2013 BHC 182
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2013 BHC 182
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

This appeal under section 37 of the Arbitration and Conciliation Act, 1996 was filed by the appellant against an order and judgment dated 24 July 2009 of the Principal District Judge, Raigad, Alibaug. The District Judge had rejected the appellant's application under section 34 of the Act (Civil Misc. Application No. 66 of 2005). In that application the appellant challenged two heads of the arbitral award: (i) an award of interest at the rate of 21% in the sum of Rs. 2,42,107/- and (ii) a claim for pendente lite interest in the sum of Rs. 4,68,263/-. The appellant contended that the arbitrator and the District Judge erred in allowing interest contrary to an express contractual prohibition.

Legal Issues Presented

  1. Whether an arbitral tribunal can award interest for the pre-reference period or pendente lite interest despite an express contractual provision (Clause 16(2) of the General Conditions of Contract) prohibiting payment of interest on amounts payable to the contractor.
  2. Whether the learned Principal District Judge was correct in rejecting the appellant's section 34 challenge while relying on section 29 of the Arbitration Act, 1940 (as applied by the District Judge), instead of applying the provisions of the Arbitration and Conciliation Act, 1996 (notably section 31(7)(a) and section 28(3)).

Arguments of the Parties

Appellant's Arguments

  • The appellant relied on Clause 16(2) of the General Conditions of Contract which provides that "No interest will be payable upon the earnest money or the security deposit or amounts payable to the Contractor under the contract" (with an exception for government securities). This clause, it was submitted, prohibits any payment of interest to the contractor under the contract.
  • Relying on Clause 16(2), the appellant submitted that the arbitrator ignored the express contractual term and, in breach of the contract, allowed interest by placing reliance on section 29 of the Arbitration Act, 1940, which was not applicable to the present reference under the Arbitration and Conciliation Act, 1996.
  • The appellant relied upon Supreme Court authority in Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat, (2010) 8 SCC 767 (para 19) and on Union of India v. Krafters Engineering Co. (Civil Appeal No. 2005 of 2007) — both of which were cited to demonstrate that where parties have agreed that no interest shall be payable, the arbitral tribunal cannot award interest for the period from cause of action to award under section 31(7)(a) of the 1996 Act.
  • The appellant also relied upon a Division Bench decision of this Court in Union of India v. Shyam Constructions (unreported, 19 October 2012) which followed Sree Kamatchi and held that specific contractual bars against payment of interest preclude arbitral awards of pre-reference or pendente lite interest.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat, (2010) 8 SCC 767 Holds that, by reason of section 31(7)(a) of the Arbitration and Conciliation Act, 1996 — and the phrase "unless otherwise agreed by the parties" — an arbitrator is bound by contractual terms that bar payment of interest; therefore, where parties have agreed no interest shall be payable, the arbitral tribunal cannot award interest for the period from the cause of action to the date of award. The Court treated the facts as identical to those in Sree Kamatchi and relied on that authority to conclude that the arbitrator erred in awarding pre-reference and pendente lite interest contrary to Clause 16(2) of the contract.
Union of India v. Krafters Engineering Co. (Civil Appeal No. 2005 of 2007; reported 2011 (5) Mh.L.J (S.C) 707) Considered an identical contractual clause and held that where the contract prohibits payment of interest, the arbitrator could not award interest under section 31(7) of the Arbitration and Conciliation Act, 1996. The Court regarded this decision as following Sree Kamatchi and forming part of the supporting jurisprudence for setting aside interest awards made contrary to a contractual prohibition.
Union of India v. Shyam Constructions (Division Bench of this Court, unreported, 19 October 2012, Appeal (L) No. 309 of 2011) Applied Sree Kamatchi to specific claims, holding that contractual clauses prohibiting interest and clauses barring claims arising from extensions must be respected and an arbitral tribunal cannot award interest or compensation contrary to such express contractual terms. The Court relied on this Division Bench decision to demonstrate how clause 16(2) and clause 17(iii) had been interpreted in analogous factual circumstances and to support the view that the arbitrator had acted contrary to the contract.
Ramnath International Construction (P) Ltd. v. Union Of India (cited in the opinion) Interpreted contractual conditions that no claim for compensation shall be admitted arising as a result of extensions; such contractual clauses preclude awards of compensation for extensions. Cited by the Court as precedent for interpreting clause 17(iii) of the General Conditions of Contract and for the proposition that awards of compensation contrary to express contractual bars are unsustainable.
Chaitanya Electrical Private Limited v. General Manager Central Railway (single judge decision; appeal dismissed 17 March 2003) Interpreted clause 17(3) (a clause similar to clause 17(iii) considered in the opinion) and supported the view that contractual bars on claims arising from granted extensions defeat awards of compensation. Referred to by the Court as supporting authority on the proper interpretation of clause 17(iii) and to show consistent judicial treatment of such contractual provisions.

Court's Reasoning and Analysis

The Court's analysis proceeded by comparing the express contractual provision (Clause 16(2) of the General Conditions of Contract) with the statutory scheme under the Arbitration and Conciliation Act, 1996 — specifically section 31(7) (and its sub‑provision (a)) and section 28(3).

Step-by-step reasoning as reflected in the opinion:

  • The Court identified Clause 16(2) which expressly prohibits payment of interest on earnest money, security deposits or amounts payable to the contractor under the contract (government securities excepted).
  • The Court observed that section 31(7) of the 1996 Act permits an arbitral tribunal to include interest in an award "unless otherwise agreed by the parties." The Court treated the clause "unless otherwise agreed by the parties" (referred to at times as section 31(7)(a) in the opinion) as binding the arbitrator to the contractual agreement between the parties regarding interest.
  • The Court noted section 28(3), which makes it clear that an arbitral tribunal shall decide in accordance with the terms of the contract, and concluded it was not open to the tribunal to ignore an express contractual bar.
  • The Court relied upon Supreme Court authority (Sree Kamatchi and Union of India v. Krafters) and a Division Bench decision of this Court (Union of India v. Shyam Constructions) interpreting similar contractual clauses and applying the statutory provision in the 1996 Act to hold that awards of pre-reference or pendente lite interest are impermissible where the contract bars interest.
  • On the basis of these authorities and statutory provisions, the Court concluded that the arbitrator had acted contrary to the express terms of the contract by awarding interest and that the learned Principal District Judge had erred by relying on section 29 of the Arbitration Act, 1940 (an inapplicable provision) instead of properly applying the 1996 Act. The Court further characterised the award as being contrary to public policy insofar as it awarded interest in breach of the contract.
  • Accordingly, the Court found the impugned award and the District Judge's order unsustainable and proceeded to set aside the award insofar as it granted interest.
  • The Court also addressed a practical interim measure: an earlier ad‑interim order of this Court (dated 16 April 2010) had permitted the respondent to withdraw Rs. 7,10,370/- deposited by the appellant, subject to an undertaking to return it if the appellant succeeded. The Court provided directions depending on whether the amount had been withdrawn.

Holding and Implications

Core Ruling: The appeal is allowed, the impugned order dated 24 July 2009 of the Principal District Judge is set aside, Civil Misc. Application No. 66 of 2005 is allowed, and the impugned award insofar as the grant of interest is concerned is set aside.

Direct consequences and directions given by the Court:

  • If the respondent withdrew the sum of Rs. 7,10,370/- pursuant to this Court's ad-interim order of 16 April 2010, the respondent is directed to pay that amount with interest at 6% per annum to the appellant within four weeks from the date of the present order.
  • If the respondent did not withdraw that amount pursuant to the 16 April 2010 order, the office is directed to return the said amount to the appellant with accrued interest, if any.
  • No order as to costs was made.

Broader implications: The opinion rests its decision on the interplay between an express contractual bar on interest and the statutory provision in section 31(7) of the Arbitration and Conciliation Act, 1996 (the "unless otherwise agreed by the parties" language). The decision applies existing precedent (as cited) to the facts; the opinion does not purport to announce a novel or new legal principle beyond applying those authorities and statutory provisions to set aside the award of interest.

Appeal allowed.
To access the original judgment, please Sign In or Subscribe.

    Union Of India v. S.N Naik And Bros., Panvel .

    1. By this appeal filed under section 37 of the Arbitration and Conciliation Act, 1996, appellant seeks to challenge an order and judgment dated 24th July, 2009 passed by the Principal District Judge, Raigad, Alibaug rejecting application filed by the appellant under section 34 of the Act (Civil Misc. Application No. 66 of 2005). By the said Civil Misc. Application No. 66 of 2005, the appellant had challenged two claims out of several claims viz. grant of interest at the rate of 21% in the sum of Rs. 2,42,107/- and pendente lite interest in the sum of Rs. 4,68,263/-.

    2. Mr. Sureshkumar, the learned counsel appearing on behalf of the appellant places reliance on clause 16 (2) of General Conditions of Contract which reads thus:—

    16(2) No interest will be payable upon the earnest money or the security deposit or amounts payable to the Contractor under the contract, but Government securities deposited in terms of Sub-Clause (1) of this clause will be repayable with interest accrued therein.

    3. Relying upon this clause, the learned counsel appearing for the appellant submits that such clause prohibits payment of interest from the appellant to the respondent contractor. It is submitted that though the clause prohibits payment of interest on the earnest money or the security deposit or any amount payable to the contractor under the contract, the learned arbitrator ignored the terms of the contract and in breach thereof has allowed the claim for interest placing reliance upon section 29 of the Arbitration Act, 1940. It is submitted that though admittedly the present reference was under the provisions of Arbitration and Conciliation Act, 1996, the learned District Judge placed reliance upon section 29 of Arbitration Act, 1940 while rejecting the application filed by the appellant which is totally misplaced and on the face of it, perverse. The learned counsel invited my attention to the judgment of the Supreme Court in case of Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat, (2010) 8 SCC 767 and more particularly para (19). Supreme Court has considered the same clause which was relied upon by the appellant and was part of the contract. After considering the same, the Supreme Court in para (19) has held as under:—

    19. Section 37(1) of the new Act by using the words ‘‘unless otherwise agreed by the parties” categorically clarifies that the arbitrator is bound by the terms of the contract insofar as the award of interest from the date of cause of action to date of award. Therefore where the parties had agreed that no interest shall be payable, arbitral tribunal cannot award interest between the date when the cause of action arose to date of award.

    4. The learned counsel also invited my attention to the judgment of the Supreme Court in the case of Union of India v. Krafters Engineering Co. in Civil Appeal No. 2005 of 2007 [since reported in 2011 (5) Mh.L.J (S.C) 707] in which the Supreme Court has considered the identical clause and had taken a view that in view of the prohibition, the learned arbitrator could not have awarded interest under section 31(7) of the Arbitration and Conciliation Act, 1996.

    5. The learned counsel also invited my attention to the unreported judgment of this Court delivered on 19th October, 2012 by the Division Bench in case of Union of India v. Shyam Constructions in Appeal (L) No. 309 of 2011. The Division Bench of this Court has followed the judgment of the Supreme Court in case of Sree Kamatchi Amman Constructions (supra) and in para 6 has held thus:—

    6. Counsel appearing on behalf of the Appellant has challenged the arbitral award insofar as the following claims came to be awarded viz. Claim Nos. 1, 2, 5, 10, 12 and 13. The principal basis of the appeal is that the award of the claims by the arbitral Tribunal was contrary to the express terms and conditions of the contract. Hence, in order to evaluate these submissions, it would be necessary to consider the arbitral award and the specific contractual conditions governing each head of claim.

    i) Claim No. 1 was in respect of work done but not paid in respect of which the arbitral Tribunal awarded interest at the rate of 10% per annum from 20 November, 1997 to 3 June, 2002, in the total amount of Rs. 2,04,813/-. The arbitral Tribunal has noted that an amount of Rs. 4,55,140/- was paid over to the contractor only on 21 May, 2002 and on this ground awarded interest for the period of delayed payment. Clause 16(2) of the General Conditions of Contract provides as follows:

    “16(2) : No interest will be payable upon the Earnest Money and Security Deposits or amounts payable to the Contractor under the Contract”

    The effect of this very clause was considered by the Supreme Court in a judgment in Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat (supra). The Supreme Court held that if there is a specific bar against payment of interest in the contract, the arbitrator cannot award any interest for the pre-reference period or pendente lite. The Supreme Court held that in view of the specific provisions made in the Act of 1996 in section 31(7)(a) by the use of the words “unless otherwise agreed by the parties”; the arbitrator was bound by the terms of the contract in regard to the award of interest from the date of the cause of action to the date of the award. Hence, where the parties had agreed that no interest shall be payable, the arbitral Tribunal cannot award interest between the date when the cause of action arose to the date of the award. In view of the express provisions of clause 16(2) of the General Terms of Contract, the award of interest was prohibited and there was an agreement between the parties as “otherwise agreed” within the meaning of section 31(7)(a). Section 28(3) makes it clear that in all cases the arbitral Tribunal shall decide in accordance with the terms of the contract. It is not open to the arbitral Tribunal to ignore the terms of the contract. Evidently the arbitral Tribunal has acted contrary to the terms of the contract while awarding this claim;

    ii) Claim No. 2 related to the refund of security deposit on which interest has been awarded by the arbitral Tribunal at the rate of 10% between 19 November, 1998 and 10 October, 2002. Here again, it is evident that the award of interest is directly in the teeth of Clause 16(2);

    iii) Claim No. 5 is for the award of interest on delayed payments. The arbitral Tribunal has hereagain awarded interest at 10% per annum. What has been held in regard to the award of interest in respect of claim Nos. 1 and 2 will also apply to the award under this head. The award of interest for the pre-reference period was clearly contrary to the provisions of clause 16(2);

    iv) Claim No. 10 was for the underutilization of overheads. The arbitral Tribunal noted that the contract was extended for approximately two years from 25 March, 1994 to 31 March, 1996. The Tribunal came to the conclusion that the liability for this delay ought to be shared equally by both the parties and that the claimant - Respondent should be compensated for the non-utilization of overheads for a period of one year for which an award in the amount of Rs. 1.56 lacs was made. Now insofar as this aspect is concerned, clause 17(iii) of the General Conditions of Contract provides as follows:

    “(iii) In the event of any failure or delay by the Railway to hand over to the contractor possession of the lands necessary for the execution of the works or to give the necessary notice to commence the works or to provide the necessary drawings or instructions or any other delay caused by the Railway due to any other cause whatsoever, then such failure or delay shall in no way affect or vitiate the contract or alter the character thereof or entitle the contractor to damages or compensation therefore, but in any such case, the Railway may grant such extension or extensions of the completion date as may be considered, reasonable.”

    v) When the Respondent sought an extension of the period for completion, it had declared that it shall not claim any compensation. The Appellant had while granting extension clarified that the contractor would not be entitled to make claims whatsoever against the Railways by virtue of the extension being granted nor would the Railways entertain or consider any such claim, if made. A similar provision was interpreted in the judgment of the Supreme Court in Ramnath International Construction (P) Ltd. v. Union Of India In that case, the contractual conditions stipulated that no claim in respect of compensation or otherwise howsoever arising as a result of the extensions granted shall be admitted. The Supreme Court held that in view of the clear terms of the contract, the award of compensation had been rightly set aside by the High Court. A similar view was taken in a judgment of a learned Single Judge of this Court in Chaitanya Electrical Private Limited v. General Manager Central Railway while interpreting the provisions of clause 17(3). An appeal against the decision was dismissed by the Division Bench on 17 March, 2003. In view of the express terms of the contract, the arbitral Tribunal has manifestly erred in ignoring the contract and awarding the claim;

    vi) Claim No. 12 and Claim No. 13 related to the award of compensation for the underutilization of labour force and of centering and shuttering respectively. Here again the arbitral Tribunal has granted compensation on account of the extended period of the contract by partly apportioning the liability to the Appellant. The award under both these heads is clearly unsustainable in view of the specific conditions contained in Clause 17(iii) noted earlier.

    6. In my view, the facts of this case are identical to the facts before Supreme Court in case of Sree Kamatchi Amman Constructions (supra) which has been followed by the Supreme Court subsequently in case of Union of India v. Krafters Engineering Co. (supra).

    7. Section 31(7) of the Arbitration and Conciliation Act, 1996 provides that unless otherwise agreed by the parties, the tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made. In view of the express provision of Clause 16(2) of the General Conditions of Contract prohibiting payment of interest, read with section 31(7)(a), it is clear that the payment of interest was prohibited and thus the learned arbitrator has acted contrary to the terms of the contract and also contrary to section 31(7)(a) of the Act. The award is thus contrary in conflict with public policy. The learned District Judge has also ignored the provisions of section 31(7)(a) and also the prohibition clause prohibiting payment of interest and erroneously relied upon section 29 of Arbitration Act, 1940 which was not applicable to the facts of this case. The award as well as the order passed by the learned District Judge is clearly unsustainable. The impugned award as well as the judgment delivered by the learned Judge is thus contrary to the law laid down by the Supreme Court and this Court and also contrary to section 31(7)(a) and deserves to be set aside.

    8. I, therefore, pass the following order:—

    (a) Appeal is allowed.

    (b) Impugned order passed by the learned Principal District Judge on 24th July, 2009 is set aside.

    (c) Civil Misc. Application No. 66 of 2005 is allowed.

    (d) Impugned award insofar as grant of interest is concerned, is set aside.

    (e) By ad-interim order passed by this Court on 16th April, 2010, this Court had permitted respondent to withdraw a sum of Rs. 7,10,370/- deposited by the appellant on the respondent's furnishing undertaking that the amount would be brought back or paid to the appellant in the event of appellant succeeding in this appeal. If the respondent has withdrawn any such amount pursuant to the liberty granted by this Court on 16th April, 2010, the respondents are directed to pay the said amount with interest at the rate of 6% per annum to the appellant within four weeks from the date of this order. If the respondent has not withdrawn the amount as per order passed by this Court on 16th April, 2010, the office is directed to return the said amount to the appellant with accrued interest if any.

    (f) Appeal is allowed in the aforesaid terms.

    (g) No order as to costs.

    Appeal allowed.