(a) Any person who is the owner or authorised occupier of a land or a building where water supply facility is to be made available by the department may apply to the Executive Engineer concerned in prescribed form paying re. 1 for pipe water connection (prescribed form is given in the Annexure A ).
(b) The application so received shall be recorded by the concerned Executive Engineer with reference to the serial No. Of the form and shall submit estimate to the applicant after detailed site inspection and taking measurement as per necessity if found technically feasible. The estimate to prepare will include cost of material, wages of labour and Rs. 500 being the connection fee.
(c) The applicant shall than deposit the amount in the shape of Demand Draft on any National Bank after the estimated amount deposited, the concerned Executive Engineer shall cause to provide water connection as expeditiously as possible and allot a definite consumer number.
(d) Water connection shall be provided with galvanised iron pipe of 15 millimeters diameter or 20 millimeters diameter medium quality.
(e) The water connection shall be provided to the ground floor or any other floor below the ground floor of any building only.
(f) Pipe water connection shall be provided only after full receipt of payment in accordance with the estimate. Every effort shall be made by the department to provide water connection within a period of three months after receipt of payment. In case department cannot provide water connection within a period of three months due to certain delay or inability the department shall intimate the cause of delay to the consumer. In any case, water connection shall depend upon the availability of pipes etc. specials and prevailing weather condition.
(g) In case, for providing pipe water connection if any road is to be crossed, the cost of bringing the road to precondition shall be added to the estimate. Connection shall be made available only after receiving permission for such road crossing from the authority.
(h) Any private land, required to be used for providing water connection, shall be settled by the consumer before starting the work.
(i) Supply tank or point from where pipe water connection is to be made shall be decided by the Department before starting the work.
(j) Similarly if any owner of a land or a building desires of shifting of any existing water supply pipe passing through his/her land or by the side of his/her building may apply in the same form for shifting. The procedure will be same as mentioned in the aforesaid clauses of this section.
(k) No house water connection shall be transferred from one place to another.