ORDERED that the order entered January 8, 2025 [*6]is modified, on the law, without costs, by reversing so much thereof as granted petitioners' request for a preliminary injunction, and, as so modified, affirmed.
ORDERED that the orders entered April 1, 2025 and May 22, 2025 are affirmed, without costs.
ORDERED that petitioners' motion to dismiss the appeals is denied, without costs.
Footnotes
Footnote 1 Petitioners alleged that respondent's operations resulted in "relentless noise pollution," unlawfully encroached upon the Venetian's property to create access roads, and overburdened the sewer system. Upon this basis, pending a final determination on petitioners' application, Supreme Court issued a temporary restraining order prohibiting respondent from acting in violation of the terms of the declaration and applicable noise ordinances. Footnote 2
Although respondent appealed from the April 1, 2025 order, it has abandoned its appeal therefrom by failing to raise any potential issues in its appellate brief (seeZwickel v Underhill Land LLC, 243 AD3d 973, 974 n 2 [3d Dept 2025]).
3