FELHAM ENTERPRISES (CAYMAN) LIMITED v. CERTAIN UNDERWRITERS AT LLOYDS, LONDON COMPANIES, ZURICH AMERICAN INSURANCE CO., MARINE OFFICE OF AMERICA CORPORATION AND TRINITY YACHTS, INC.

ORDER AND REASONS

KURT ENGELHARDT, District Judge

Presently before the Court is Zurich's Motion for Leave to Amend Answer (Rec. Doc. No. 342). As stated herein, IT IS ORDERED that the motion is GRANTED IN PART and DENIED IN PART.

On August 19, 2004, the Court granted the motion for continuance of trial filed by Zurich for the specific and limited purpose of allowing discovery on the "stability issue" identified in the motion. See Rec. Doc. No. 47. Although not expressly stated in the August 19, 2004 Order, the Court contemplated that Zurich's discovery might lead it seek amendment of its answer to assert additional affirmative defenses based on the stability problems allegedly plaguing the M/Y Ulysses at the time of the fire. Indeed, that was the very reason Zurich requested the continuance. See August 10, 2004 Motion for Continuance (Rec. Doc. No. 206) at 25. Accordingly, the passage of the deadline for amendments to pleadings previously established does not totally preclude Zurich's efforts to amend its answer at this date.

In granting Zurich's request for a continuance in August 2004, however, the Court did not reopen discovery for all purposes or declare an open season for amendments to Zurich's answer. To the contrary, the August 19, 2004 Order expressly limited the authorized additional discovery to that directed at only the stability issue. Thus, with the exception of Zurich's proposed "Tenth Defense," the only amendments that the Court will allow are those identified in Zurich's August 10, 2004 motion for continuance of the September 20, 2004 trial date, i.e., those stemming from alleged questionable stability of the Ulysses at the time of the fire.

Indeed, the Order limits the discovery to that listed on page 24 of Zurich's Memorandum (Rec. Doc. No. 206) and any responsive discovery by Felham, Halter, and/or Trinity directly relative to that issue.

In hopes of avoiding any confusion regarding its ruling and, even more important, any subsequent motion practice regarding this issue, the Court states as follows regarding the defenses identified in Zurich's proposed amended answers (Rec. Doc. No. 342, Exhibits A and B):

1. Seventh (Felham)/Eleventh(Halter) Defense

Although labeled as one, this proposed defense actually touches on a number of defenses. To aid its discussion, the Court has broken down Zurich's assertions as follows: (a) that Felham and Halter did not report the higher project value before the fire; (b) that material changes to the design, specification, and value of the vessel occurred during construction which caused stability problems; (c) that Felham advised the builder, shortly before the sea trial, that the vessel's "trim" was unacceptable and was believed to be a design defect for which the builder was responsible; (d) that (a-c) resulted in an increased moral hazard that, when not disclosed, voided the policy; (e) that the insurance claims were manipulated to make it appear as if the Ulysses project came under the 1999-2000 policy year rather than the one under which the project was originally reported (2000-2001); and (f) that Felham and Halter knew or should have known of the above-mentioned acts/misrepresentations/omissions and that their failure to disclose this information constituted a breach of the terms and conditions of the insurance policy and the duty of utmost good faith owed under maritime law (the uberrimae fidei doctrine).

With regard to statement (a), Zurich has long been aware of the post-loss changes in reported value. The argument also has nothing to do with stability. In addition, Zurich has offered no explanation in its motion for leave to amend and supporting memorandum as to why it should be allowed to add this particular defense at this point in the litigation. Accordingly, the Court declines this requested amendment insofar as it as offered as the factual basis for an added affirmative defense.

Statement (b) does address the stability problem that was the basis of the motion to continue and, thus, can be asserted in connection with the moral hazard argument set forth in statement (d), and the uberrimae fidei doctrine and policy violation defenses referenced in statement (f).

Statement (c) alleges an impact on the vessel's trim, which the Court understands to be different from stability. Accordingly, Zurich will not be allowed at this juncture of the proceeding to offer this information as the factual basis for a new affirmative defense.

Statement (e) alleges a manipulation of the applicable policy year, and has no apparent connection to stability. Additionally, Zurich has long been aware of the change from the later policy period to the earlier, and that Continental disputed the propriety of the change. Indeed, this dispute was highlighted in the motions and supporting memoranda that Continental filed in January and February 2004. Footnote 16 of Zurich's August 10, 2004 motion for continuance, moreover, indicated that it believed then that the claim had been "manipulated to force it under the earlier policy." Despite this revelation, Zurich did not suggest it as a basis for the requested continuance. Nor did it then seek to add this as an affirmative defense. The Court will not allow it to do so at this late date.

2. Eighth (Felham)/Twelfth (Halter) Defense

This defense seeks to estop Felham and Halter from claiming any increase in the reported value of the Ulysses project higher than that which was reported prior to the fire. The Court will not allow the addition of this defense for the same reasons stated above in connection with statement (a) under the heading "Seventh (Felham)/Eleventh (Halter) Defense."

3. Ninth (Felham)/Thirteenth (Halter) Defense

This defense asserts that coverage for Owner Furnished Equipment is limited to $2.5 million. This proposed amendment is unrelated to stability, and is information that Zurich knew or should have known long ago. Indeed, Zurich's Keith Morley referenced a $2.5 million limit on OFE in correspondence to Halter's broker that is dated November 7, 2002 (Z-1817). Furthermore, Zurich has offered no explanation as to why it should be able to add this defense at this late date. Accordingly, the Court does not allow this amendment.

5. Fourteenth Defense (Halter)

This defense asserts that Halter cannot seek policy proceeds for cost overruns incurred on the Ulysses project. This argument has nothing to do with stability. In addition, neither Zurich's motion for leave to amend or its supporting memorandum explain why this defense was not asserted before December 20, 2004. Its supplemental memorandum regarding the bad faith issues (Rec. Doc. No. 358), indicates that this information was revealed during John Dane's August 16, 2004 deposition. Significantly, however, Zurich has not alleged that it was in any way prevented by Halter from discovering the information earlier in the proceeding. Nor did Zurich seek to add the defense in August 2004, or assert that it required additional discovery, as it did with the stability issue, to determine its validity. Under these circumstances, the Court declines to allow Zurich to amend its answer to assert this defense.

Halter submitted its claim in October 2002, and filed suit on July 1, 2003. On August 16, 2004, trial in this matter was little more than a month away. The discovery deadline, moreover, already had passed.

6. Tenth Defense (Felham)

This defense is that Felham's claim is barred in whole or in part by the doctrine of unclean hands and misrepresentation, and is based on the purported discrepancy between the claimed amount of the costs to strip, clean, and repaint the damaged part of the vessel, and the amount that Felham actually has spent, as well as Felham's alleged efforts to avoid disclosing the actual amounts during discovery. The Court recognizes that this defense was not specifically identified in Zurich's motion to continue. Nevertheless, the information from which this defense has arisen was not known to Zurich until Felham actually incurred these costs for the Ulysses. Furthermore, Zurich's attempts to discover this information were precluded for a number of months by Felham's objections and the Court's rulings. Accordingly, the Court will allow Zurich to amend its answer to Felham's complaint to assert this defense.

In conclusion, the Court recognizes that allowing amendments to a defendant's answer approximately a month from trial hardly is desirable. Given the specific circumstances of this particular case, the Court finds the narrow amendments allowed herein to be warranted. Nevertheless, the Court emphasizes that it does not suggest a determination of the merits of these added defenses.