AMICUS AI
Citation Codes
Neutral Citations
2007 INSC 563
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 11(6) of the Act, Section 16 of the Act
  • the 1983 Income Tax Act
  • Article 16(3)
  • Section 37 of the Act
  • Model Law, Article 16
  • The Arbitration Act, 1940
  • Section 37 of the Arbitration and Conciliation Act, 1996
  • Preamble to the Arbitration and Conciliation Act, 1996
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • Section 34(2)(a)(v) of the Act
  • Section 34 of the Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2007 INSC 563
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 11(6) of the Act, Section 16 of the Act
  • the 1983 Income Tax Act
  • Article 16(3)
  • Section 37 of the Act
  • Model Law, Article 16
  • The Arbitration Act, 1940
  • Section 37 of the Arbitration and Conciliation Act, 1996
  • Preamble to the Arbitration and Conciliation Act, 1996
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • Section 34(2)(a)(v) of the Act
  • Section 34 of the Act
Smart Summary

Factual and Procedural Background

Gas Authority of India Ltd. (GAIL) awarded four construction contracts at its Petro-Chemical Complex, Dibiyapur, U.P., to M/s Keti Construction (I) Ltd. during 1995. Clause 107 of Contract (D) dated 28-9-1995 contained an arbitration mechanism requiring the appointing authority to forward a panel of three names to the contractor, who would then select a sole arbitrator.

Disputes arose regarding execution and cost. On 16-2-1999 GAIL forwarded a panel naming Justice N.N. Goswami (Retd.) first. Reiterating this panel on 15-11-1999, GAIL proposed one arbitrator for all four contracts to make the process “cost effective, economical and quick.” Notwithstanding this, the contractor, after issuing a notice on 17-7-1999, unilaterally appointed Brig. Nardip Singh (Retd.) on 10-12-1999.

GAIL appointed Justice Goswami on 13-1-2000, who issued notices to both parties. The contractor did not appear or file a claim; Justice Goswami made a “no-claim” award on 19-4-2000.

The contractor’s Section 34 petition to set aside the award was dismissed by a Single Judge of the Delhi High Court on 20-10-2003. A Division Bench, however, allowed the contractor’s Section 37 appeal on 7-12-2004, set aside the award, and directed Brig. Singh to proceed with arbitration. GAIL obtained special-leave to appeal, leading to the present Supreme Court judgment.

Legal Issues Presented

  1. Whether GAIL’s prior transmission of a panel of arbitrators satisfied Clause 107, thereby rendering its appointment of Justice N.N. Goswami valid and the contractor’s appointment of Brig. Nardip Singh invalid.
  2. Whether the contractor could, under Section 34(2)(a)(v) of the Arbitration and Conciliation Act, 1996, challenge the composition of the Arbitral Tribunal after having failed to raise a jurisdictional objection before the arbitrator in terms of Section 16 of the Act.
  3. Whether the Division Bench erred in setting aside the “no-claim” award in the absence of any procedural or jurisdictional infirmity attributable to Justice Goswami’s appointment.

Arguments of the Parties

Appellants (GAIL)

  • A panel containing Justice Goswami’s name was sent on 16-2-1999 and reiterated on 15-11-1999 for all four contracts; hence the contractor had no authority to nominate another arbitrator.
  • Letters dated 31-7-1999 and 15-11-1999 asked the contractor to choose from the panel; silence amounted to acceptance of GAIL’s procedure.
  • The contractor never challenged Justice Goswami’s jurisdiction under Section 16 and abstained from the arbitral proceedings; consequently, Section 34 could not be invoked to contest tribunal composition.
  • A single arbitrator for all disputes would be economical and in line with the contractual intent.

Respondent 1 (Keti Construction)

  • GAIL failed to send a panel within 30 days of the contractor’s notice dated 17-7-1999, thereby forfeiting its right under Clause 107. Consequently the contractor validly nominated Brig. Nardip Singh on 10-12-1999.
  • The subsequent appointment of Justice Goswami on 13-1-2000 contravened the agreement and vitiated the award, attracting Section 34(2)(a)(v).
  • The letter allegedly sent by GAIL’s advocate on 31-7-1999 was neither registered nor proved to have been received; hence it could not cure the contractual default.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Konkan Railway Corpn. Ltd. v. Rani Construction (P) Ltd., (2002) 2 SCC 388 Arbitral Tribunal, even if allegedly improperly constituted, may rule on its own jurisdiction under Section 16 (“kompetenz-kompetenz”). Cited to emphasise that the contractor should have raised any objection to tribunal composition before Justice Goswami; failure to do so weighed against Section 34 relief.
SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618 While overruling Konkan on another aspect, it affirmed that tribunals constituted without recourse to Section 11 retain full Section 16 powers. Used to reinforce the continued validity of the “kompetenz-kompetenz” doctrine in the present context.
Sundaram Finance Ltd. v. NEPC India Ltd., (1999) 2 SCC 479 Provisions of the 1996 Act must be interpreted consistently with the UNCITRAL Model Law. Invoked to justify reliance on international commentary supporting early jurisdictional objections before the arbitral forum.

Court's Reasoning and Analysis

The Supreme Court conducted a factual examination of correspondence between the parties and found that:

  • GAIL had complied with Clause 107 by forwarding a panel on 16-2-1999 and reiterating it on 15-11-1999 for all four contracts; this satisfied the contractual pre-condition.
  • The contractor’s unilateral appointment of Brig. Singh after receiving the reiterated panel was “wholly unjustified.” GAIL’s insistence on a single arbitrator for multiple contracts was deemed reasonable.
  • Section 16 provides that objections to tribunal jurisdiction must be raised before the tribunal. The contractor, despite notice, never appeared before Justice Goswami or filed a statement of claim; consequently, there was no contemporaneous challenge to jurisdiction.
  • Consistent with Konkan Railway and SBP & Co., failure to invoke Section 16 precluded the contractor from attacking tribunal composition under Section 34 absent “good reasons,” which were not demonstrated.
  • The Division Bench erred in compartmentalising correspondence and overlooking the broader, common-sense reading of contractual dealings that covered all four contracts.

Holding and Implications

Appeal Allowed; Division Bench judgment dated 7-12-2004 set aside; Single Judge order dated 20-10-2003 dismissing the Section 34 petition affirmed; costs awarded to GAIL throughout.

The immediate effect is that Justice Goswami’s “no-claim” award stands and Brig. Nardip Singh’s appointment is nullified. The decision reinforces two principles: (i) contractual procedures for constituting the tribunal must be observed, and (ii) parties must raise jurisdictional objections before the arbitrator under Section 16; failure to do so significantly limits recourse under Section 34. No new legal precedent was created, but existing jurisprudence on tribunal competence and party conduct was firmly applied.

To access the original judgment, please Sign In or Subscribe.

    Gas Authority Of India Ltd. And Another v. Keti Construction (I) Ltd. And Others

    G.P Mathur, J.— Leave granted.

    2. This appeal, by special leave, has been preferred against the judgment and order dated 7-12-2004 of a Division Bench of the Delhi High Court by which the appeal filed by M/s Keti Construction (I) Ltd., the contractor (Respondent 1 herein) under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) was allowed and the judgment and order dated 20-10-2003 of a learned Single Judge by which the petition filed by Respondent 1 under Section 34 of the Act was dismissed, was set aside and the award given by the arbitrator (Respondent 2 in the present appeal) on 19-4-2000, was also set aside. It was further directed that Brig. Nardip Singh (Retd.) who was appointed by Respondent 1 shall proceed with the arbitration in accordance with law and give the award.

    3. Gas Authority of India Ltd. (GAIL, Appellant 1 herein) awarded four contracts for its project at Petro-Chemical Complex, Dibiyapur, District Etawah (U.P) to M/s Keti Construction (I) Ltd., Indore (the contractor), which is arrayed as Respondent 1 in the present appeal. All the four contracts were awarded in the year 1995 and they related to construction of certain types of houses for GAIL Vihar Township, premix bitumen carpeting and repair of roads in GAIL Vihar Colony, construction of external sewerage line and construction of certain residential quarters in UPPC Complex, Dibiyapur. Certain disputes arose between the parties regarding completion of the construction work in accordance with the design and cost of construction, etc. The contracts entered into between the parties contained arbitration clause. Appellant 1 referred the dispute with regard to contract dated 28-9-1995 for arbitration to Justice N.N Goswami (Retd.) who was formerly a Judge of the Delhi High Court. The arbitrator gave a “no-claim award” on 19-4-2000. Respondent 1 filed a petition under Section 34 of the Act in the Delhi High Court for setting aside the award. A learned Single Judge who heard the petition, after detailed discussion of the material on record, found that the petition was devoid of merits and accordingly dismissed the same by the judgment and order dated 20-10-2003. Respondent 1 then preferred an appeal before the Division Bench of the High Court under Section 37 of the Act which allowed the same by the judgment and order dated 7-12-2004 and set aside the award of the arbitrator. It was further directed in the order that parties shall appear before Brig. Nardip Singh (Retd.) who had been nominated as arbitrator by Respondent 1 (the contractor) and he shall proceed in accordance with law and give the award.

    4. The principal ground on which the petition under Section 34 of the Act had been filed by Respondent 1 was that it had invoked the arbitration clause by sending a notice to Appellant 1 on 17-7-1999 and accordingly Appellant 1 was required to send a panel of three names for arbitration within 30 days of receipt of notice. Since Appellant 1 did not respond to the notice and did not send a panel within 30 days, it forfeited its right to nominate a panel and thereafter Respondent 1 sent its own panel on 28-10-1999. Appellant 1 again did not make any response and did not choose anyone from the panel nominated by Respondent 1 and accordingly it informed Appellant 1 on 10-12-1999 that it had selected Brig. Nardip Singh (Retd.) as an arbitrator and the said arbitrator entered upon the reference on 6-1-2000. Appellant 1 appointed Justice N.N Goswami (Retd.) as an arbitrator subsequently on 13-1-2000, which appointment was not valid being contrary to the terms of the agreement entered into between the parties. Respondent 1 thus submitted that the appointment of Justice N.N Goswami (Retd.) was invalid and the award given by him was liable to be set aside in view of Section 34(2)(a)(v) of the Act.

    5. The petition was contested by the appellants on the grounds, inter alia, that Appellant 1 had already sent a panel of three names on 16-2-1999 in which the name of Justice N.N Goswami (Retd.) was mentioned at Serial No. 1 and it was mentioned that disputes between the parties relating to all the contracts be resolved by the same arbitrator. In reply to the notice of Respondent 1, the appellants' Advocate Mr Sushil Chauhan had sent a reply on 31-7-1999 asking to choose any one from the said panel. This was again reiterated by a letter dated 15-11-1999 when Respondent 1 sent its own panel on 28-10-1999. The appointment of Brig. Nardip Singh (Retd.) as an arbitrator made by Respondent 1 which was communicated by its letter of 10-12-1999 was challenged by Appellant 1 by sending a letter dated 31-12-1999 and a letter was also sent in this regard to Brig. Nardip Singh (Retd.) to desist from proceeding with arbitration. It was further submitted that Respondent 1 did not challenge the jurisdiction of the arbitrator appointed by Appellant 1 in accordance with Section 16 of the Act. The contractor did not at all appear before the arbitrator appointed by Appellant 1 viz. Justice N.N Goswami (Retd.) and did not submit any statement of claim. In these circumstances, there was no ground for setting aside the award made by Justice N.N Goswami (Retd.) on 19-4-2000 and the petition under Section 34 of the Act filed by Respondent 1 was liable to be dismissed.

    6. We have heard Mr Mohan Parasaran, Additional Solicitor General for the appellant and Mr P.C Markanda, Senior Advocate for Respondent 1 and have perused the record.

    7. Gas Authority of India Ltd. (Appellant 1 herein) awarded four contracts to M/s Keti Construction (I) Ltd. (Respondent 1 herein) for various construction works at its Petro-Chemical Complex, Dibiyapur, District Etawah (U.P) which were as follows:

    “(A) Work Order No. CE/AUR/Ph-II Extn. B. Works/97A/95 dated 26-5-1995: Balance work of construction of C-6 and D-2 Houses at GAIL Vihar Township, Dibiyapur;
    (B) Work Order No. CE/115.Auraiya/Gail/Gail Vihar Road Work/95 dated 10-2-1995: Construction of premix bitumen carpeting and repairs of roads in Gail Vihar Colony and Compressor Station;
    (C) Work Order No. CE/137.Auraiya/Ext/SER/95 dated 1-11-1995: Construction of external sewerage line at UPPC Nagar, Dibiyapur; and
    (D) Work Order No. CE/136.Auraiya/Housing/95 dated 28-9-1995: Construction of residential quarters Type A—25 units, Type B—105 units, Type C—55 units for UPPC Complex, Dibiyapur.”

    8. The dispute here pertains to Contract No. (D) dated 28-9-1995. Clause 107 of the agreement, which is relevant for the controversy in dispute reads as follows:

    “107.1. All disputes or differences whatsoever which shall at any time arise between the parties hereto touching or concerning the works or the execution or maintenance thereof of this contract or the rights touching or concerning the works or the execution effect thereof or to the rights or liabilities or the construction meaning operation or effect whether during or after completion of the contract or whether before or after determination, foreclosure or breach of the contract (other than those in respect of which the decision of any person is by the contract expressed to be final and binding) shall after written notice by either party to the contract to the other of them and to the appointing authority hereinafter mentioned be referred for adjudication to a sole arbitrator to be appointed as hereinafter provided.
    107.2. For the purpose of appointing the sole arbitrator referred to above, the appointing authority will send within thirty days of the receipt of the notice to the contractor, a panel of three persons who shall all be presently unconnected with the organisation for which the work is executed.
    The contractor shall on receipt of the names, as aforesaid, select any one of the persons named to be appointed as a sole arbitrator and communicate his name to the appointing authority within thirty days of receipt of names. The appointing authority shall thereupon without any delay appoint the said person as the sole arbitrator. If the contractor fails to communicate such selection as provided above within the period specified, the appointing authority shall make the selection and appoint the selected as the sole arbitrator.
    If the appointing authority fails to send to the contractor the panel of three names as aforesaid within the period specified, the contractor shall send the appointing authority a panel of three names of persons who shall all be unconnected with either party. The appointing authority shall on receipt of the names as aforesaid select any one of the persons named and appoint him as the sole arbitrator. If the appointing authority fails to select the person and appoint him as the sole arbitrator within 30 days of the receipt of the panel and inform the contractor accordingly, the contractor shall be entitled to appoint one of the persons from the panel as the sole arbitrator and communicate his name to the appointing authority.
    If the arbitrator so appointed is unable to or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever, another sole arbitrator shall be appointed as aforesaid.
    The work under the contract shall, however, continue during the arbitration proceedings and no payment due or payable to the contractor shall be withheld on account of such proceedings.
    The arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties fixing the date of the first hearing.
    The arbitrator may, from time to time, with the consent of the parties, enlarge the time for making and publishing the award.
    The venue of the arbitration shall be New Delhi.
    The fees, if any, of the arbitrator shall, if required to be paid before the award is made and published, be paid half and half by each of the parties. The costs of the reference and of the award including the fees, if any, of the arbitrator shall be in the discretion of the arbitrator who may direct to and by whom and in what manner, such costs or any part thereof shall be paid and may fix or settle the amount of costs to be so paid.
    The award of the arbitrator shall be final and binding on both the parties.
    Subject to aforesaid the provisions of the Arbitration Act, 1940 or any statutory modification or re-enactment thereof and the rules made thereunder, and for the time being in force, shall apply to the arbitration proceedings under this clause.”

    9. A perusal of clause 107 would show that on a dispute being raised by the contractor, the appointing authority was required to send a panel of three names to the contractor and he was entitled to select any one of them as sole arbitrator and to communicate his decision to the appointing authority within 30 days. Thereafter, the appointing authority was under an obligation to appoint the said person as sole arbitrator. However, if the appointing authority failed to send the panel of three names within the stipulated period, the contractor was given the option to send a panel of three names to Appellant 1, which was required to select any one of them and communicate the said fact within 30 days.

    10. The plea taken by Respondent 1 is that the completion certificate with regard to the work in dispute was issued on 24-1-1998 and it wrote several times for settling the accounts. It invoked the arbitration clause on 17-7-1999 by sending a letter to the appointing authority to send a panel but as there was no response, it sent its own panel of three names on 28-10-1999 and finally informed vide letter dated 10-12-1999 that it had nominated Brig. Nardip Singh (Retd.) as the arbitrator. Voluminous correspondence was exchanged between the parties and many such letters were placed on record before the learned Single Judge of the High Court. It appears that some dispute had been raised by Respondent 1 regarding balance work of construction of C-6 and D-2 numbers of houses at GAIL Vihar Township at Dibiyapur and a letter had been sent by it to Appellant 1 on 16-1-1999. A reply was given on behalf of Appellant 1 to Respondent 1 on 16-2-1999, relevant part of which reads as under:

    “Sir,
    This has reference to your letter vide Ref. No. IND.KT.44(6)/99 dated 16-1-1999. We would like to bring to your kind notice that you have not so far informed us the nature of disputes you want to refer for resolution by the arbitrator.
    However, in the meantime, we are suggesting you a panel of three persons to select one of them as sole arbitrator:
    1. Mr Justice N.N Goswami
    Retd. Judge, Delhi High Court
    2. Dr. Avtar Singh
    Professor of Law
    3. Mr Harish Chandra
    Director General, CPWD (Retd.) & Ex. Member, UPSC
    Further, it is suggested to appoint the same arbitrator and to club the arbitration proceedings in both the matters so as to reduce on cost and time incurred in the said arbitration.
    Accordingly, you are called upon to select any one of the abovenamed persons as sole arbitrator in both the matters.”

    11. The evidence on record shows that in connection with the dispute with regard to all the four contracts several meetings had taken place in the office of GAIL also and in the office of their consultant, M/s C.P Kukreja & Associates in which the representatives of Respondent 1 had participated. This fact is not in dispute that several meetings did take place to resolve the dispute regarding all the four contracts between the representatives of Appellant 1 and Respondent 1. The Senior Manager (Civil) of Appellant 1 sent a letter dated 15-11-1999 to Respondent 1 which has considerable bearing on the controversy in hand and, therefore, the same is being reproduced below:

    “Ref.: CE/GAIL/99November 15, 1999
    M/s Keti Construction (I) Ltd.
    31/6, Sneh Nagar, Main Road
    Opp. Sapna Sangeeta Theatre
    Indore (M.P).
    Subject : Disputes relating to:
    (A) Work Order No. CE/AUR/Ph-II Extn. B. Works/97A/95 dated 26-5-1995
    Balance work of construction of C-6 and D-2 numbers of houses at GAIL Vihar Township, Dibiyapur.
    (B) Work Order No. CE/115.Auraiya/GAIL/GAIL Vihar Road Work/95 dated 10-2-1995
    Construction of premix bitumen carpeting and repairs of roads in GAIL Vihar Colony and Compressor Station.
    (C) Work Order No. CE/137.Auraiya/Ext/SER/95 dated 1-11-1995
    Construction of external sewerage line at UPPC Nagar, Dibiyapur.
    (D) Work Order No. CE/136.Auraiya/Housing/95 dated 28-9-1995
    Construction of residential quarters TYPE A—25 units, TYPE B—105 units, TYPE C—55 units for UPPC Complex, Dibiyapur.
    Dear Sir,
    Kindly recall various meetings held in our office and also in the office of Consultant, M/s C.P Kukreja Associates in respect of the above-referred contracts and the disputes arising therefrom, wherein it was agreed between us to settle the disputes amicably and through discussions. Despite this clear understanding, you had vide your letters dated 25-8-1998 invoked arbitration clause in respect of Work Orders Nos.: (1) CE/AUR/Ph-II/Extn. B. Works/97A/95 dated 26-5-1995 relating to balance work of construction of C-6 and D-2 numbers of houses at GAIL Vihar Township of Dibiyapur and (2) CE/115.Auraiya/GAIL/GAIL Vihar Road Work/95 dated 10-2-1995 relating to construction of premix bitumen carpeting and repairs of roads in gail Vihar Colony & Compressor Station.
    Subsequently, vide your letters dated 5-10-1998 in respect of the above work orders, you submitted a panel of three arbitrators asking us to select one of them to act as sole arbitrator on the above two cases. However, we responded to your communications vide our letters dated 16-2-1999 and as per the terms of the contract suggested the following panel of three distinguished persons:
    1. Mr Justice N.N Goswami (Retd.) Judge, Delhi High Court
    2. Dr. Avtar Singh, Professor of Law, IIM, Lucknow
    3. Mr Harish Chandra, Director General, CPWD (Retd.) & Ex-Member, UPSC.
    You were requested to select any of them to act as sole arbitrator. However, no action has been taken by you so far and even the issues which seem to have been resolved by discussions have not been confirmed, keeping the matters pending unnecessarily.
    During our meetings, we have suggested to you that all the disputes arising out of the above contracts which cannot be settled by mutual discussions, may be referred to a sole arbitrator selected by you from among the panel of distinguished persons mentioned above, so that the resolution of disputes by reference to arbitration becomes cost effective, economical and quick.
    In view of the above, you are requested once again to select any of the persons mentioned herein to act as a sole arbitrator in all the above disputes.
    Assuring you of our best cooperation at all times.
    Yours faithfully,
    sd/-
    (P.K Sarkar)
    Sr. Manager (Civil)”

    12. It may be noted that the abovenoted letter of 15-11-1999 was written by the Senior Manager (Civil) of Appellant 1 in connection with the disputes relating to all the four contracts viz. (A), (B), (C) and (D). In this letter reference was made to the earlier letter dated 16-2-1999 sent by Appellant 1 and the same panel of three names in which name of Justice N.N Goswami (Retd.) was at Serial No. 1 was reiterated. The last paragraph of the abovequoted letter is very important where it was clearly mentioned that the dispute arising out of the four contracts which cannot be mutually settled may be referred to a sole arbitrator selected by Respondent 1 from amongst the persons mentioned in the panel so that the resolution of disputes by reference to arbitration becomes cost effective, economical and quick. Towards the end of the letter a request was made to Respondent 1 to select any one of the persons mentioned in the said letter to act as sole arbitrator in all the above disputes, which means all the disputes relating to Contracts Nos. (A), (B), (C) and (D). It is, therefore, clear that a panel of three names had been sent by the appellant to Respondent 1 on 16-2-1999 which was categorically reiterated in the letter dated 15-11-1999, sent by the Senior Manager (Civil) of Gas Authority of India Ltd. (Appellant 1) to Respondent 1. This letter was not confined to any particular contract but specifically referred to all the four contracts including the disputed Contract No. (D) dated 28-9-1995. The stand of Appellant 1 was quite reasonable that if all the disputes were referred to a single arbitrator, the arbitration proceedings would be cost effective, economical and quick. After receipt of this letter dated 15-11-1999, wherein the earlier panel communicated vide letter dated 16-2-1999 had been reiterated, there was no occasion for Respondent 1 to appoint Brig. Nardip Singh (Retd.) as arbitrator by sending a communication to that effect subsequently on 10-12-1999. The stand of the appellant had been made very clear and explicit by the aforesaid two letters and it was not required to respond again specifically to the letter dated 28-10-1999 sent by Respondent 1 to select an arbitrator from the panel intimated by it. The stand of Respondent 1 to the effect that as the appellant did not respond to its letter dated 28-10-1999, it selected Brig. Nardip Singh (Retd.) by sending a communication on 10-12-1999 is, therefore, wholly unjustified.

    13. There is contemporaneous evidence which shows that a number of meetings had taken place between the representatives of Appellant 1 and the representatives of Respondent 1, wherein effort was made to resolve the disputes without reference to arbitration and an understanding had been reached between the parties that unresolved disputes of all the four contracts shall be referred to a sole arbitrator to make the arbitration proceedings quick and cost effective. After Respondent 1 had sent the letter dated 10-12-1999 to the appellant that it had nominated Brig. Nardip Singh (Retd.) for the purpose of arbitration, the Senior Deputy Manager (Law) of Appellant 1 sent a letter to him on 31-12-1999 requesting him to desist from entering upon the reference or taking any further steps in view of the fact that in the meeting held between the representatives of the two organisations, it was clearly agreed that the matter shall be referred to a sole arbitrator and Respondent 1 was expected to select a name from the panel suggested by Appellant 1. The letter is self-eloquent and is being reproduced below:

    “Brig. Nardip SinghDecember 31, 1999
    Chief Engineer, MES (Retd.)
    B-64, Sector 30
    NOIDA
    Dear Sir,
    Sub. : Letter by Keti Const. Ltd. No. IND/KTIL/908/99 dated 20-12-1999 in the matter of construction of residential quarters of UPPC, Dibiyapur, Etawah, U.P
    This has reference to the captioned communication on the subject cited above.
    M/s Keti Construction have been awarded contracts by GAIL for execution of a number of its projects. In relation to some of which contracts, including the contract in question now sought to be placed before you, certain disputes are alleged to remain outstanding, as per Keti Construction.
    Keti Construction made their requests for resolution of inter se disputes with GAIL by reference to arbitration, including the contract in question.
    Upon receipt of these requests of Keti Construction by GAIL, GAIL made suggestion for resolution of disputes by a sole arbitrator and sent to Keti Construction a panel of three distinguished persons who may be appointed as sole arbitrator. Thereupon, Keti Construction came forward for negotiations. During these discussions/negotiations, the representatives of Keti Construction were repeatedly suggested to refer all unresolved issues of various contracts to a sole arbitrator selected by them from amongst the panel suggested by GAIL. Representatives of Keti Construction agreed to our suggestion as it was less time consuming and GAIL in turn took liberal view on various issues with clear objective of resolving these disputes without reference to arbitration. These efforts yielded results and the requests for arbitration of Keti Construction were withdrawn by them.
    As all these matters were between two organisations and it was clearly agreed by the parties to refer unresolved disputes of all contracts to a sole arbitrator to make the arbitration proceedings quick and cost effective. We would have expected Keti Construction to have sent a name from the panel suggested by GAIL in accordance with the spirit of the discussions held and the principles accepted therein for resolution of inter se disputes, which have been acted upon as aforesaid.
    Unfortunately, Keti Construction has unilaterally sought to nominate your goodself, despite the overwhelming record to the contrary.
    In this factual background we request you to desist from entering upon the reference or taking any further steps in pursuance to the captioned communication, keeping the cherished values you have maintained in high esteem all through your distinguished career in armed forces.
    Assuring you of our best attention at all times.
    Yours faithfully,
    sd/-
    (Ch. Harnath)
    Sr. Dy. Manager (Law)
    CC to
    Keti Construction (I) Ltd.
    31/6, Sneh Nagar, Main Road
    Opposite Sapna Sangeeta Theatre
    Indore 452 001 (M.P)”

    14. It may be noted that the four contracts (A), (B), (C) and (D) were awarded on different dates in quick succession between 10-2-1995 and 1-11-1995 and related to various construction works in Petro-Chemical Complex, Dibiyapur, District Etawah (U.P). The terms of the agreement have to be understood in a broad commonsense manner. The material placed on record before the learned Single Judge shows that the discussion which took place in the meetings held between the representatives of Appellant 1 and representatives of Respondent 1 were not confined to the dispute relating to a single contract, but they related to disputes concerning all the four contracts. It will not be proper to segregate or compartmentalise the correspondence exchanged between the parties as if a particular letter was confined to a particular contract alone. The correspondence exchanged between the parties is not like evidence in a suit or trial where a piece of evidence given in a particular suit or trial cannot be read or taken into consideration in another suit or trial. The stand of the appellant right from the beginning was that all the disputes should be referred to a single arbitrator, which will be cost effective, economical and quick. There can be no doubt that this stand was very reasonable. Appellant 1 had sent a panel on 16-2-1999, which was reiterated in the communication dated 15-11-1999. In these circumstances, Respondent 1 was not at all entitled to nominate Brig. Nardip Singh (Retd.) as an arbitrator which it chose to do subsequently on 10-12-1999. We do not find anything wrong on the part of the appellant when it intimated vide letter dated 15-11-1999 that a panel had already been sent earlier on 16-2-1999 for appointment of a single arbitrator for resolution of all the disputes between the parties.

    15. According to the appellants, after Respondent 1 had sent the notice dated 17-7-1999 invoking the arbitration clause, a reply thereto was given on their behalf by Mr Sushil Chauhan, Advocate, on 31-7-1999 wherein it was mentioned as under:

    “Ref.: Your Letter No. IND/KT/522/99 dated 17-7-1999
    Pursuant to the discussions held on various occasions by you and my client, GAIL officials with regard to settlement of disputes and appointment of sole arbitrator, I am instructed by my client, Gas Authority of India Ltd. (GAIL) to call upon you to select the sole arbitrator from the names of three distinguished persons already suggested by my clients during discussions in response to your notices. Please take further necessary action.”

    16. Respondent 1 has seriously challenged the receipt of the letter dated 31-7-1999 sent by Mr Sushil Chauhan. It has been urged that the said letter was not sent by registered post and was not received by them. We have, therefore, not taken into consideration the said letter. There is other material on record to show that a panel of three names had already been sent by Appellant 1 to Respondent 1 which was a sufficient compliance with the clause of the agreement. There is neither any such clause in the agreement nor is there any requirement in law that for each of the contracts (A), (B), (C) and (D) a separate panel ought to have been sent. The same panel could very well be utilised for resolving the disputes arising out of the four contracts. In fact, as suggested on behalf of the appellant, it would have been more convenient, time saving and economical to have the same person as arbitrator in resolving the disputes between the parties with regard to all the contracts. The view to the contrary taken by the Division Bench of the High Court is clearly erroneous in law.

    17. Appellant 1 sent a communication to Justice N.N Goswami (Retd.) on 13-1-2000 appointing him as sole arbitrator for resolution of disputes relating to the contract in question and a copy of this letter was also sent to Respondent 1. Justice N.N Goswami (Retd.) then entered upon the reference and sent notices to the parties on 11-2-2000 to appear before him on 6-3-2000. Respondent 1, however, chose not to put in appearance before Justice N.N Goswami (Retd.). On 28-3-2000, the arbitrator passed an order holding that his appointment as arbitrator was in accordance with the terms of the agreement, but in the interest of justice he would give another notice to Respondent 1. The relevant part of the order passed by him reads as under:

    “In terms of my order dated 6-3-2000, M/s Gas Authority have produced the complete file. On perusal of the file and after hearing Mr Chauhan, prima facie I am satisfied that my appointment as arbitrator is in accordance with the terms of agreement between the parties. I would have proceeded further, but in the interest of justice I feel that one final notice be served on M/s Keti Construction before publishing the award.
    To come up on April 18, 2000 at 6.30 p.m The parties may file their statements of claim before the next date of hearing.”

    18. Since Respondent 1 did not appear on the date fixed, the arbitrator passed an order fixing 19-4-2000 as the next date of hearing. A no-claim award was finally given by him on 19-4-2000.

    19. Respondent 1 did not at all appear before the arbitrator appointed by Appellant 1. Respondent 1 neither filed any statement of claim nor raised any plea of jurisdiction before the arbitrator. Section 16 of the Act says that the Arbitral Tribunal may rule on its own jurisdiction, including ruling on any objections with respect to the existence or validity of the arbitration agreement. In Konkan Rly. Corpn. Ltd. v. Rani Construction (P) Ltd. (2002) 2 SCC 388 in para 21 a Constitution Bench of 5 learned Judges has ruled that if the Arbitral Tribunal has been improperly constituted, it would be open to the aggrieved party to require the Arbitral Tribunal to rule on its own jurisdiction in view of Section 16 of the Act. It was also observed that the expression used in sub-section (1) that the “Arbitral Tribunal may rule on any objections with respect to the existence or validity of the arbitration agreement” shows that the Arbitral Tribunal's authority under Section 16 is not confined to the width of its jurisdiction, but goes to the very root of its jurisdiction and there is no impediment in contending before the Arbitral Tribunal that it had been wrongly constituted. This decision has been partly overruled on another point by a larger Bench of 7 learned Judges in SBP & Co. v. Patel Engg. Ltd. (2005) 8 SCC 618 but the aforesaid view has not been dissented from or reversed. This will be evident from the conclusions arrived at by the larger Bench which have been summarised in para 47 of the Report and sub-para (ix) thereof reads as under:

    “(ix) In a case where an Arbitral Tribunal has been constituted by the parties without having recourse to Section 11(6) of the Act, the Arbitral Tribunal will have the jurisdiction to decide all matters as contemplated by Section 16 of the Act.”

    20. It will be useful to take note of the Preamble to the Arbitration and Conciliation Act, 1996 which reads as under:

    “Whereas the United Nations Commission on International Trade Law (UNCITRAL) has adopted the UNCITRAL Model Law on International Commercial Arbitration in 1985;
    And whereas the General Assembly of the United Nations has recommended that all countries give due consideration to the said Model Law, in view of the desirability of uniformity of the law of arbitral procedures and the specific needs of international commercial arbitration practice;
    And whereas the UNCITRAL has adopted the UNCITRAL Conciliation Rules in 1980;
    And whereas the General Assembly of the United Nations has recommended the use of the said Rules in cases where a dispute arises in the context of international commercial relations and the parties seek an amicable settlement of that dispute by recourse to conciliation;
    And whereas the said Model Law and Rules make significant contribution to the establishment of a unified legal framework for the fair and efficient settlement of disputes arising in international commercial relations;
    And whereas it is expedient to make law respecting arbitration and conciliation, taking into account the aforesaid Model Law and Rules;”

    21. The Preamble to the Act makes it amply clear that Parliament has enacted the Arbitration and Conciliation Act, 1996 almost on the same lines as the Model Law, which was drafted by the United Nations Commission on International Trade Law. In Sundaram Finance Ltd. v. NEPC India Ltd. (1999) 2 SCC 479, AIR 1999 SC 565 it has been observed that the provisions of the Arbitration and Conciliation Act, 1996 should be interpreted keeping in mind the Model Law as the concept under the present Act has undergone a complete change. It will, therefore, be useful to take note of the corresponding provisions of the UNCITRAL Model Law. Article 16 of the Model Law, which corresponds to Section 16 of the Act, is being reproduced below:

    UNCITRAL Model Law
    “16. Competence to rule on own jurisdiction.—(1) The Arbitral Tribunal has the power to rule on its own jurisdiction, including any objections with respect to the existence or validity of the arbitration agreement. For the purpose, an arbitration clause which forms part of a contract shall be treated as an agreement independent of the other terms of the contract. A decision by the Arbitral Tribunal that the contract is null and void shall not entail ipso jure the invalidity of the arbitration clause.
    (2) A plea that the Arbitral Tribunal does not have jurisdiction shall be raised not later than in the statement of defence. A party is not precluded from raising such a plea by the fact that he has appointed, or participated in the appointment of, an arbitrator. A plea that the Arbitral Tribunal is exceeding the scope of its authority shall be raised promptly after the Arbitral Tribunal has indicated its intention to decide on the matter alleged to be beyond the scope of its authority. The Arbitral Tribunal may, in either case, admit a later plea if it considers the delay justified.
    (3) The Arbitral Tribunal may rule on a plea referred to in clause (2) of this article either as a preliminary question or in an award on the merits. In either case, a ruling by the Arbitral Tribunal that it has jurisdiction may be contested by any party only in an action for setting aside the arbitral award.”

    22. The commentary on the three clauses of the Model Law has been given under Headings A, B, C and D. Note 1 under Heading A and Note 11 under Heading D, which are relevant for the controversy in hand, are being reproduced below:

    “A. ‘Kompetenz-kompetenz’ and separability doctrine, clause (1).
    Note 1. Article 16 adopts the important principle that it is initially and primarily for the Arbitral Tribunal itself to determine whether it has jurisdiction, subject to ultimate court control (see below paras 12-14). Clause (1) grants the Arbitral Tribunal the power to rule on its own jurisdiction, including any objections with respect to the existence or validity of the arbitration agreement. This power, often referred to as ‘kompetenz-kompetenz’, is an essential and widely accepted feature of modern international arbitration but, at present is not yet recognised in all national laws.
    D. Ruling by the Arbitral Tribunal and judicial control, clause (3) [Corr. to Sections 16(5), (6)].
    Note 11. Objections to the Arbitral Tribunal's jurisdiction go to the very foundation of the arbitration. Jurisdictional questions are, thus, antecedent to matters of substance and usually ruled upon first in a separate decision, in order to avoid possible waste of time and costs. However, in some cases, in particular, where the question of jurisdiction is intertwined with the substantive issue, it may be appropriate to combine the ruling on jurisdiction with partial or complete decision on the merits of the case. Article 16(3), therefore, grants the Arbitral Tribunal discretion to rule on a plea referred to in clause (2) either as a preliminary question or in an award on the merits.

    23. So, the commentary on the Model Law which was drafted by UNCITRAL and has been adopted by many countries including India, shows that where a party asserts that the Arbitral Tribunal has not been properly constituted or it has no jurisdiction, then such a plea must be raised before the Arbitral Tribunal right at the beginning and normally not later than in the statement of defence.

    24. The whole object and scheme of the Act is to secure an expeditious resolution of disputes. Therefore, where a party raises a plea that the Arbitral Tribunal has not been properly constituted or has no jurisdiction, it must do so at the threshold before the Arbitral Tribunal so that remedial measures may be immediately taken and time and expense involved in hearing of the matter before the Arbitral Tribunal which may ultimately be found to be either not properly constituted or lacking in jurisdiction, in proceedings for setting aside the award, may be avoided. The commentary on Model Law clearly illustrates the aforesaid legal position.

    25. Where a party has received notice and he does not raise a plea of lack of jurisdiction before the Arbitral Tribunal, he must make out a strong case why he did not do so if he chooses to move a petition for setting aside the award under Section 34(2)(a)(v) of the Act on the ground that the composition of the Arbitral Tribunal was not in accordance with the agreement of the parties. If plea of jurisdiction is not taken before the arbitrator as provided in Section 16 of the Act, such a plea cannot be permitted to be raised in proceedings under Section 34 of the Act for setting aside the award, unless good reasons are shown.

    26. Though Respondent 1 had ample opportunity to appear before Justice N.N Goswami (Retd.) and raise a plea of jurisdiction to the effect that he had been wrongly appointed as arbitrator by Appellant 1, yet, it chose not to do so. This feature of the case weighs heavily against Respondent 1. The learned Single Judge has taken this fact as an additional ground for rejecting the petition filed by Respondent 1 under Section 34 of the Act and we are in agreement with the said view.

    27. For the reasons discussed above, the appeal is allowed with costs throughout and the judgment and order dated 7-12-2004 of the Division Bench of the High Court is set aside. The judgment and order dated 20-10-2003 of the learned Single Judge dismissing the petition under Section 34 of the Act, which was filed by Respondent 1, is affirmed.

    Use AI to get other relevant cases.

    Comments

    Gas Authority Of India Ltd. And Another v. Keti Construction (I) Ltd. And Others
    (May 11, 2007)