Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 37 of the Arbitration Act
  • The Arbitration and Conciliation Act, 1996 (for short, 'the Arbitration Act')
  • The 1983 Act
  • Section 34 of the Arbitration Act
  • The Arbitration Act
  • Section 11(6) of the Arbitration Act
  • Section 7 of the Madhya Pradesh Rural Road Development Authority 983 Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Article 142 of the Constitution of India
  • Section 7 of the 1983 Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 37 of the Arbitration Act
  • The Arbitration and Conciliation Act, 1996 (for short, 'the Arbitration Act')
  • The 1983 Act
  • Section 34 of the Arbitration Act
  • The Arbitration Act
  • Section 11(6) of the Arbitration Act
  • Section 7 of the Madhya Pradesh Rural Road Development Authority 983 Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Article 142 of the Constitution of India
  • Section 7 of the 1983 Act
Smart Summary

Factual and Procedural Background

M/s. Modern Builders (“the appellant”) was awarded a contract by the State of Madhya Pradesh to construct a minor bridge. The contract contained an arbitration clause (Clause 29). On 9 November 2001 the Executive Engineer, National Highway Division, rescinded the contract. The appellant first invoked Section 7 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (“1983 Act”) and approached the Madhya Pradesh Arbitration Tribunal. By order dated 19 April 2010, the Tribunal ruled that because the contract contained an arbitration clause, the Arbitration and Conciliation Act, 1996 (“Arbitration Act”) and not the 1983 Act governed the dispute.

Relying on that order, the appellant filed a petition under Section 11(6) of the Arbitration Act before the High Court of Madhya Pradesh, which appointed a retired District Judge as sole arbitrator. On 25 April 2014 the arbitrator passed an award in favour of the appellant for Rs 6,52,235 with interest.

The State and its Executive Engineer (“the respondents”) challenged the award under Section 34 of the Arbitration Act; the District Judge dismissed their challenge. The respondents then filed an appeal under Section 37 before the High Court, which set aside the award solely on the ground that, as per Madhya Pradesh Rural Road Development Authority v. L.G. Chaudhary Engineers and Contractors (2018) 10 SCC 826, the 1983 Act applied. The appellant appealed to the Supreme Court of India.

Legal Issues Presented

  1. Whether the High Court was justified in setting aside the arbitral award on the ground that the 1983 Act, and not the Arbitration Act, governed the dispute.
  2. Whether an arbitral award may be annulled for lack of jurisdiction when the objection to the tribunal’s jurisdiction was not raised at the appropriate stage.
  3. Whether, in the circumstances, the Supreme Court should exercise its powers under Article 142 of the Constitution to do complete justice.

Arguments of the Parties

Appellant's Arguments

  • The precedent relied upon by the High Court (M.P. Rural Road Development Authority) was delivered four years after the award and is inapplicable because para 17 of that decision states that an award should not be annulled on jurisdictional grounds if no timely objection was raised.
  • The respondents never challenged the Section 11(6) appointment order nor invoked Section 16(1) of the Arbitration Act before the arbitrator; hence the objection is belated.
  • The award should therefore stand, and the High Court’s order be set aside.

Respondents' Arguments

  • The written statement before the arbitrator did raise the plea that the appellant ought to have proceeded under Section 7 of the 1983 Act; hence the jurisdictional objection was timely.
  • Under the ratio of M.P. Rural Road Development Authority, the 1983 Act is the correct governing statute notwithstanding the contract’s arbitration clause, and the award is liable to be set aside.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Madhya Pradesh Rural Road Development Authority & Anr. v. L. G. Chaudhary Engineers and Contractors, (2018) 10 SCC 826 The 1983 Act applies to disputes involving the State of Madhya Pradesh even where an arbitration clause exists; however, para 17 carves out an exception where an award is already made and jurisdictional objection was not timely raised. The Supreme Court relied on para 17 to hold that the award should not be annulled merely on jurisdictional grounds because the respondents did not raise the objection at the proper stages.

Court's Reasoning and Analysis

1. The Court noted that the appellant initially invoked the 1983 Act, but the Arbitration Tribunal itself directed the parties to the Arbitration Act. Acting on that order, the appellant sought appointment of an arbitrator under Section 11(6), which the High Court granted without any jurisdictional objection from the respondents.

2. The respondents did not challenge the Section 11(6) order, nor did they invoke Section 16(1) before the arbitrator. Their first substantial reliance on the 1983 Act occurred only in written submissions and later before the High Court under Section 37.

3. Referring to para 17 of M.P. Rural Road Development Authority, the Court emphasised that where an award has already been made and timely objection is absent, the award “may not be annulled only on that ground.”

4. Given the modest quantum (Rs 6.52 lakh plus interest) and the procedural history demonstrating acquiescence by the State, the Court found it inequitable to invalidate the award solely on the statutory route chosen.

5. Even assuming the 1983 Act technically applied, the Court invoked its power under Article 142 to ensure complete justice, determining that the High Court should examine the Section 37 appeal on merits without disturbing the award on jurisdictional grounds.

Holding and Implications

HELD: The Supreme Court allowed the appeals, set aside the High Court’s orders dated 5 July 2021 and 12 May 2022, and restored Arbitration Appeal No. 45 of 2019 to the High Court’s file. The High Court is directed to decide the appeal on merits, expressly precluded from setting aside the award on the basis of the 1983 Act’s applicability.

Implications: The decision preserves the arbitral award pending a fresh merits review and clarifies that belated jurisdictional objections will not suffice to annul an award. It underscores the Supreme Court’s willingness to exercise Article 142 powers to prevent procedural technicalities from defeating substantive justice, but it sets no new binding precedent beyond the specific factual matrix.

To access the original judgment, please Sign In or Subscribe.

    M/S MODERN BUILDERS v. THE STATE OF MADHYA PRADESH

    2024 INSC 643

    Civil Appeal No.8528-8529 of 2024 Page 1 of 7 NON-REPORTABLE

    IN THE SUPREME COURT OF INDIA

    CIVIL APPELLATE JURISDICTION

    CIVIL APPEAL NOS. 8528-8529 OF 2024 M/s. Modern Builders … Appellant versus

    State of Madhya Pradesh & Anr. … Respondents

    J U D G M E N T

    ABHAY S. OKA, J.

    FACTUAL ASPECTS

    1. The appellant was appointed as a contractor to construct a minor bridge. The contract was granted by the first respondent-State of Madhya Pradesh. The second respondent, Executive Engineer, National Highway Division Sagar, Madhya Pradesh, rescinded the contract by the letter dated 9th November 2001. Clause 29 in the work order incorporated an arbitration clause. The appellant requested for constitution of an Arbitral Board. The said request was rejected. Even the subsequent representation was rejected. Therefore, the appellant applied for a reference to the Madhya Pradesh Arbitration Tribunal, Bhopal (for short, 'the Arbitration Tribunal') in accordance with Section 7 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (for short, 'the

    1

    1983 Act'). By the order dated 19th April 2010, the Arbitration Tribunal concluded that as there was an arbitration clause in the contract, the provisions of the Arbitration and Conciliation Act, 1996 (for short, 'the Arbitration Act') would apply. The Tribunal held that only when there is no arbitration clause, the provisions of the 1983 Act would apply. In view of this order, the appellant filed a petition under Section 11(6) of the Arbitration Act before the High Court of Madhya Pradesh at Jabalpur. The petition was allowed, and a retired District Judge was appointed as the Arbitrator. An award was made on 25thApril 2014 by the learned Arbitrator.

    2. The respondents, aggrieved by the said award, preferred a petition under Section 34 of the Arbitration Act before the District Judge, Jabalpur. The learned District Judge dismissed the said petition. The respondents filed an appeal under Section 37 of the Arbitration Act before the High Court for challenging the order of the District Court. By the impugned judgment, the High Court proceeded to set aside the award only on the ground that as held by this Court in the case of Madhya Pradesh Rural Road Development Authority & Anr. v. L. G. Chaudhary Engineers and Contractors1, the provisions of the 1983 Act were applicable.

    SUBMISSIONS

    3. The learned counsel appearing for the appellant invited our attention to the fact that the decision in the case of

    1 (201 8) 1 0 SCC 826

    2

    Madhya Pradesh Rural Road Development Authority1was rendered nearly four years after the date of the award. However, in paragraph 17 of the said decision, this Court observed that if an award is already made by the Arbitrator and if the objection to the jurisdiction of the Arbitrator was not raised at an appropriate stage, the award may not be annulled only on that ground. The learned counsel submitted that the respondents did not challenge the order passed by the High Court under Section 11(6) of the Arbitration Act. The objection regarding the jurisdiction of the arbitration was raised only in the written submissions. He would, therefore, submit that the award could not have been set aside based on the decision of this Court.

    4. The learned counsel appearing for the respondents submitted that, as seen from the award, a contention was raised in the written statement filed before the Arbitrator that the appellant should have taken recourse to Section 7 of the

    1 983 Act. Therefore, the dispute was raised at the appropriate stage, and hence, paragraph 17 of the decision in the case of

    Madhya Pradesh Rural Road Development Authority1will have no application.

    CONSIDERATION OF SUBMISSIONS

    5. A few factual aspects will have to be noted. After the contract granted to the appellant was rescinded, the appellant invoked Section 7 of the 1983 Act by approaching the Arbitration Tribunal. By the order dated 19thApril 2010, the Arbitration Tribunal held that in view of the arbitration clause

    3

    in the contract, the 1983 Act will have no application and the appellant will have to take recourse to the Arbitration Act. In view of this order, the appellant invoked the jurisdiction of the High Court under Section 11(6) of the Arbitration Act by filing a petition for the appointment of an Arbitrator. The order dated 22ndJuly 2011 passed by the High Court on the said petition shows that the respondents' opposition was only on the merits of the claim. The objection based on the applicability of the

    1 983 Act was not raised. The respondents did not challenge the order of appointment of the Arbitrator passed by the High Court under Section 11(6) of the Arbitration Act. Even before the learned Arbitrator, Section 16(1) of the Arbitration Act was not invoked to raise the jurisdiction issue. However, in the written statement filed before the Arbitrator, the contention regarding the applicability of the 1983 Act was raised. 6. Now, coming to the decision of this Court in the case of Madhya Pradesh Rural Road Development Authority1, after considering the provisions of the 1983 Act and the Arbitration Act, in the light of Section 2(4) of the Arbitration Act, this Court held that although there was an arbitration clause, the 1983 Act would apply. In paragraph 17, this Court held thus: "17. We do not express any opinion on the applicability of the State Act where award has already been made. In such cases if no objection to the jurisdiction of the arbitration was taken at relevant stage, the award may not be annulled only on that ground."

    4

    7. As noted earlier, in the facts of the case, before taking recourse to the Arbitration Act, the appellant had taken recourse to Section 7 of the 1983 Act. The order of the Arbitration Tribunal, holding that the Arbitration Act will apply, led the appellant to file a petition under Section 11(6) of the Arbitration Act, which was not objected to on the grounds of the applicability of the 1983 Act. The objection of the State government was confined to the merits of the claim. The award is only in the sum of Rs. 6,52,235/- with interest. The award was made on 25thApril 2014. Therefore, in the facts of the case, it will be unjust to set aside the award only on the ground of the failure of the appellant to take recourse to the 1983 Act. In fact, the appellant had taken recourse to the 1983 Act before seeking the appointment of an Arbitrator. In this case, as can be seen from the impugned judgment, the award has been set aside only on the ground that the appellant ought to have invoked the provisions of the 1983 Act. Even assuming that the observations in paragraph 17 of the decision in the case of

    Madhya Pradesh Rural Road Development Authority1, are not applicable, this is a fit case to exercise jurisdiction under Article 142 of the Constitution of India to ensure that complete justice is done. Therefore, by setting aside the impugned judgment, the appeal under Section 37 of the Arbitration Act will have to be restored with a request to the High Court to decide the same on merits.

    8. Accordingly, the impugned judgment dated 12thMay 2022 passed in the Review Petition no.584 of 2021, and the

    5

    order dated 5thJuly 2021 passed in the Arbitration Appeal no.45 of 2019 are set aside. The Arbitration Appeal no.45 of 2019 is restored to the file of the High Court of Madhya Pradesh, Principal Seat at Jabalpur. The restored appeal shall be listed before the roster bench on Monday, the 30th September 2024. The parties to the appeal shall appear before the High Court on that day, and no further notice of the date fixed in the appeal shall be given to the parties. On 30th September 2024, the High Court will fix a date for hearing the restored appeal, which shall be heard and decided in accordance with law and in light of the observations made in this judgment. All the issues on the merits of the restored appeal under Section 37 of the Arbitration Act are kept open. However, the award should not be set aside on the grounds of the applicability of the 1983 Act.

    9. If the appellant has withdrawn the amount paid as per the award, the same shall be deposited by the appellant with the High Court within two months from today. The amount shall be invested by the High Court in a fixed deposit with any nationalised bank till the disposal of the restored appeal. The

    High Court, while deciding the appeal, shall pass appropriate directions regarding the withdrawal of the amount with interest accrued thereon. 10. Subject to the observations made above, the appeals are allowed.

    6

    11. The Registry shall forward a copy of this judgment to the Registrar (Judicial) of the High Court of Madhya Pradesh at Jabalpur.

    ...…………………………….J.

    (Abhay S Oka)

    ..…………………………….J.

    (Augustine George Masih)

    New Delhi; August 30, 2024.

    7

    Use AI to get other relevant cases.

    Comments

    M/S MODERN BUILDERS v. THE STATE OF MADHYA PRADESH
    (Aug 30, 2024)