Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Sec. 92 (3) of the District Board Act
  • Article 56 of the Limitation Act
  • Art. 56 to the facts. Article 56
  • Art. 56 of the Limitation Act
  • Sec. 73 of the Contract Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Sec. 92 (3) of the District Board Act
  • Article 56 of the Limitation Act
  • Art. 56 to the facts. Article 56
  • Art. 56 of the Limitation Act
  • Sec. 73 of the Contract Act
Smart Summary

Summary of the Opinion

Factual and Procedural Background

The plaintiff (now appellant) sued for recovery of Rs. 2,717-82 nP due under a contract to execute earth work and provide barbed-wire fencing for the first defendant Panchayat at Gundugolanu. The plaintiff submitted a tender, was awarded the contract, executed the agreed work and some additional items. The Panchayat refused to pay the full amount claimed. At trial, after framing issues and recording evidence, the trial court found that the plaintiff had done the work and that the amount sued for was correct; it also found the suit was not barred by limitation and decreed the suit.

The first defendant appealed. The lower appellate court agreed that some excess work had been done and the Panchayat was liable for that excess, but dismissed the suit on the ground that Article 56 of the Limitation Act applied because the work was completed more than three years before institution of the suit, making the suit time-barred. The plaintiff appealed to the present court (second appeal), challenging the lower appellate court's application of Article 56 and arguing that Article 115 should apply instead.

Legal Issues Presented

  1. Whether Article 56 of the Limitation Act applies to the present dispute (i.e., whether the claim is a suit for the price of work done at the defendant’s request such that limitation runs from completion of the work).
  2. Alternatively, whether Article 115 of the Limitation Act applies (i.e., whether the suit is in effect one for compensation for breach of contract and the limitation period should start from the date of breach).

Arguments of the Parties

Appellant's Arguments

  • The principal contention advanced by counsel for the appellant was that Article 56 is not applicable to the case and that Article 115 ought to apply (i.e., the suit should be treated as arising from breach of contract rather than price of work done).
  • Counsel attempted to distinguish between work done "at the request of the defendant" and work done pursuant to a contract, arguing that because the plaintiff performed under a contract Article 56 should not govern.
  • Counsel relied upon certain decisions (listed in the opinion) said to support application of Article 115 to contracts with local bodies, although the opinion records that no direct authority was cited refusing application of Article 56 to such cases.

Respondent's (First Defendant / Panchayat) Position

  • The first defendant maintained that the contractor did not carry out certain works entrusted to him, performed works not entrusted to him, and that some work was unsatisfactorily done; hence they refused to pay more than the amount certified by the technical officer.
  • In reply to the plaintiff's notice (Ex. A-13), dated in response to a notice first issued by the plaintiff, the Panchayat asserted defects in the work, identified items done in excess of the sanctioned estimate, and stated that reliance was placed on the Assistant Engineer's certificate which authorized payment only of Rs. 4,581, refusing the balance claimed by the plaintiff.
  • The Panchayat consistently refused liability for the excess amounts and by resolution declined to sanction a revised estimate; thus they maintained the stand of denial of the plaintiff's claim for the excess amounts from the date of their reply.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Mathura Prasad v. Chairman District Board, Sitapur, AIR 1928 Oudh 297 at p. 298 Applied Article 56 in suits by contractors for the price of work done for local bodies. The court cites this decision as supporting the application of Article 56 to claims by contractors for price of work done.
Raunak Ali v. Municipal Board, Unao, AIR 1948 Oudh 49 Applied Article 56 in a contractor's suit for price of work done. Used as authority reinforcing that Article 56 governs such contractor claims.
Sundaram v. Sankara, ILR 9 Mad 334 at p. 342 Another decision applying Article 56 in the context of contractor claims. Cited by the court to fortify its conclusion that Article 56 applies to the facts of this case.
Secretary of State v. Gajjan Singh, AIR 1935 Lah 775 at p. 777 Discussed factual scenario where payment became due only after final bill and certificate; the case did not consider Article 115. The court observes this case did not discuss Article 115 and was decided on the factual finding that payment fell due only after final bill/certificate; the decision therefore does not assist the appellant on the question whether Article 115 applies generally.
M. L. Dalmia and Co. v. Union of India Relied upon by appellant (details not set out in the opinion). The opinion notes the appellant relied on this decision but does not describe its holding; the court addresses the appellant's reliance in general terms and finds the cited authorities not persuasive for applying Article 115 in the present case.
District Board, Allahabad v. Baijnath Prasad, AIR 1934 All 458 Held that, given the contract terms, the time started from the date of accrual of cause of action (i.e., after scrutiny and acceptance of the bill). The court notes this case found no cause of action until after scrutiny and acceptance of the bill; the opinion treats it as distinguishable and not helpful to the appellant.

Court's Reasoning and Analysis

The court proceeded by examining the pleaded facts, the correspondence between the parties and the legal character of the plaintiff's claim.

  1. Identification of the legal question: the court framed the central issue as whether Article 56 or Article 115 of the Limitation Act applied to the plaintiff's claim (para (1)). The lower appellate court had applied Article 56 and held the suit time-barred.
  2. Factual findings relevant to limitation: the plaintiff completed the work on 15-4-1955; the plaintiff issued a first notice (dated 8-11-1955) and the Panchayat replied (Ex. A-13) denying liability for the balance claimed and relying on the Assistant Engineer's certificate which limited payment to Rs. 4,581. The Panchayat consistently refused to sanction payment for excess work and reconfirmed that position by resolution (para (8)).
  3. Distinction between categories of work: the court divided the claim into (a) excess work (work done beyond sanctioned estimate) and (b) work included in the contract but rejected by the Assistant Engineer as unsatisfactory. For excess work, the court accepted the defendant's contention that such work, although disputed as to sanction, was done at the defendant's request to some extent and thus falls within Article 56 (paras (10)–(11)). Because the work was completed on 15-4-1955, limitation for that portion began then and the claim for that portion was time-barred.
  4. Application of Article 56 to contract work generally: the court explicitly rejected a rigid distinction that would exclude contract-based work from Article 56. It held there is no material difference between "at the request of the defendant" and work done under a contract; calling and acceptance of tenders simply records a contractual relationship but the work is still "at the request" of the defendant for purposes of Article 56 (para (12)). Thus Article 56 is applicable to work done under contract as well as to work done at request.
  5. Consideration of Article 115: the court examined Article 115 and observed it applies to suits for "compensation for the breach of any contract" and that the limitation period runs from the date of the breach (para (12)). The court analyzed the nature of the plaintiff's claim and concluded the suit seeks the price for work done, not compensation for breach. Reading "compensation" in Article 115 in light of Section 73 of the Contract Act, the court found a clear distinction between compensation for breach and the price of work done (para (17)).
  6. Requirements for Article 115 to apply: the court emphasized that to bring a case under Article 115, there must be (i) a contract, (ii) a breach of that contract, and (iii) a suit for compensation as a consequence of the breach (para (13)). Where there is no contract (as to excess work) or where the plaintiff seeks the price of the work (not compensation), Article 115 does not apply.
  7. Treatment of authorities relied upon by the parties: the court considered the precedents cited by both sides. It found several earlier decisions where Article 56 had been applied to contractor claims (Mathura Prasad, Raunak Ali, Sundaram v. Sankara) and considered the appellant's cited cases (including Secretary of State v. Gajjan Singh and the Allahabad District Board case) to be distinguishable on their facts or not directly addressing Article 115 in the relevant manner (paras (13)–(25)).
  8. Conclusion of the analysis: having applied the legal principles to the facts, the court concluded that Article 56 governs the claim (both for excess work done at the defendant’s request and for the contract work as characterized in the opinion) and that the claim, insofar as it accrued more than three years before suit (or from the date of unequivocal denial on 8-12-1955), is time-barred (paras (11)–(13), (20)).

Holding and Implications

Holding: The second appeal is dismissed; the court agreed with the lower appellate court that the suit is barred by limitation because Article 56 of the Limitation Act applies to the facts of this case (paras (20)–(22)).

Implications:

  • The lower appellate court's application of Article 56 stands: portions of the plaintiff's claim (particularly for excess work done and work effectively denied by the defendant) are time-barred because limitation ran from completion of work (15-4-1955) or from the date of unequivocal denial (8-12-1955).
  • The court declined to apply Article 115 because the plaintiff's suit was for the price of work done and not for compensation for breach of contract; Article 115 applies to suits for compensation arising from breach and not to price claims for work performed (paras (12)–(13), (16)–(18)).
  • Direct consequence for the parties: the appeal is dismissed and the parties are ordered to bear their own costs throughout (para (21)).
  • The opinion does not purport to establish a broader new precedent beyond applying Article 56 to the facts; it relies on prior authorities and factual distinctions to reach the result.

Order: Appeal dismissed. No leave. Parties to bear their own costs.

    Badarwada Bhima Subbaraju v. Village Panchayat Of Gundugolanu, Reptd. By Its Executive Officer, Gundugolanu .

    (1) The short but important question which this enquiry posses is, whether Article 56 of the Limitation Act applies to the facts of the case or is it Article 115 which is applicable.

    (2) The necessary facts in order to appreciate the contentions raised before me are that the plaintiff who is the appellant before me instituted the suit for recovery of an amount of Rs. 2,717-82 nP. due on the execution of contract work of the first defendant Panchayat at Gundugolanu. It was alleged inter alia in the plaint that tenders were called for by the first defendant for some earth work for deepening the Vindyavasi tank in Gundugolanu village and for providing barbed wire fencing. In response to that call the plaintiff submitted his tender. His tender was finally approved and an agreement was executed by the plaintiff in favour of the first defendant. He completed the work as well as certain other items which were not included in the contract. As the defendant refused to pay the amount, the suit was laid.

    (3) The principal defence raised by the first defendant was that the contractor did not carry out certain works entrusted to him. He carried out certain works which were not entrusted to him and some work was not satisfactorily carried out. The first defendant, therefore, refused to pay any amount more than what was certified by the technical officer.

    (4) The trial court after framing proper issues and recording evidence of the parties, reached the conclusion that the plaintiff has done the work for which he has not been paid by the first defendant and that the amount sued for is the correct amount due to the plaintiff. It was found by the trial Court that the suit is not barred by limitation. The suit was therefore decreed.

    (5) The first defendant carried the matter in appeal. The lower appellate Court found that some excess work was done by the plaintiff and that the first defendant is liable for the same, it however dismissed the suit on the ground that Art. 56 of the Limitation Act applies to the facts of the case and as the work was completed more than three years before the suit. the suit is barred by the statute of limitation. It is this view of the Court below, that is assailed in this second appeal.

    (6) The main contention of Mr. Ramachandra Rao, the learned counsel for the appellant is that Art. 56 is not applicable and it is Art. 115 which must apply.

    (7) In order to appreciate this contention, it is necessary to mention a few more facts before those articles are read.

    (8) The plaintiff issued the first notice on 8-11-1955 to which the first defendant gave a reply Ex. A-13. It mentions among other things, the defects in the work executed by the plaintiff. It clearly mentions several items which were in excess of the estimate sanctioned by the first defendant and also refers to some of the work which, was not satisfactorily carried out by the plaintiff. Relying upon the certificate issued by the Assistant engineer authorising the Panchayat to pay the plaintiff an amount of Rs. 4,581 after deducting the items of work which were unsatisfactory as well as directing the Panchayat to withhold the payment in regard to the work excessively done by the plaintiff for which no estimate was sanctioned by the first defendant, the panchayat mentioned in the said reply that in accordance with the certificate issued by the Assistant Engineer, the Panchayat was willing to pay Rs. 4,581 and refused to pay the balance claimed by the plaintiff. It is pertinent to note in this connection that the plaintiff had claimed in the notice the amount of Rs. 6,411-14-0 but the first defendant agreed to pay on the strength of the certificate issued by the Engineer only Rs. 4,581/- and refused categorically the liability to pay the balance claimed by the plaintiff.

    It is true that subsequently the Panchayat Supervisor seems to have informed the contractor-plaintiff through his letter dated the 29th October 1957 that he has prepared the revised estimate for the repairs to the Vindyavasi Tank, that the same has been approved by the Divisional Engineer and that the same has been forwarded to the Panchayat for taking necessary action. The Panchayat however seems to have stuck to their view through resolution, Ex. B-22, which they took on 25-10-57, It was resolved that as the Engineer has not informed the Panchayat about the work done over the estimate and as the Panchayat resolved by resolution 190 dated the 10th January 1956 that it would not take responsibility for the work done above the estimation, the sanction of the revised estimate was refused. It is thus clear that the first defendant Panchayat stuck to the stand which they had taken in their first reply which they gave on 8-12-1955 and in which they had refused to pay the plaintiff the excess amount which was claimed. On the basis of these facts let me therefore see which Article of Limitation applies.

    (9) The lower appellate Court has applied Art. 56 to the facts. Article 56 mentions that for the price of work done by the plaintiff for the defendant at his request where no time has been fixed for payment. the starting point for such a suit is when the work is done.

    (10) What is argued before me by the counsel for the appellant is that in this case, the contractor has executed the work on the strength of a contract entered into between the parties and therefore it cannot be said that the plaintiff has claimed the price of work done at the request of the defendant. He attempted to make a distinction between the request which is made by the defendant and the contract entered into between the parties. No direct authority however is cited in support of this contention. What is therefore to be seen first is whether the suit amount to the work done by the plaintiff for which the claim is put and relates to the contract entered into between the parties or is it in relation to the excess of the work which the plaintiff has executed as is claimed by the defendant continuously in their stand. It could not be shown to me either from the plaint or from the judgments of the Courts below that what are the items for which the suit is laid that fall within the ambit of the contract and what is the amount claimed for the excess work done.

    As stated earlier, as far as the defendant is concerned, it has been clearly urged at the very first occasion that the amount refused by the first defendant related only to the work done over and above the sanction by the first defendant. It, of course, included some items of work which was not satisfactory and which was rejected by the Assistant Engineer. It is disputed that for the work which is done in excess, no regular sanction of the estimate by the first defendant is there. As far as that work is concerned, it is not seriously disputed that the work was done at the request of the first defendant and to that extent it must follow that the claim is not based upon the contract. As that portion of the claim is for the price of work done by the plaintiff at the request of the defendant, there can be no hesitation in concurring with the conclusion of the lower of the lower court. To that extent Art 56 applies. Admittedly the work was completed on 15-4-55 i.e., the date from which the limitation starts. Calculated thus, it cannot be denied that to that extent the suit is clearly time barred.

    Now in regard to the items which were included in the contract but for which the Assistant Engineer had issued a certificate that the contractor is not entitled to any amount and which was refused by the first defendant, it is clear that even in regard to such items, the first defendant had denied the liability to pay on 8-12-1955 in the reply to the notice. In that case also, therefore, the suit ought to have been filed within three years from the date of the denial. I should not however be understood to have laid down that Art. 56 does not apply to the items of work done by the plaintiff under the contract. I do not see any material difference between the words used in Art. 56 i.e., "at the request of the defendant" and work done under the contract entered into between the parties. Merely because the parties have entered into an agreement or a contract it can hardly be disputed that the work in such cases would not be deemed to have been carried out by the plaintiff at the request of the defendant. After all, when the tenders are called for it is an offer which the defendant had made an a counter offer was made in the form of submission of tenders by the contractor. Once that tender is accepted, it is a contract which was entered into between parties. But merely because the contract is reduced to writing or the work is executed on the basis of such contract, it cannot be said that Art. 56 does not apply.

    There is no other article which was brought to my notice and which says that for the work done under the contract, some other article is applicable. In the either fall under Art. 56 and if it does not fall under the article. It is only the residuary article of 115 that can be attracted. I am however of the clear opinion that it is Art. 56 which is applicable to such cases. I am fortified in my conclusion by the following decisions :

    Mathura Prasad v. Chairman District Board, Sitapur, AIR 1928 Oudh 297 at p. 298, Raunak Ali v. Municipal Board, Unao, AIR 1948 Oudh 49 and Sundaram v. Sankara, ILR 9 Mad 334 at p. 342.

    (11) The first two cases relate to suits by the contractor either against the District Board or the Municipality for the price of the work done viz., to make certain constructions. In all these cases it was Art. 56 which was applied and not Art. 115. I have already said that the learned counsel for the appellant has not cited any direct ruling refusing to apply Art. 56 to such cases. He has however relied on certain decisions which have applied Art. 115 to cases where contracts were executed by the contractor relating to certain local bodies. I will deal with them at the appropriate stage.

    (12) Now coming to Art. 115, it is clear from a reading of that Article that it applies to suits which are instituted for compensation for the breach of any contract, express or implied not in writing, registered and not therein specifically provided for. The time starts from the date when the contract is broken. Admittedly, the suit is not for compensation for the breach of any contract express or implied but it is a suit, even according to the plaint, for the price of the work done. What is argued now is, that as far as the plaintiff is concerned, he fulfilled his part of the obligation arising under the contract but in so far as payment is concerned, when the defendant had refused to discharge his obligation, when the defendant had refused to discharge his obligation, it must be presumed that the defendant has broken the contract. Assuming that it is so, even then, I do not think it advances that case of the plaintiff any further. The contract was certainly broken on the date when the defendant refused to pay the amount claimed by the plaintiff and that was on 8-12-1955. That refusal was unequivocal and it is only to that refusal that the defendant stuck on. The contract therefore was clearly broken on 8-12-1955 was clearly barred by the statute of limitation in arriving at the conclusion that this is not a suit for compensation of a breach of contract.

    The expression 'compensation' used in Art. 115 must be read in the light of Sec. 73 of the Contract Act which uses that term. A reading of that section would reveal that compensation is pair when contracts are broken. The term 'compensation' may bear a different meaning than the word 'damages' but in my view the term 'compensation' does not carry the same meaning as the price for the work done. There is a clear distinction between the two. What is claimed in the suit by the plaintiff is not compensation alleging breach of contract but clearly claiming the price for the work which he had done for the defendant. On this ground also, I do not think Art. 115 can apply to such cases.

    (13) It is beyond doubt that any breach of contract on the part of a party gives rise to an option on the part of the other party. He can either elect to keep the contract alive and seek its enforcement or rescind it and claim compensation. It is to such suits of compensation that Art. 115 applies and not to the former class of cases where contract has not been rescinded without which compensation cannot be claimed. In order to apply Art. 115, therefore, there must be a contract, a breach thereof and the suit must be for compensation. The facts found in the case leave me in no doubt that in regard to excess work there was no contract between the parties, hence no question of breach of contract arises which can give rise to suit for compensation. In regard to the defective work, it is plain that it not being in consonance with the contract, defendant rejected it. If the plaintiff succeeds in proving that it was it was in accord with the contract, what he will get is the price of the work done and not the compensation for any breach of contract. Article 115 in such a case cannot apply.

    (14) The learned counsel for the appellant relied upon the following three cases :

    Secretary of State v. Gajjan Singh, AIR 1935 Lah 775 at p. 777, M. L Dalmia and Co. v. Union of India, and District Board, Allahabad v. Baijnath Prasad, AIR 1934 All 458 (2).

    (15) The Lahore case does not discuss Art. 115 at all and it was not necessary to so discuss and decide because the learned Judge had found on the facts that the amount became payable according to the terms of the contract only after the final bill is prepared and a certificate of completion is issued. In view of that finding it was unnecessary for that court to decide whether Art. 115 applied to not. It is true that the senior Subordinate Judge had applied Art. 115 to the facts of the case. Nevertheless, it was found even by the senior Subordinate Judge that

    "all those claims which would have been included or decided by the measurements in the final bills are within time, because though the final bills were drawn up in December 1921, they were not signed by the Engineer-in-charge till 20th March 1927."

    (16) I do not know this conclusion was reached and how Art. 115 would apply under such a conclusion. In that case the claim within the period of limitation because the starting point was from the date when the bill was sanctioned. There was therefore no occasion for a breach of contract and no question of applying Art 115 consequently would arise.

    (17) The Calcutta case does not render assistance to the appellant be on the facts of that case the learned Judge found that the Government was guilty of breach of contract. If this finding was clearly given, there can be little doubt that Art. 115 applied. It must however be pointed out that there is no reference to Art. 56 or any decision thereupon in that case.

    (18) In the Allahabad case it was found that in view of the terms of the contract the time started from the date of accrual of cause of action.

    (19) No doubt it was a case where a suit was instituted against the District Board for recovery of money due to the contractor for repairs effected. The judgment negatived the contention that Sec. 92 (3) of the District Board Act applies. Negativing that contention and without discussing either Art. 56 or 115, it was found that the contractor could have no cause of action until after the scrutiny of the bill by the District Board servants and the amount was found due. The cause of action therefore arose in that case on the date when the bill was accepted. That case therefore does not help appellant.

    (20) For the reasons which I have given, I do not find any reason to interfere with the conclusion of the Court below that the suit is time barred.

    (21) The second appeal therefore is dismissed. In view of the circumstances of the case, the parties will bear their own costs throughout.

    No leave.

    (22) Appeal dismissed.