AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • S. 30(2) of the M.R.T.U and P.U.L.P Act.
  • S. 30(2) of the M.R.T.U & P.U.L.P Act
  • P.U.L.P Act, 1971,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • S. 30(2) of the M.R.T.U and P.U.L.P Act.
  • S. 30(2) of the M.R.T.U & P.U.L.P Act
  • P.U.L.P Act, 1971,
Smart Summary

Factual and Procedural Background

The respondent No. 2, an employee of the petitioner-company and a member of respondent No. 1 union, was working as a Technician Grade-III in the production department. He was issued two charge-sheets in March 2003 for various misconducts. After an enquiry conducted by Sri K.P Gurav from May 2003 to January 2004, the charges against respondent No. 2 were held proved, including wilful insubordination, disorderly behavior, refusal to accept communication, and acts subversive of discipline. Following the enquiry report, the company dismissed respondent No. 2 by punishment on 26 February 2004.

Subsequently, Complaint (ULP) No. 168 of 2003 was filed alleging unfair labour practice. An application for interim relief under Section 30(2) of the M.R.T.U and P.U.L.P Act was initially filed but not pressed. The Labour Court rejected a stay on the dismissal order on 27 February 2004. A fresh complaint (ULP No. 85 of 2004) was filed in March 2004 with an application for interim relief to stay the dismissal. The Labour Court allowed the interim relief on 4 August 2004, directing the withdrawal and cancellation of the dismissal order pending final disposal. The petitioner-company challenged this in the Industrial Court, which dismissed the revision application on 1 February 2005. This petition challenges those orders.

Legal Issues Presented

  1. Whether the Labour Court correctly exercised its jurisdiction under Section 30(2) of the M.R.T.U and P.U.L.P Act in granting interim relief by staying the dismissal order without a prima facie finding of unfair labour practice.
  2. Whether the Labour Court and Industrial Court erred in relying on a so-called undertaking allegedly given by the company not to take action against the employee during the enquiry.
  3. Whether the enquiry and dismissal proceedings were conducted properly and whether the nature of charges proved against the employee justified the dismissal.

Arguments of the Parties

Petitioner’s Arguments

  • The impugned order of the Labour Court is grossly erroneous and contrary to established law regarding the powers of the Labour Court under Section 30(2) of the M.R.T.U and P.U.L.P Act.
  • The Labour Court was misled by a purported undertaking that no action would be taken against the employee, which was not actually furnished.
  • The Labour Court failed to consider the prima facie case of unfair labour practice and the nature of charges proved in the enquiry before granting interim relief.

Respondents’ Arguments

  • The respondents supported the view taken by the Labour Court and the Industrial Court in allowing the interim relief and confirming the stay on dismissal.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. Dinanath Shantaram Karekar [1998 (4) L.L.N 14] Termination order is deemed communicated once sent, even if not received by the employee. Labour Court relied on this to hold that dismissal was effective once communicated by the company.
Dalai Engineering (Private) Ltd. v. Ramrao Bapurao Sawant [1992 (1) L.L.N 304] Jurisdiction of Labour Court under Section 30(2) requires a prima facie finding of unfair labour practice before granting interim relief. The Court emphasized that the Labour Court failed to apply this principle and must examine prima facie unfair labour practice and balance of convenience before granting interim relief.
Premier Automobiles Ltd. v. Engineering Mazdoor Sabha [1982 (2) L.L.N 484] Limits of Labour Court’s jurisdiction to issue interim orders under Section 30(2) require prima facie unfair labour practice. Reiterated the necessity of a prima facie finding before interim relief is granted.
Kirloskar Oil Engines Ltd. v. U.B Dharurkar [1986 (2) L.L.N 1009] Similar to Premier Automobiles, delineates jurisdictional limits for interim relief under Section 30(2). Supported the principle that no interim order can be issued without prima facie unfair labour practice.

Court's Reasoning and Analysis

The Court analyzed the powers of the Labour Court under Section 30(2) of the M.R.T.U and P.U.L.P Act, emphasizing that interim relief can only be granted upon a prima facie finding of unfair labour practice. The Labour Court’s reliance on an alleged undertaking by the company not to take action against the employee was found misplaced, especially as no written undertaking was furnished. The Court noted that the Labour Court and the Industrial Court failed to examine the prima facie evidence, the nature of charges proved in the enquiry, and whether the enquiry was conducted properly. The Labour Court’s approach was described as mechanically accepting the undertaking and not applying the correct legal standards concerning unfair labour practice and balance of convenience. The Industrial Court was also criticized for not scrutinizing the correctness of the Labour Court’s order and for upholding it without proper examination. Consequently, the Court restored the application for interim relief to the Labour Court for a fresh hearing uninfluenced by the alleged undertaking, directing adherence to the established legal principles.

Holding and Implications

The Court allowed the petition, quashing and setting aside the orders of the Labour Court dated 4/5 August 2004 and the Industrial Court dated 1 February 2005. The application for interim relief in Complaint (ULP) No. 85 of 2004 was restored to the Labour Court for fresh hearing and decision, to be conducted expeditiously and preferably within six months.

The direct effect of this decision is to require the Labour Court to reconsider the interim relief application by properly applying the legal standards for unfair labour practice and balance of convenience without being influenced by any purported undertaking. No new precedent was set; rather, the Court reinforced adherence to established jurisprudence regarding the jurisdiction and powers of Labour Courts under the M.R.T.U and P.U.L.P Act.

To access the original judgment, please Sign In or Subscribe.

    Anthea Aromatics (Private), Ltd. v. Association Of Chemical Workers And Others

    1. Heard Sri A.D Shetty with Ms. Rita Joshi, T. Shetty for petitioners and Ms. N.D Buch with Ms. Bina Dholakia for respondent Nos. 1 and 2. Respondent No. 3 be deleted forthwith.

    Rule. Ms. N.D Buch waives service of notice of rule for respondent Nos. 1 and 2. By consent of the parties, the writ petition is heard finally.

    2. The learned counsel for the petitioner has also submitted the paper book of the proceedings before the enquiry officer.

    3. The respondent No. 2 is an employee of the petitioner-company and member of the respondent No. 1. He was working as a Technician Grade-III (skilled category) in the production department of Plant II. He was issued two different charge-sheets i.e dated 19 March, 2003 and 24 March, 2003. As his reply was not found satisfactory to the said chargesheets, a joint enquiry was held and it was conducted by Sri K.P Gurav. The enquiry commenced from May, 2003 and the enquiry officer submitted his report on 28 January, 2004 and held that the following charges were proved against the respondent-employee on the basis of evidence placed on record, i.e—

    (a) wilful insubordination and disobedience of lawful and reasonable orders of the superior;

    (b) disorderly and indecent behaviour in the premises of the establishment;

    (c) refusal to accept the communication served; and

    (d) commission of an act subversive of discipline and good behaviour on the premises of the establishment. On receipt of the said enquiry report, a copy of the same was forwarded to the chargesheeted employee vide show-cause notice dated 2 February, 2004 and to the respondent No. 1-union.

    4. On the basis of the chargesheet issued, apprehending the dismissal from service. Complaint (ULP) No. 168 of 2003 under item 1 of Sch. IV of the M.R.T.U & P.U.L.P Act, 1971, along with an application for interim relief under S. 30(2) of the said Act was filed on 18 July, 2003. This application for interim relief was not pressed. The company while addressing a letter, dated 25 February, 2004, to the respondent No. 1 pointed out that while the enquiry was in progress against respondent No. 2, he had separate instances indulging in acts of threatening and intimidating two of the key witnesses in the enquiry and also another workman of the company. Two police complaints were lodged against the respondent No. 2 at the Rabale Police Station and a chapter case came to be filed against him. It was also pointed out that the respondent No. 2 was an habitual offender with several cases of misconduct committed during his employment with the company. Under these circumstances, no lenient view to be taken against the chargesheeted workman and request for voluntary retirement on the basis of monetary claims, could not be accepted. It appears that by an order, dated 26 February, 2004, the company dismissed the respondent No. 2 by way of punishment.

    5. An application Exhibit 17 came to be filed in Complaint (ULP) No. 168 of 2003 for hearing on interim application urgently and the stay to the dismissal order till the hearing of the complaint. This application was rejected by the learned Judge (Mrs. P.P Karnik) of the Labour Court vide her order, dated 27 February, 2004. The learned Judge referred to the decision of the Supreme Court in the case of Union of India v. Dinanath Shantaram Karekar [1998 (4) L.L.N 14], and noted that once the order of termination was sent by the company, it ought to be held to have been communicated to the chargesheeted workman even though he may not have actually received the same.

    6. A fresh complaint registered as Complaint (ULP) No. 85 of 2004 came to be filed with the Labour Court sometimes in March, 2004 along with an application for interim relief so as to stay the operation of dismissal or to temporarily withdraw/cancel the same. The petitioner-company filed its reply and opposed the said application at Exhibit U2. However, by an order dated 4 August, 2004, the learned Judge (P.J Patil) allowed the application for interim relief and directed to withdraw and cancel the order of dismissal, dated 26 February, 2004, pending the hearing and final disposal of the complaint.

    7. Being aggrieved by the said order, the petitioner-company approached the Industrial Court in Revision Application (ULP) No. 68 of 2004 and the learned Member of the Industrial Court at Thane, was pleased to dismiss the revision application by his judgment and order, dated 1 February, 2005. Hence, this petition.

    8. Sri Shetty, the learned counsel for the petitioner-company urged that the impugned order passed by the Labour Court is grossly erroneous and against the law laid down by this Court regarding the powers of the Labour Court while entertaining the application for interim relief under S. 30(2) of the M.R.T.U and P.U.L.P Act. He submitted that without setting out the reasons of prima facie case of unfair labour practice, the learned Judge of the Labour Court was swayed by the purported undertaking furnished in Complaint (ULP) No. 168 of 2003 and subsequently breached by issuing the dismissal order, whereas in fact there was no such undertaking furnished before the Labour Court in the earlier proceedings.

    9. Ms. Buch, the learned counsel for the respondents on the other hand, has supported the view taken by the Labour Court and confirmed subsequently by the Industrial Court.

    10. In the order, dated 27 February, 2004, passed below the application at Exhibit 17 in Complaint U.L.P No. 168 of 2003 the learned Judge of the second Labour Court at Thane (Smt. P.P Karnik) noted in Para. 7 as under:

    “Advocate Anaokar appeared on behalf of respondents. No say is filed by him but he submitted that as per the assurances many meetings took place about the settlement of the dispute but the complainants were making exorbitant demands and therefore, parties could not settle the matter. He further submitted that as such after making many efforts of the settlement, respondents came to know that no settlement can take place in between the parties and thereafter the order of termination was sent to the complainant No. 2. He further submitted that when order of termination is sent to the complainants, the interim relief application is not tenable as there is no pleading regarding the dismissal of complainant No. 2”

    In Para. 4 of the said order, the learned Judge further noted:

    “Admittedly, the case was fixed for hearing on interim relief application, there is no written undertaking given by the respondents regarding not taking any action against the complainant. At the same time, it is necessary to see what is the position at this stage when the order of dismissal of complainant No. 2 is already filed on record…”

    The above quoted observations though indicated that while Complaint (U.L.P) No. 168 of 2003 was pending before the second Labour Court, negotiations were on between the parties, i.e, company and the complainants and efforts were being made to settle the issue regarding the action to be taken against the complainant No. 2, amicably. But it appears that exorbitant monetary demands were being made for the voluntary retirement of complainant No. 2. In any case, there was no written undertaking furnished by the company to the effect that no action would be taken against the chargesheeted workman.

    11. While allowing the application for interim relief in complaint, i.e, ULP No. 85 of 2004, the learned Judge of the 1st Labour Court (Sri P.J Patil) appears to have been overwhelmed by the so-called undertaking by the company and he recorded prima facie finding in favour of the complainant only on the basis of this so-called undertaking. In Para. 17 of his order, dated 4 August, 2004, the learned Judge observed:

    “It is pertinent to note that these cases are not applicable to the instant case on the ground that the company had acted in haste in conducting the enquiry inspite of its Advocate Sri Mohit Kapoor giving assurance to the Labour Court of not taking any action against the concerned workman and the complainants not insisting on the immediate hearing of interim relief application. This had not happened in any of these cases, as such the instant case is different from all these cases, and these cases are not applicable to the instant case.”

    The learned Judge held that the complainants were able to prove prima facie case in their favour. In Para. 19, the learned Judge proceeded to observe as under:

    “The record filed by the complainant shows that the Court was given assurance by the Advocate Sri Mohit Kapoor on behalf of the company not to take any legal action against the concerned workman till next date and thereafter Advocate Sri Mohit Kapoor had withdrawn his Vakalatnama and advocate Sri P.N Anaokar filed his appearance on behalf of Respondent-company thereafter the company proceeded with the enquiry thereby terminating the workman. This itself shows the guilty mind and predetermined mind on behalf of the respondents to complete the enquiry in undue haste without giving reasonable opportunity to the concerned workman to defend himself as such it is obvious that the balance of convenience is favouring the case of the complainants, therefore, I answer this point as balance of convenience is lying in favour of the complainants”.

    12. The learned Judge of the Labour Court did not consider the prima facie evidence, nature of charges and unfair labour practice if any, on the part of the management by issuing the order of dismissal.

    13. This Court has from time to time settled the law governing the powers of the Labour Court while dealing with an application for interim relief under S. 30(2) of the M.R.T.U and P.U.L.P Act. In the case of Dalai Engineering (Private), Ltd. v. Ramrao Bapurao Sawant [1992 (1) L.L.N 304], in Para. 11, at page 310, the learned Single Judge (B.N Shrikrishna, J. as His Lordship then was), observed as under:

    “However wide the sweep of the jurisdiction of the Court to prevent unfair labour practices under the Act, however deep and pervasive the doctrine of social justice, the Labour Court and the Industrial Court are both creature of statute, and have only so much jurisdiction as is conferred upon them thereunder. They cannot assume or usurp them jurisdiction which does not directly flow from the statute under which they function. In the instant case, the jurisdiction to entertain the complaint and grant reliefs therein, interim or final, is conferred on the Labour Court by S. 30 of the Act Sub-sec. (1) of the said section deals with final relief and Sub-sec. (2) with that of interim relief. By the judgments of this Court in the Premier Automobiles Ltd. v. Engineering Mazdoor Sabha [1982 (2) L.L.N 484] and Kirloskar Oil Engines Ltd. v. U.B Dharurkar [1986 (2) L.L.N 1009], the limits of the jurisdiction to issue an interim order under S. 30(2) of the Act, have been surveyed and delineated by this Court. The two judgments have, in unmistakable terms, laid down that the jurisdiction to issue an order comes into existence only upon a finding that there is an unfair labour practice. If it is a final order, there must be a final finding, and, if it is an interim order, there must at least be a prima facie finding of unfair labour practice. This is the bare disideratum without which the Court can issue no order under S. 30. Recourse to the doctrine of social justice or Part III of the Constitution may not be necessary for this purpose. Apart from the jurisdictional limits indicated in these two judgments, the Labour Court must also realise that the general principles of law are still applicable to trials before it, unless the contrary is indicated by statute. One general principle of law is that an interim order is intended to ensure that the proceeding which is pending before the Court arising out of specific cause of action does not become frustrated by any act of a party, pending the hearing of the proceeding. This is really the raison d'etre for an interim order, be it under any statute…”

    14. In the revision application as well, the learned Member of the Industrial Court failed to examine the correctness of the order under challenge and as passed by the Labour Court directing the management to withdraw the order of dismissal and mechanically proceeded to hold that the view taken by the Labour Court did not call for interference. The approach of the Industrial Court is indefensible. It was not sufficient for the Labour Court to consider the so-called undertaking and it was necessary for the Courts below to examine the prima facie case of unfair labour practice and also the issue of balance of convenience. This has not been done. It was also necessary for the Courts below to consider the proceedings before the enquiry officer and whether the enquiry was conducted properly or not. Regards also must be had to the nature of charges held to have been proved by the enquiry officer while deciding the application for interim relief. The Labour Court failed to follow the law laid down by this Court while exercising its powers under s. 30(2) of the m.r.t.u & p.u.l.p act and therefore, it is imperative that the application filed in complaint U.L.P No. 85 of 2004 for interim relief is restored and directed to be heard afresh and without being influenced by the so-called undertaking given by the management.

    15. In the premises, the petition is allowed and the impugned order passed by the Labour Court in complaint (ULP) No. 85 of 2004, dated 4/5 August, 2004 and order, dated 1 February, 2005 passed in Revision Application (ULP) No. 68 of 2004 in Complaint (ULP) No. 85 of 2004, is hereby quashed and set aside. The application at Exhibit U/2 in complaint U.L.P No. 85 of 2004 is hereby restored to file of the First Labour Court at Thane and it is directed that the said application shall be heard and decided afresh and as expeditiously as possible and preferably within a period of six months from the date of first appearance of the parties. The parties to appear before the Labour Court on 21 March, 2005 at 11 a.m

    16. Rule made absolute accordingly with no order as to costs. Writ to go to the Labour Court forthwith.

    Petition allowed.