    Provided that before either a licensee or a consumer applies to the Electrical Inspector under this subsection, he shall give to the other party not less than seven days' notice of his intention so to do.”

    12. In Bharat Barrel & Drum Manufacturing Company Private Limited v. The Municipal Corporation for Greater Bombay, AIR 1978 Bom. 369, a Division Bench of this court was concerned with a situation where additional amounts for eleven years period were claimed from the consumer on the basis of failure to multiply the reading by 2 (two) and not on the basis of faulty meter. The question was whether the licensee had to restrict its claim to six months. The Division Bench observed that under Section 26 of the Indian Electricity Act, 1910 restriction as to six months does not seem to apply to a claim made by the licensee on the ground that there was a failure to multiply the reading by the changed multiplication factor.

    13. In U.A Thadani's case (supra), learned Single Judge of this court was concerned with similar fact situation. Two bills were raised on the consumer demanding additional amounts because multiplying factor was wrongly charged. It was argued by the consumer on the basis of sub-section (6) of Section 26 that the Electrical Inspector could determine the quantum of electricity consumed during the statutory period of six months and for the period anterior to it the reading registered in the disputed meter will have to be presumed to be correct. Relying on the judgment of this court in Bharat Barrel, learned Single Judge held that the restriction as to six months' period provided in Section 26 has no application to a demand made by the licencee or the Electricity Board for the unpaid amount for the electricity consumed if the consumer was under-billed due to clerical mistakes or human error or such like mistakes.

    14. The principle which can be deduced from the above judgments is that in case the consumer is under-billed on account of clerical mistake such as the present case, where the multiplication factor had changed from 500 to 1000, but due to oversight, the department issued bills with 500 as multiplication factor instead of 1000, the bar of limitation cannot be raised by the consumer. Though Section 26(6) of the Indian Electricity Act, 1910 is not in pari materia with Section 56(2) of the Electricity Act, 2003, in our opinion, the present case would be governed by the above principle and, hence, the challenge raised by the petitioners must fail.

    15. The question raised in this petition can be examined from yet another angle keeping Section 56(2) of the Electricity Act, 2003 with which we are concerned here in the forefront.

    16. In Yatish Sharma's case tariff was changed from GP1 to GP2. Between 19/1/2000 and 27/5/2000, the readings of the electronic meter were not taken. A supplementary bill was raised by the petitioner Corporation therein on the basis of the average monthly consumption. By the supplementary bill, a demand of Rs. 78,187.17 was raised on the consumer and debited to the amount of the bill for the month of April, 2004. The consumer raised a grievance before the Consumer Grievance Redressal Forum. The matter ultimately reached the Ombudsman. He held that the supplementary bill was raised after a period of four years from the date when it became first due and, hence, the amount was not recoverable under Section 56(2) of the Electricity Act, 2003. The Ombudsman's order was challenged in this court.

    17. The issue which arose before learned Single Judge was what interpretation should be placed on the words “when such sum becomes first due”. The question was whether the Ombudsman's view that since the arrears for consumption became due immediately upon the usage of energy, the supplementary bill raised in August, 2004 for the disputed period between January, 2000 to May, 2000 was barred under Section 56(2).

    18. While dealing with this submission, learned Single Judge referred to Delhi High Court's judgment in H.D Shourie… v. Municipal Corporation Of Delhi & Anr.…, AIR 1987 Delhi 219, where the Delhi High Court was considering the expression “due” appearing in Section 24 of the Electricity Act, 2003. The Delhi High Court observed that if the word “due” is to mean consumption of electricity, it would mean that electricity charges would become due and payable the moment electricity is consumed and if charges in respect thereof are not paid then even without a bill being issued, a notice of disconnection would be liable to be issued under Section 24, which could not have been the intention of the legislature. The Delhi High Court observed that the word “due” in this context would mean due and payable after a valid bill has been sent to the consumer. Learned Single Judge followed this view and set aside the Ombudsman's order which had taken a contrary view. We are in respectful agreement with learned Single Judge. In this case, the demand notice with revised bill dated 3/10/2007 was, according to the petitioners, served on them on 9/11/2007. Therefore, the revised bill amount first became due on 9/11/2007. Hence, Section 56(2) of the Electricity Act 2003 would not come in the way of the respondents from recovering the said amount under the revised bills. The impugned order dated 12/9/2008 warrants no interference.

    19. The petition is dismissed.

    Use AI to get other relevant cases.

    Comments

    M/S. Rototex Polyest... v. Administrator, Admin...
    (Aug 20, 2009)