Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Neutral Citations
1995 INSC 429
Equivalent Citations
citation codes
Case Number
Disposition
Judges
Acts
  • Section 8 or any other provision under the Act
  • The Act (relevant provisions)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Sections 5, 8, 11 and 29 of the Arbitration Act, 1940
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
1995 INSC 429
Equivalent Citations
citation codes
Case Number
Disposition
Judges
Acts
  • Section 8 or any other provision under the Act
  • The Act (relevant provisions)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Sections 5, 8, 11 and 29 of the Arbitration Act, 1940
Smart Summary

Factual and Procedural Background

The dispute arises out of a contract containing Clause 25-A, which designates the “Superintending Engineer, Planning Circle, Chandigarh” (or the person acting in that post at the relevant time) as the sole arbitrator for any disagreements connected with the contract. Alleging that the named arbitrator delayed issuing an award, the contractor (appellant) filed an Original Petition before the Senior Judge seeking revocation of the arbitrator’s authority and appointment of an independent arbitrator under the Arbitration Act, 1940. The Senior Judge acceded to that request. The employer (respondent) challenged this order in revision. The High Court of Punjab and Haryana set aside the Senior Judge’s order, holding that the arbitrator had been proceeding diligently and that delays were attributable to the contractor’s own conduct. The present appeal is against the High Court’s decision.

Legal Issues Presented

  1. Whether a civil court, in exercise of its powers under Sections 5, 8, 11 and 29 of the Arbitration Act, 1940, can revoke the appointment of an arbitrator specifically named in Clause 25-A of the contract and appoint a new arbitrator in his place.

Arguments of the Parties

Appellant (Contractor)

  • Contended that the designated arbitrator had delayed the proceedings for a considerable period, necessitating judicial intervention and appointment of an independent arbitrator.

Respondent (Employer)

  • Maintained that any delays were caused by the contractor, who repeatedly sought adjournments and failed to cooperate.
  • Argued that no misconduct, fraud, or other disqualifying factor was alleged against the arbitrator, and therefore his authority could not be revoked under the Act.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court reiterated the settled principle that when parties have contractually agreed on a specific arbitrator, the courts cannot interfere with that choice unless statutory grounds such as legal misconduct, fraud, or disqualification are both pleaded and proved. Revocation of an arbitrator’s authority is tantamount to his removal and therefore requires “just and sufficient cause,” which was absent in this case.

Reviewing the record, the Court accepted the High Court’s findings that:

  • The contractor had repeatedly consented to adjournments and thus contributed to any delay.
  • The arbitrator had been “proceeding with the task of arbitration in right earnest,” with the successor Superintending Engineer continuing the work upon transfer of his predecessor.
  • No allegation of misconduct or incapacity had been substantiated against the arbitrator.

Consequently, the civil court lacked jurisdiction to revoke the named arbitrator’s mandate or to appoint a substitute under Sections 8 or other provisions of the Act. The High Court was therefore correct in reversing the Senior Judge’s order.

Holding and Implications

Appeal Dismissed. The original arbitrator (the current Superintending Engineer, Planning Circle, Chandigarh) is directed to conclude the arbitration and deliver an award within six months of receiving the Court’s order. The time-limit will not restrain the arbitrator if the contractor again fails to cooperate.

Implications: The decision reaffirms the narrow grounds on which courts may revoke an agreed-upon arbitrator’s mandate. It underscores party autonomy in arbitration agreements and discourages dilatory tactics aimed at replacing a designated arbitrator without proof of misconduct. No new precedent is set, but the ruling reinforces existing jurisprudence limiting judicial intervention in arbitral appointments.

To access the original judgment, please Sign In or Subscribe.

    Bhupinder Singh Bindra v. Union Of India And Another

    Order

    1. Leave granted.

    2. We have heard both the counsel. The only question in this case is whether the civil court, while exercising the power under Sections 5, 8, 11 and 29 of the Arbitration Act, 1940 (for short, ‘the Act’) would be justified in revoking the appointment of an arbitrator appointed in terms of clause 25-A of the contract. Clause 25-A reads thus:

    “ 25-A. if question, difference or objections whatsoever shall arise in any way connected with or arising out of this instrument or the meaning or operation of any part therefor, the rights, duties or liabilities of other party, then save insofar as the decision of any such matter is hereinbefore provided and has been so decided every such matter including whether it has been finally decided accordingly, or whether the contract should be terminated or has been rightly terminated and regards the rights and obligations of the parties as the result of such termination shall be referred for arbitration to the Superintending Engineer, Planning Circle, Chandigarh, or acting as such at the time of reference within 180 days viz., six months from the date of making final payment to the contractor….”

    3. It is settled law that court cannot interpose and interdict the appointment of an arbitrator, whom the parties have chosen under the terms of the contract unless legal misconduct of the arbitrator, fraud, disqualification etc. is pleaded and proved. It is not in the power of the party at his own will or pleasure to revoke the authority of the arbitrator appointed with his consent. There must be just and sufficient cause for revocation. There is no general power for the court to appoint an arbitrator unless the case falls within the relevant provisions of the Act nor will the court make an appointment where the arbitration agreement provides a method by which appointment is to be made. Clause 25-A expressly provides appointment of the named officer by designation who was appointed in terms thereof and had entered upon the duties immediately. Revocation of arbitrator's authority is exactly equivalent to removal which would be done on specified grounds like misconduct or omission to enter upon duties within time etc. Both parties by consent may revoke the authority of the arbitrator but that is not the case herein. The contract clearly indicates that the Superintending Engineer, Planning Circle, Chandigarh or anyone acting as such at the time of reference within 180 days, i.e six months from the date of making final payment of the contractor is the designated officer chosen voluntarily by the parties. It was impugned in the OP filed in the court of the Senior Judge that the officer had delayed for considerable period in making the award and that, therefore, it necessitated the appellant to invoke the jurisdiction of the civil court under the Act.

    4. The High Court of Punjab and Haryana in the impugned order in Civil Rev. No. 516 of 1991 has pointed out that the contractor had consented for adjournments and that there was no allegation of misconduct of the arbitrator in adjudicating the dispute. On the other hand, the High Court recorded that:

    “… the Arbitrator was proceeding with the task of an arbitration in right earnest, in spite of the fact that the Contractor was not cooperating in this behalf. On the transfer of Shri R.K Aggarwal, Superintending Engineer, the work of arbitration had been taken up by his successor Shri Puran Jeet Singh, Superintending Engineer.”

    5. Thus it was held that the arbitrator was willing to proceed with and that the appellant was not cooperating in conducting the proceedings. Therefore, having consented for adjournments and dragged on the case for a considerable time, it is no longer open to contend that the arbitrator neglected to make the award. Under those circumstances, it cannot be said that there are any laches on the part of the arbitrator in giving the award. When the parties, under the clauses of the contract, have specifically chosen a named authority and not any other arbitrator, without the consent of the parties, court has no jurisdiction to interpose into the contract and appoint an arbitrator under Section 8 or any other provision under the Act. The High Court, therefore, was clearly right in setting aside the order of the Senior Judge appointing an independent arbitrator to adjudicate the dispute.

    6. Since the matters are pending for a long time, the arbitrator is directed to adjudicate upon the dispute and give his award within six months from the date of the receipt of this order. It is needless to mention that in case the appellant does not cooperate in the disposal of the application, the time-limit prescribed by us would not deter the arbitrator to decide the dispute according to law. The appeal is accordingly dismissed. No costs.

    Use AI to get other relevant cases.

    Comments

    Bhupinder Singh Bindra v. Union Of India And Another
    (Jul 28, 1995)