  • Rule 6 of the Delhi Development Authority (Disposal of Developed Nazul Land) Rules, 1981
  • CONTEMPT OF COURTS ACT 1971
  • Rule 6 of the Nazul Rules.
  • Rule 2(1)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Rule 6 of the Delhi Development Authority (Disposal of Developed Nazul Land) Rules, 1981
  • CONTEMPT OF COURTS ACT 1971
  • Rule 6 of the Nazul Rules.
  • Rule 2(1)
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

This contempt petition arises from an allegation that the respondents have not complied with the Division Bench order dated July 15, 2002 in Civil Writ No. 1750/1996. The Division Bench had allowed the petition with costs of Rs. 5,000 payable by the Delhi Administration, Land and Building Department, New Delhi, quashed and set aside Annexure-‘J’ dated 1.6.1982 and consequential actions, and directed the DDA to allot the plot in question and execute a lease deed within two months from receipt of the writ order or from production of a copy of the order by the petitioner, subject to compliance with requisite formalities including payment of charges and premium; if the original plot was not available, a similar plot was to be allotted on the same terms.

The petitioner’s land had been acquired in 1969. By letter dated 1.6.1982 the petitioner was informed that his recommendation for allotment of a 250 sq. yards plot (recommended on 21.2.1980) stood withdrawn because an application had not been received within time. That withdrawal was successfully challenged before the Division Bench in Civil Writ No. 1750/1996.

The present controversy is whether the DDA, while offering a plot to the petitioner, was obliged to compute the “pre-determined rate” at the level prevailing in 1982 (Rs. 178 per sq. mtr. as claimed by petitioner) or whether it could charge the prevailing rates in 2003 (Rs. 6,224 per sq. mtr. as computed by the DDA). The petitioner contends that charging 2003 rates violates the order’s phrase “on same terms” and constitutes contempt; the respondents contend the Division Bench’s express inclusion of “including payment of requisite charges and the premium” contemplated payment at then-prevailing rates.

Legal Issues Presented

  1. Whether the DDA’s computation of premium at rates prevailing in 2003, rather than at rates prevailing in 1982, amounted to wilful disobedience of the Division Bench order (i.e., whether such conduct constituted contempt).
  2. If the order directing allotment “on same terms” is ambiguous, whether the contempt jurisdiction is the appropriate forum to resolve the dispute about which point in time determines the “pre-determined rates” under Rule 6 of the DDA (Nazul) Rules.

Arguments of the Parties

Petitioner’s Arguments (as summarized in the opinion)

  • Because the Division Bench used the phrase “on same terms,” the DDA was precluded from claiming payment at current (2003) rates; the premium payable ought to be the rates prevailing in 1982.
  • The Division Bench’s order quashing Annexure-'J' and directing allotment on the same terms implicitly fixed the terms (including premium) at the earlier point in time.
  • Reliance was placed on Rule 6 of the Delhi Development Authority (Disposal of Developed Nazul Land) Rules, 1981 and on decisions such as J.S. Rao (Prof.) v. D.D.A to support the contention that the allottee may be entitled to the price prevailing on the date of his application or otherwise at an earlier rate.

Respondent’s Arguments (as summarized in the opinion)

  • The Division Bench expressly directed allotment subject to “including payment of requisite charges and the premium”, which indicates that the allotment would be subject to payment at prevailing rates when the allotment is made, not necessarily at 1982 rates.
  • Reliance was placed on the Supreme Court decision in Delhi Development Authority v. Pushpendra Kumar Jain to show that identification or selection (and analogous earlier steps) do not vest a right to allotment at prices prevailing at an earlier date; the price applicable is the one prevailing on communication of allotment unless the scheme provides otherwise.
  • Counsel also relied upon the Full Bench decision in Ramanand v. Union of India for the proposition that Rule 6 contemplates the predetermined rates in force at the time the offer/allotment is made.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Delhi Development Authority v. Pushpendra Kumar Jain, 1994 Supp (3) SCC 494 : AIR 1995 Supreme Court 1 The principle that a mere draw of lots or early selection does not vest an indefeasible right to allotment at the price prevailing on the date of the draw; the right arises on communication of the allotment letter and the price applicable is that prevailing on the date of such communication unless otherwise provided. The respondent relied on this decision; the Court observed the circumstances in that decision were not identical to the present case but acknowledged the decision’s relevance to the question of which date’s rates apply.
Ramanand v. Union of India, AIR 1994 DELHI 29 (Full Bench) Full Bench holding that the rates of premium chargeable from an individual whose land has been acquired shall be the predetermined rates in force at the time when the offer is made to the concerned person or the allotment of a specific plot is made under Rule 6 of the Nazul Rules. The Court noted that applying this ratio to the present case could support either the petitioner’s or respondent’s position because it is arguable that the relevant time-point could be 1982 or 2003.
Gurpawan Kumar v. S.P. Jakhanwal, 1996 (36) DRJ 29 Not specified in the provided opinion excerpt. The opinion records that counsel relied on this decision, but it does not extract or state the principle or how it was applied in the present proceedings.
J.S. Rao (Prof.) v. D.D.A, 2001 1 AD (DELHI) 235 The observation that a person incorrectly not entered in a draw of lots can claim allotment of the flat at the price prevailing on the date of his application. The petitioner’s counsel drew attention to this decision; the Court recorded the citation but did not decide the merits in the contempt proceeding.
Jhareswar Prasad Paul v. Tarak Nath Ganguly, (2002) 5 SCC 352 Authoritative statement on the purpose and limits of contempt jurisdiction: contempt powers must be exercised sparingly; they are confined to deliberate disobedience and should not be used to re-adjudicate matters or to decide questions not decided in the original order. The Court relied upon the quoted paragraph from this decision as instructive authority for dismissing the contempt petition and explaining why the court should not resolve the substantive dispute in contempt proceedings where more than one reasonable interpretation of the order exists.

Court's Reasoning and Analysis

The Court framed the procedural and substantive contours of the petition as a contempt application: the core inquiry was whether the Division Bench order admitted of only one interpretation and whether the respondents had deliberately disobeyed that singular directive.

Key steps in the Court’s analysis:

  1. The Court identified that the disputed phrase is “on same terms” in the Division Bench order and noted that the Division Bench also required compliance with “including payment of requisite charges and the premium.” The parties advanced rival textual interpretations as to whether the phrase fixed the premium at 1982 levels or allowed the DDA to charge prevailing rates.
  2. The Court reviewed the statutory framework (Rule 6 of the DDA (Disposal of Developed Nazul Land) Rules, 1981 and the definition of “pre-determined rates” in Rule 2(1)) to situate the dispute about the timing for rates determination, but did not resolve the substantive statutory question in the contempt proceeding.
  3. The Court examined relevant authorities cited by the parties (including the Supreme Court’s decision in Delhi Development Authority v. Pushpendra Kumar Jain and the Full Bench in Ramanand). It recognized that these precedents bear on whether the applicable rate is the one prevailing at an earlier date or at the date of offer/allotment, but concluded that the present facts allow for at least two reasonable interpretations.
  4. Applying the principle elaborated in Jhareswar Prasad Paul v. Tarak Nath Ganguly, the Court emphasized that contempt jurisdiction is limited to cases of deliberate and contumacious disobedience and should not be used to re-decide disputes or to resolve matters where the order is susceptible to more than one reasonable interpretation.
  5. Given that the order might reasonably be understood in more than one way—i.e., whether “on same terms” fixes 1982 premium rates or whether the express phrase about payment of charges contemplates prevailing rates—the Court held it would be inappropriate to invoke contempt powers to determine the substantive dispute.

The Court therefore refrained from adjudicating the substantive controversy over rates or from finding contempt; instead it dismissed the petition with directions allowing the petitioner liberty to pursue appropriate legal proceedings to obtain a fuller adjudication on the merits.

Holding and Implications

Holding: Petition dismissed.

Implications:

  • The contempt petition was dismissed because the Division Bench order could reasonably admit of more than one interpretation, and contempt jurisdiction cannot be used to resolve such substantive disputes.
  • The petitioner was granted liberty to pursue any appropriate legal proceedings to obtain a full adjudication of the controversy regarding the applicable premium rates (i.e., whether 1982 rates or 2003 rates apply).
  • The parties were directed to bear their respective costs. The Court did not lay down any novel precedent on the substantive question of which date fixes the predetermined rate; rather, it applied established limits on contempt jurisdiction (as articulated in Jhareswar Prasad Paul) and declined to decide the underlying dispute in these proceedings.

Note: This summary is based exclusively on the contents of the provided opinion. No facts, arguments, or legal holdings beyond those expressly contained in the opinion have been added.

    Tilak Ram v. Z.U. Siddiqui

    Vikramajit Sen, J.— In this Contempt Petition it has been alleged that the Orders of the Division Bench dated July 15, 2002 have not been complied with by the respondents. The relevant paragraph of the said Order in Civil Writ No. 1750/1996, whereby the Petition was allowed with costs of Rs. 5,000/- payable by the Delhi Administration, Land and Building Department, New Delhi, reads thus;

    “Resultantly, the petition is allowed. The impugned letter Annexure-‘J’ dated 1.6.1982 and consequential actions taken thereunder are quashed and set aside. Consequently, DDA is directed to allot the plot in question and execute a lease deed in respect of the said plot reserved within a period of two months from the date receipt of this writ order of from the date of production of a copy of this order by the petitioner to the DDA, subject to the petitioner complying with all other requisite formalities, including payment of requisite charges and the premium. In case for any reason whatsoever the plot is not available, the petitioner will be allotted plot of similar size in the same area/residential scheme on same terms.”(Underlining added)

    2. It is contended by Mr. Ravinder Sethi, learned Senior Counsel for the petitioner, that since the Bench had employed the words “on same terms”, it was implicit that while allotting the plot to the petitioner, the DDA could not claim payment at the current rates. In the present case, the Petitioner's land was acquired in 1969. By letter dated 1.6.1982, the petitioner was informed that since his application for allotment of an alternate plot in lieu of the acquired land had not been received within time, the recommendation made in his favour for allotment of a plot measuring 250 sq. yards on 21st February, 1980 stood withdrawn. It was this action which was successfully challenged before the Division Bench in Civil Writ No. 1750/1996.

    3. Mr. Sethi has drawn attention to Rule 6 of the Delhi Development Authority (Disposal of Developed Nazul Land) Rules, 1981 which stipulates, inter alia, that subject to other provisions of the Rules, the Authority shall allot Nazul land at the pre-determined rates to individuals whose land has been acquired for planned development of Delhi after 1st day of January, 1961, and which forms part of Nazul land. Rule 2(1) defines “Pre-determined rates” to mean the rates of premium chargeable from different categories of persons and determined by notification from time-to-time by the Central Government, having regard to—

    (a) cost of acquisition,

    (b) development charges, and

    (c) concessional charges for use and occupation.

    4. The Provisos to the Rule permit different rates being levied in respect of middle and low income groups, and thereafter also permits a differences in the rates between plots situated at main roads, corner of two roads or other advantage positions, and others.

    5. The only controversy which arises in these proceedings is that although a plot has now been offered to the Petitioner, the DDA has computed the predetermined rate thereof in accordance with existing in 2003, whereas the petitioner claims that it should be those prevailing in 1982. In 1982 it is stated that the rate was Rs. 178 per sq. mtr., whereas the amount changed/levied in 2003 is calculated at the rate of Rs. 6224/- per sq. mtr., thereby brining about an astronomical increase. The Petitioner contends that this demand is not “on the same terms” prevailing in 1982 and therefore there has been a wilful Contempt of the Orders of the Division Bench. The contention of respondent, however, is that inasmuch as the Division Bench had also employed the words “including payment of requisite charges and the premium”, it was clearly in contemplation that the allotment would be subject to the prevailing rates as on date.

    6. Reliance has been placed in Delhi Development Authority v. Pushpendra Kumar Jain, 1994 Supp (3) SCC 494 : AIR 1995 Supreme Court 1 in which it was pronounced that a mere draw of lots does not vest indefeasible right in the allottee for allotment at the price obtaining on the date of draw of lots. This observation was made in circumstances not similar to those obtaining in the present case as is evident from the following passage relied upon by Counsel for the respondent.

    “Now coming to the other ground, we are unable to find any legal basis for holding that the respondent obtained a vested right to allotment on the draw of lots. Since D.D.A is a public authority and because the number of applicants are always more than the number of flats available, the system of drawing of lots is being resorted to with a view to identify the allottee. It is only a mode, a method, a process to identify the allottee, i.e, it is a process of selection. It is not allotment by itself. Mere identification or selection of the allottee does not clothe the person selected with a legal right to allotment at the price prevailing on the date of draw of lots. The scheme evolved by the appellant does not say so either expressly or by necessary implication. On the contrary, Clause (14) thereof says that “the estimated prices mentioned in the brochure are illustrative and are subject to revision/modification depending upon the exigencies of layout, cost of construction, etc.” It may be noted that registration of applicants under the said scheme opened on September 1, 1979 and closed on September 30, 1979. About, 1,70,000/- persons applied. Flats were being constructed in a continuous process and lots were being drawn from time-to-time for a given number of flats ready for allotment. Clause (14) of the Scheme has to be understood in this context-the steady rise in the cost of construction and of land. No provision of law also could be brought to our notice in support of the proposition that mere draw of lots vests an indefeasible right in the allottee for allotment at the price obtaining on the date of draw of lots. In our opinion, since the right to flat arises only on the communication of the letter of allotment, the price or rates prevailing on the date of such communication is applicable, unless otherwise provided in the Scheme. If in case the respondent is not willing to take or accept the allotment at such rate, it is always open to him to decline the allotment. We see no unfairness in the above procedure.”

    7. Ms. Chandra, learned Counsel for the respondent has justifiably drawn attention to the decision of the Full Bench in Ramanand v. Union of India, AIR 1994 DELHI 29 wherein it has been held that the rates of premium chargeable from an individual whose land have been acquired shall be the predetermined rates in force at the time when the offer is made to the concerned person or the allotment of a specific plot of land in a particular area or zone, under Rule 6 of the Nazul Rules. However, as I see it, when this ratio is applied to the present case, it is certainly arguable that it could relate either to 1982 as well as to 2003. The principle laid down by the Hon'ble Supreme Court in Delhi Development Authority v. Pushpendra Kumar Jain (supra), had already been expressed in anticipation by the Full Bench, in that it had opined that “we find that an individual whose land has been acquired for planned development of Delhi has no absolute right of allotment, but, he is eligible to be considered for allotment of an alternative plot for residential purposes; and that the D.D.A may allot Nazul land to such an individual, in conformity with the plans and subject to other provisions of the Nazul Rules.”

    8. Counsel has also relied on Gurpawan Kumar v. S.P Jakhanwal., 1996 (36) DRJ 29.

    9. Mr. Sethi has drawn attention to the decision of the Division Bench of this Court in J.S Rao (Prof.) v. D.D.A, 2001 1 AD (DELHI) 235 wherein it was observed that a person whose name was incorrectly not entered in the draw of lots can claim allotment of the flat at the price prevailing on the date of his application.

    10. In my view, it would not be appropriate to proffer an opinion on the merits of these contentions raised before me in the present Petition wherein contempt of the Orders of this Court has been alleged. The correct approach in the present proceedings is to ascertain whether the words of the Order/Judgment admit of only one interpretation, which has not been implemented. Wherever two or more understandings or interpretations are reasonably possible, it is wholly inappropriate for the Court to press into use the powers contained under the Contempt of Courts Act.

    11. The following paragraph in Jhareswar Prasad Paul v. Tarak Nath Ganguly, (2002) 5 SCC 352 is of great instructive value:

    “The purpose of contempt jurisdiction is to uphold the majesty and dignity of the Courts of law, since the respect and authority commanded by the Courts of law are the greatest guarantee to an ordinary citizen and the democratic fabric of society will suffer if respect for the judiciary is undermined. The Contempt of Courts Act, 1971 has been introduced under the statute for the purpose of securing the feeling of confidence of the people in general for true and proper administration of justice in the country. The power to punish for contempt of Court is a special power vested under the Constitution in the Courts of record and also under the statute. The power is special and needs to be exercised with care and caution. It should be used sparingly by the Courts on being satisfied regarding the true effect of contemptuous conduct. It is to be kept in mind that the Court exercising the jurisdiction to punish for contempt does not function as an original or appellate Court for determination of the disputes between the parties. The contempt jurisdiction should be confined to the question whether there has been any deliberate disobedience of the order of the Court and if the conduct of the party who is alleged to have committed such disobedience is contumacious. The Court exercising contempt jurisdiction is not entitled to enter into questions which have not been dealt with and decided in the judgment or order, violation of which is alleged by the applicant. The Court has to consider the direction issued in the judgment or order and not to consider the question as to what the judgment or order should have contained. At the cost of repetition, be it stated here that the Court exercising contempt jurisdiction is primarily concerned with the question of contumacious conduct of the party, which is alleged to have committed deliberate default in complying with the directions in the judgment or order. If the judgment or order does not contain any specific direction regarding a matter or if there is any ambiguity in the directions issued therein then it will be better to direct the parties to approach the Court which disposed of the matter for clarification of the order instead of the Court exercising contempt jurisdiction taking upon itself the power to decide the original proceedings in a manner not dealt with by the Court passing the judgment or order. If this limitation is borne in mind then criticisms which are sometimes levelled against the Courts exercising contempt of Court jurisdiction ‘that it has been exceeded its powers in granting substantive relief and issuing a direction regarding the same without proper adjudication of the dispute’ in its entirety can be avoided. This will also avoid multiplicity of proceedings because the party which is prejudicially affected by the judgment or order passed in the contempt proceeding and granting relief and issuing fresh directions is likely to challenge that order and that may give rise to another round of litigation arising from a proceeding which is intended to maintain the majesty and image of Courts.”

    12. For these reasons, the present Petition is dismissed with liberty granted to the petitioner to pursue any appropriate legal proceedings so that the controversy can be laid to rest in a fuller adjudication. Parties to bear their respective costs.

    Petition dismissed.