Summary of the Legal Opinion

Factual and Procedural Background

On 22 August 1908 the plaintiff executed a mortgage bond in favour of Bohra Khetpal for Rs. 5,000, mortgaging two villages (Araila and Sikrari) as security. On 7 June 1913 the plaintiff sold the village Araila to the defendant (Har Govind) for Rs. 5,000 and left the entire consideration with the defendant to be paid to the prior mortgagee (Bohra Khetpal); the sale-deed contained a condition that if the vendee failed to pay that money to the prior mortgagee and that failure led to litigation, the vendee would be responsible for costs and interest from the date of deposit.

The defendant did not pay the Rs. 5,000 to the prior mortgagee until 22 September 1916. Subsequently the plaintiff sold the other village (Sikrari) and paid Rs. 3,174 out of that sale to Bohra Khetpal in satisfaction of the remaining mortgage money. The plaintiff claimed compensation for the extra interest he had to pay to Bohra Khetpal as a consequence of the defendant's delay.

At first instance (the trial Court) the plaintiff was awarded Rs. 987-8-0 (or, in another part of the record, an award calculated to cover extra interest up to redemption) for the extra interest. On first appeal (the lower appellate Court / District Judge) the decree was set aside on the ground that the claim was barred by limitation (the appellate Court relied on Article 116 of the Limitation Act). The case then proceeded in this appeal, where the principal contested issue was whether the suit was within time and which provision of the Limitation Act (and related principles of contract/indemnity law) governed the accrual of the cause of action.

Legal Issues Presented

  1. Whether the plaintiff is entitled to compensation (damages) for the extra interest paid to the prior mortgagee as a result of the defendant's delay in paying the Rs. 5,000 left with him for that purpose.
  2. From what date did the cause of action for damages accrue for limitation purposes — (a) the date the contract was broken (7 June 1913), or (b) the date of actual injury (when plaintiff actually suffered loss by paying extra interest or by being indemnified)?
  3. Which provision of the Limitation Act applies to the suit: Article 116, Article 83 (or Article 61 / Article 62), or does Section 24 of the Limitation Act shift the period to the date of actual injury?
  4. Whether the contractual provision in the sale-deed should be treated as (i) a simple covenant to pay the sum, (ii) an express indemnity, or (iii) an implied indemnity for damages resulting from delay — and the effect of that classification on limitation.

Arguments of the Parties

Appellant's (Plaintiff's) Arguments

  • The plaintiff claimed compensation for extra interest which he had to pay Bohra Khetpal because the defendant delayed paying the Rs. 5,000.
  • On limitation, plaintiff's counsel argued that if Article 116 governed the suit, Section 24 of the Limitation Act should be read with it so that the cause of action accrues when specific injury results (i.e., when the plaintiff actually had to pay extra interest), making the suit within time.
  • Alternatively, the plaintiff contended that Article 61 or Article 83 of the Limitation Act might be applicable (the first judge in the opinion refers to Article 83 in his reasoning).

Respondent's (Defendant's) Arguments

  • The defence asserted that the money could not be paid to the mortgagee because of the plaintiff's own fault: the plaintiff had represented that Rs. 5,000 would redeem the mortgage without accounting for interest, and the mortgagee refused to accept Rs. 5,000 in part satisfaction.
  • The defendant pleaded limitation: the breach occurred on 7 June 1913 (the date of the sale and deposit) and, under Article 116 of the Limitation Act (time running from the date the contract was broken), the claim is time-barred after six years from that date.
  • It was also argued (on the record) that Article 62 might apply, though the first judge rejected its applicability because the money was payable by the defendant to the mortgagee rather than payable by defendant to plaintiff.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Raghubar Rai v. Jairaj (1912) 34 All 429 Held that a plaintiff could sue on a covenant for payment even before any injury/damage occurred (i.e., breach itself constituted a cause of action in English law). The lower appellate Court relied on this authority to contend the plaintiff could have sued immediately after the breach (7 June 1913). The court in this opinion questions the applicability of that English rule to Indian law under the Contract Act and Limitation Act.
Sarju Misir v. Ghulam Husain (1921) 63 IC 87 Held (in dissent to Raghubar Rai) that there are two causes of action: one for breach and a second for injury resulting from it. Cited as authority supporting the view that the cause of action for damages accrues upon actual injury, not merely on breach; used to support application of Section 24 and limitation from date of actual injury.
Ram Barai Singh v. Mohendra Prasad (1912) 16 CWN 1040 Authority for the proposition that a contract of indemnity may be express or implied. Used to support the proposition that, even if the sale-deed contained a particular indemnity clause, there could also be an implied indemnity to cover damages from delay.
Kumar Nath Bhuttacharjee v. Nobo Kumar Bhuttacharjee (1899) 26 Cal 241 Discussed in the context of when limitation runs and whether a plaintiff could sue before injury; used in earlier English-law-based reasoning. Cited by the court as part of authorities where English rule suggested immediate accrual on breach; the present Court considered such English authority inapplicable to Indian contracts governed by the Contract Act.
Kaliyammal v. Kolandavela Goundar AIR 1918 Mad 1135 Held that a stipulation by a vendee to discharge an existing incumbrance is in the nature of an indemnity. Cited as support for treating similar contractual stipulations as indemnities; the first judge in the opinion (earlier portion) relied on it to argue Article 83 applied, but another judge distinguished it on grounds that the Privy Council authority relied upon was not a Limitation Act decision.
Hakim Ali Khan v. Dalip Singh (1913) 11 ALJ 478 Held in somewhat similar circumstances that limitation would run from the date when the plaintiff was indemnified (i.e., date of actual injury/indemnification). Relied upon to support the holding that Article 83 (and the concept of limitation running from actual injury) applies and that the suit was within time.
Izzat-un-nissa v. Partab Singh (1909) 31 All 583 (Privy Council) Privy Council decision referred to in connection with treatment of contractual stipulations as indemnities (used in the Madras decision Kaliyammal). The opinion notes that the Privy Council decision was not concerned with the Limitation Act and thus was not authoritative on limitation questions; Kaliyammal's reliance on it did not control the Limitation Act analysis here.
Battley v. Faulkner (1820) 3 B & Ald 288 English authority used to support the proposition that a plaintiff may sue on breach without waiting for damage to occur. Was invoked in Raghubar Rai; this Court held that the English approach (as exemplified by Battley) is not directly applicable to contracts governed by Indian law (Contract Act) in relation to the accrual of cause of action for damages.

Court's Reasoning and Analysis

The opinion contains a developed analysis of liability, contractual characterisation (covenant versus indemnity), and limitation. The Court proceeded in the following steps (reflecting the reasoning in the text):

  1. Establishing the facts: the defendant received Rs. 5,000 on 7 June 1913 to be paid to the prior mortgagee; no time for payment was specified so payment was to be made within a reasonable time; the defendant did not pay it until 22 September 1916; as a result the plaintiff ultimately paid a larger amount of interest to the mortgagee and sought to recover the excess.
  2. Characterising the contractual obligation: the sale-deed included a clause that, if the vendee failed to pay and litigation resulted, the vendee would be liable for costs and interest from the date of deposit. The Court considered whether this clause constituted (a) an indemnity only operative on litigation brought by the prior mortgagee, (b) a covenant to pay irrespective of litigation, or (c) an express indemnity plus an implied indemnity to cover damages resulting from delay.
  3. Considering limitation provisions and competing Articles: the Court examined whether Article 116 (time running from date contract broken), Article 61 or Article 83 (relating to suits to enforce security or for damages from delay), or Article 62 applied. The Court held that Article 61 did not apply (the plaintiff did not pay the money on defendant's behalf), and Article 62 was inapplicable because the defendant's obligation was to the mortgagee rather than to the plaintiff under that Article.
  4. Analysing the effect of Section 24 of the Limitation Act: the Court focused on Section 24 (which commutes the period of limitation to run from the time when “injury results” in cases where an act does not give rise to a cause of action unless specific injury results). The critical question was whether the breach itself gave rise to a cause of action for damages under Indian law, or whether under the Contract Act a cause of action for damages arises only when actual loss results.
  5. Comparing English authority and Indian law: the Court discussed English authorities (as adopted in Raghubar Rai and related cases) that treat breach itself as giving rise to a cause of action. The Court concluded that this English approach is not applicable under Indian law as embodied in Section 73 of the Indian Contract Act (which confines recovery to loss or injury actually caused), except where Section 74 (liquidated damages/penalty) applies.
  6. Interpreting the sale-deed clause and indemnity principles: the Court observed that the sale-deed's clause might be read distributively — it referred to a failure to pay and to a suit, and either contingency could give a right to sue if the plaintiff was damnified. The Court also relied on authorities recognising that an indemnity may be express or implied; even if the express indemnity clause did not operate (because no suit by the mortgagee followed), an implied indemnity could arise to cover damages caused by delay.
  7. Applying limitation: the Court concluded that Section 24 applies so that, where a cause of action for damages depends on the occurrence of actual injury, limitation runs from the date of actual injury (the date on which the plaintiff suffered loss or paid the extra interest). The Court noted authorities (e.g., Hakim Ali Khan) where limitation was held to run from the date of indemnification/actual injury, and held that the instant suit was filed within the applicable period (within three years from the date of actual injury as considered under Article 83 by one judge and under Section 24/Article 116 framework by another).
  8. Rejection of the immediate-accrual rule for Indian contracts: the Court emphasised that under Section 73 of the Contract Act a suit for compensation requires injury already caused (except where Section 74 applies). Therefore, unlike the English rule in Battley and the decisions that followed it, a mere breach without actual damage did not, under Indian law, give an immediate right to claim damages; limitation should run from the date of actual injury.
  9. Conclusion on remedies and limitation: applying the foregoing principles to the facts, the Court held that the plaintiff's right to sue for damages accrued on the date when he actually incurred the extra interest (or was otherwise indemnified), and that the present suit was within time. Accordingly, the appeal was to be allowed and the decree of the first instance restored.

Holding and Implications

Holding: The appeal was allowed. The Court ordered that the decree of the lower appellate Court be set aside and that the decree of the Court of first instance (trial Court) be restored. Costs were awarded to the plaintiff in this Court and in the lower appellate Court.

Direct Effect on the Parties: The plaintiff's decree for compensation (damages for extra interest) as awarded by the trial Court is restored; the defendant's limitation defence as upheld by the lower appellate Court is rejected.

Implications (as stated or necessarily confined by the opinion): The Court emphasised that under the Indian Contract Act (Section 73) recovery of damages is tied to loss actually caused; therefore, for suits where the cause of action for damages arises only upon actual injury, Section 24 of the Limitation Act fixes the period of limitation from the date the injury results. The opinion thus treats the date of actual injury (or indemnification/payment of extra interest) as the relevant accrual date for limitation in such cases. The opinion did not purport to create a novel statute but applied and reconciled existing contract and limitation principles to the facts; it restores the plaintiff's remedy in the circumstances of this case.


Note: This summary is prepared strictly from the text of the provided opinion and does not add information beyond that opinion.

    Kedar Nath v. Har Govind

    1. The question for consideration in this case is whether the plaintiff is entitled to compensation for the loss said to have been 'occasioned to him by the delay of the defendant in paying certain money, which was left with him by the plaintiff for the payment of a prior mortgage.

    2. On the 22nd August 1908 the plaintiff executed a mortgage bond in favour of Bohra Khetpal for Rs. 5,000 repayable with interest at 6 per cent. per annum, and mortgaged two villages, Araila and Sikrari, as security for its repayment. On the 7th June 1913 the plaintiff sold the village Araila to Har Govind, the defendant-respondent, for Rs. 5,000 and left the entire consideration with him for payment to the prior mortgagee. That money was to have been paid according to the sale-deed in part satisfaction of the prior mortgage. But Har Govind did not pay that money till the 22nd September 1916. One of the conditions entered in the sale-deed was that if the vendee failed to pay the money left with him for payment to Bohra Khetpal thus occasioning a suit in Court (aur naubat nalish ki adalat tak pahunche) then the vendee shall be responsible for costs and interest on the money aforesaid from the date of the deposit.

    3. Subsequently the village Sikrari was proclaimed for sale in execution of a decree for money obtained by Peare Lal against the plaintiff, and in order to pay up the money due by him to Peare Lal and the balance of the mortgage money due to Bohra Khetpal and certain other debts due by him to other creditors, the plaintiff sold that village to Maqsud Ali Khan for Rs. 10,000, out of which Rs. 3,174 were paid by him to Bohra Khetpal in satisfaction of the remaining money due on the mortgage.

    4. In the present case the plaintiff claims the extra interest which he had to pay Bohra Khetpal in consequence of the delay of the defendant in paying the sum of Rs. 5,000, left with him for payment to Bohra Khetpal. The trial Court awarded him Rs. 987-8-0 as compensation on account of the extra interest, which he had to pay to Bohra Khetpal on the said sum of Rs. 5,000 from the 7th June 1913 to the 22nd September 1916, the date on which that money was actually paid to the prior mortgagee. The lower Court however held that the claim was barred by limitation, as the cause of action for a suit for damages for a breach of the contract accrued to the plaintiff on the date the contract was broken, namely, the date on which the sale was effected and the money was left with the vendee for payment to the prior incumbrancer.

    5. The sale-deed fixed no time for the payment of the money, and ordinarily it would be presumed that the parties intended that the payment should be made within a reasonable time. There is nothing to show why the payment of the money was withheld for over three years. Under the mortgage the plaintiff was liable to pay interest on the mortgage money at 6 per cent. per annum compoundable yearly. Had the money been paid within a reasonable time from the date of the deposit, the plaintiff would 'have been relieved from the liability for interest on that amount. Not having been so paid, the liability for interest continued and the plaintiff eventually had to pay a much larger sum than he otherwise would have been liable to pay for the balance of the mortgage money.

    6. It is urged that the right of the plaintiff to sue for damages accrued when the contract was broken and he had to pay extra interest by reason of the breach. The contract provided that if the vendee failed to pay the money left with him to the prior mortgagee and that occasioned a suit in Court, the vendee will indemnify him for his costs and for interest on the amount left with him from the date of the deposit.

    7. It might be argued that the covenant was only intended to apply if, as a result of that failure, a suit was brought by the prior mortgagee for the recovery of his money. But the suit to which the covenant refers might be either a suit brought be the prior mortgagee for the recovery of his money, or a suit which a party to the contract may have to bring either to enforce the covenant or to claim damages for its breach. The contingencies there referred to, namely, a failure to pay and a suit need not moreover be cumulative. They may be read distributively as suggestive of a possible succession of events, any one of which might give the plaintiff a right to sue, if he is damnified. Though a suit by Bohra Khetpal was averted by the plaintiff paying up his mortgage money he has had to pay a much larger amount to him than he would have had to pay, had the amount left by him with the vendee been paid to Bohra Khetpal within a reasonable time of the deposit; and he is entitled consequently to ask the vendee to pay him that amount.

    8. A man who is entrusted with a certain sum of money with instructions to pay the same to another person, to whom the person paying the money is liable, keeps the money left with him at his peril. If he fails to pay it or delays payment beyond a reasonable time, he is liable for damages as for a breach of a contract to the extent of the loss which the person depositing the money has suffered by reason of such failure or delay, and under Article 83 of the Indian Limitation Act a suit to enforce the security or for damages resulting from the delay is within time if filed within three years from the date of actual injury. The decision in Raghubar Rai v. Jairaj (1912) 34 All 429 does not apply because there was no contract of indemnity in that case and the plaintiff had not made any payment entitling him to enforce any indemnity. The damages in this case accrued when the plaintiff had to sell one of his properties to Maqsud Ali Khan and to pay the balance of the mortgage money claimed by Bohra Khetpal out of the sale consideration far any excess of what he would have been otherwise liable for had the money left with the defendant been paid in time. The suit was filed within three years from that date.

    9. As pointed out in Ram Barai Singh v. Mohendra Prasad (1912) 16 CWN 1040 and Kumar Nath Bhuttacharjee v. Nobo Kumar Bhuttajee (1899) 26 Cal 241 a contract of indemnity may be express or implied. Hare there was an express agreement for the payment of the indemnity in case the vendee failed to pay the money left with him, and the plaintiff was landed in a suit in consequence, Either of these contingencies read distributively was sufficient to give him a cause of action. If the two contingencies be read together there would still be an implied contract of indemnity to pay the plaintiff the damage which he may suffer in consequence of the delay and the suit would be within time. In Kaliyammal v. Kolandavela Goundar AIR 1918 Mad 1135 a stipulation in a contract for sale whereby the vendee agreed to discharge an existing incumbrance on the property sold was treated as in the nature of an indemnity. In Kumar Nath Bhuttacharjee v. Nobo Kumar Bhuttacharjee (1899) 26 Cal 241 and Hakim Ali Khan v. Dalip Singh (1913) 11 ALJ 478 it was held in somewhat similar circumstances that limitation would run from the date when the plaintiff was indemnified. Article 83 of the Limitation Act therefore applies to the case and the suit is within time. The appeal ought, therefore, to be allowed and the decree of the lower appellate Court set aside and that of the Court of first instance restored with costs here and in the lower appellate Court.

    Ashworth, J.

    10. This is a plaintiff's appeal. It arises out of a suit brought by the plaintiff against the defendant for damages for breach of contract. The contract was embodied in a sale-deed executed by the plaintiff on the 7th of June 1913 in favour of the defendant and in respect of village Acharela. Some five years earlier, on the 22nd of August 1908, the plaintiff had hypothecated this village and another village Sakhrari to one Khetpal Singh for Rs. 5000. In the sale-deed of the 7th of June 1913 the vendee was left the whole of the purchase price, namely, Rs. 5,000 and covenanted to pay it to the mortgagee Khetpal Singh as the principal of the mortgage. No time was specified for payment, and so it must be deemed that he was to pay it within reasonable time. It has not been shown that it was not reasonable to pay it at once and so it may be taken for the purposes of this suit that the contract was to pay the mortgagee the Rs. 5,000 on the 7th of June 1913. The money was not paid to the mortgagee but in connexion with insolvency proceedings against the plaintiff it was ultimately paid to the plaintiff on the 22nd September 1916. After this the plaintiff redeemed the mortgage on the 15th of August 1917 and had to pay Rs. 3,174-8-0 interest. His case is that if the Rs. 5,000 had been paid by the defendant to the mortgagee on or about the 7th of June 1913, when the defendant was liable to pay it, the interest due at that time would have been only Rs. 2,227-8-0. The plaintiff accordingly sued for the difference namely, Rs. 1,147

    11. The defence was that the money could not be paid by the defendant to the mortgagee owing to the plaintiff's fault. The plaintiff had represented that the Rs. 5,000 would redeem the mortgage not taking into account the interest. The mortgagee refused to take the Rs. 5,000 in part payment of what was due under the mortgage. The plea of limitation was also taken, it being contended that the breach of the agreement occurred on the 7th of June 1913, and that limitation expired after six years from that date.

    12. The first Court held that the defendant never tendered the Rs. 5,000 to the mortgagee, and that the contention was false that the mortgagee refused to take it. It held that a cause of action accrued when the plaintiff had to pay the extra interest to Khetpal Singh in respect of the sum of Rs. 5,000 in question. It gave the plaintiff a decree for the interest on Rs. 5,000 at the rate mentioned in the mortgage bond from the 7th of June 1913 to the date of payment of the interest, namely, the 15th of August 1917.

    13. In first appeal the District Judge found that the defendant never tendered the money as he was bound to do, to the mortgagee Khetpal Singh but he held that the suit was barred by limitation under Article 116 of the Limitation Act. In this appeal plaintiff's counsel argued that if the suit is governed by Article 116, then reading that article with Section 24 of the Limitation Act the suit is within time, as the cause of action accrued when the plaintiff had to pay up the extra interest. Alternatively he argues that Article 61 or Article 83 is applicable. I hold that Article 61 has no application. The plaintiff did not pay this money for the defendant, as the mortgagee had no right to claim it from the defendant. Nor was the contract one to indemnify. It is true that the sale-deed contained a provision that If the defendant did not pay up the Rs. 5,000 and litigation ensued, the defendant would be liable for costs of the litigation and for interest on the said sum.

    14. This, however, was a particular clause constituting a contract of indemnity in a certain event. As the mortgagee never sued the plaintiff, nor was the plaintiff involved in a suit in consequence of the non-payment, this indemnity did not come into operation. The fact of this special provision being incorporated would not prevent the contract as a covenant to pay the money, apart from a suit by the mortgagee, taking effect. It is true that in a Madras case, Kaliyammal v. Kolandavela Goundan AIR 1918 Mad 1135 a similar contract was held to be one of indemnity governed by Article 83 on the strength of the Privy Council decision in Izzat-un-nissa v. Partab Singh (1909) 31 All 583. But the Privy Council decision relied on was not one with reference to the Limitation Act, and I consider was no authority for the view that this contract would fall under Article 83. On behalf of the respondent it has been argued that Article 62 might apply, but the money was never payable under the covenant by the defendant to the plaintiff but by the defendant to the mortgagee. Accordingly the only question I consider that arises on the score of limitation is whether Article 116 will apply, and if so, should it be read with Section 24. There can be no doubt that the suit is one based on breach of a registered contract: and that the time begins to run under Article 116 from the date when the contract is broken. The contract was broken on the 7th of June 1913. The suit would therefore be time-barred unless we can invoke 8. 24 of the Limitation Act which is as follows:

    In the case of a suit for compensation for an act which does not give rise to a cause of action unless some specific injury actually results therefrom, the period of limitation shall be commuted from the time when the injury results.

    15. In construing this section I can give no meaning to the word specific' unless possibly it means 'that can be specified. It appears to me to be redundant. We have therefore to see whether the act of the defendant in not paying or tendering the Rs. 5,000 to the mortgagee gave rise to a cause of action independently of the fact that plaintiff had to pay the additional interest in 1917. In other word could the plaintiff have sued on the breach of contract before 1917 when he paid the additional interest. The lower appellate Court has relied on Raghubar Rai v. Jairaj Rai (1912) 34 All 429 decided by a Bench of two Judges of this Court. It was there held on the authority of an English case. Battley v. Faulkner (1820) 3 B & Ald 288 and of Kumarnath Bhuttacharjee v. Nobo Kumar Bhuttacharjee (1899) 26 Cal 241, that the plaintiff could have brought an action on the convenant even before any injury was done or damage took place, in order that the person making the convenant (i.e. defendant) should place him in a position to meet the liability the defendant had undertaken on the plaintiff's behalf In other words, plaintiff could have sued at any time after the 7th of June 1913 for the Rs. 5,000. If this is correct then Section 24 of the Limitation Act could not be invoked.

    16. This decision in Raghubar Rai v. Jairaj Rai (1912) 34 All 429 was dissented from by a later decision of a Bench of two Judges of this Court, Sarju Misir v. Ghulam Husain (1921) 63 IC 87. In that decision it was held that the plaintiff got one cause of action owing to breach of the contract and a second cause of action owing to injury resulting from it.

    17. It appears to me that if the decision in Raghubar Rai v. Jairaj (1912) 34 All 429, that the plaintiff could have sued at an earlier date for mere breach before incurring actual loss is correct, then it must be admitted that the suit is barred by limitation, but I consider that the English law as set forth in Raghubar Rai v. Jairaj Rai (1912) 34 All 429 and Kumarnath Bhuttacharjee v. Nobo Kumar Bhuttacharjee (1899) 26 Cal 241 is not applicable to contracts in India. A reference to the terms of Section 73 of the Contract Act shows that a suit can only be brought for injury or loss already caused and not for prospective loss. Section 74 makes an exception to this. It allows a suit to be based on mere breach when the contract names a sum to be paid in case of mere breach or contains a stipulation by way of penalty. The present contract did neither. Where there is no sum named to be paid in case of breach or stipulation by way of penalty, under India Law a mere breach of the covenant by omission to pay, as in this case, gives no right to a claim for compensation, and the suit will come within the language of Section 24 of the Limitation Act. I may mention that the word act in section 24 will include an omission (see Section 3(2) of the General Clauses Act, 10 of 1897.) It has been urged that Section 24 is only applicable to suits based on tort, but no reason appears for holding this. The English Law in fact makes the mere breach the cause of action and treats the injury as the measure of the compensation for the breach. Section 73 of the Contract Act treats the loss or injury actually incurred as the cause of action. It has been suggested that, if this view is correct, the promisee has no remedy until years after the breach. It may be remarked, however, that in such a case as this' though he could not sue for specific performance ( the time for performance having passed), he could have treated the agreement as void under Section 55 of the Contract Act and sued for restoration of the Rs. 5,000 under Section 65. In the present case the suit is one for damages for breach and is not one for compensation by reason of avoidance of the contract.

    18. For these reasons I hold that the period for limitation runs from the data of actual injury and that the suit is within time. This was held in a case based on facts materially the same in Hakim Ali Khan v. Dalip Singh (1913) 11 ALJ 478, by a Bench of this Court, though the law was not discussed therein.

    19. I would, therefore, allow the appeal with costs here and in the lower appellate Court and restore the decree of the first Court.