Factual and Procedural Background
In November 2016, Company A and Defendant entered into a construction contract for alterations and an extension to the Defendant's home, based on the SBCC Standard Building Contract with Quantities for use in Scotland (2011 edition) incorporating Amendment 1 (March 2015). The contract price was £1,049,631.03 exclusive of VAT. Work commenced in January 2017. On 14 October 2022, Company A submitted an Interim Payment Notice for £367,808.84 to the Quantity Surveyor nominated by the Defendant, who responded that he was no longer instructed. Company A then served the Notice on the Contract Administrator, who issued a Pay Less Notice certifying that no sums were due.
On 1 December 2022, Company A served a Notice of Adjudication, appointing an adjudicator. The adjudicator determined on 9 January 2023 that the sum claimed was due and that the Defendant should bear the adjudicator's fees. Company A sought to enforce this decision through court action. The Defendant contended that the adjudicator's decision was a nullity due to failure to exhaust jurisdiction.
Legal Issues Presented
- Whether the adjudicator validly addressed the Defendant's defence that the Interim Payment Notice was invalid for failing to provide a proper basis of calculation, specifically the omission of an appendix to a letter dated 14 March 2022 which contained the calculation details.
- Whether the adjudicator failed to exhaust his jurisdiction by not properly considering the impact of the appendix not being sent to the Quantity Surveyor.
- Whether the adjudicator's decision should be enforced or set aside on the basis of jurisdictional or procedural defects.
Arguments of the Parties
Defendant's Arguments
- The adjudicator failed to address the Defendant's defence that the Interim Payment Notice was invalid because the appendix to the 14 March 2022 letter, containing detailed calculations, was neither sent with the Notice nor previously supplied to the Quantity Surveyor.
- The adjudicator did not exhaust his jurisdiction as he failed to answer the critical question of whether the Quantity Surveyor’s lack of knowledge of the appendix invalidated the Notice.
- The adjudicator's generic assertion of considering all submissions was insufficient to cure this failure, rendering the decision a nullity and unenforceable.
- Relied on established case law requiring adjudicators to address all material lines of defence to validly exercise jurisdiction.
Company A's Arguments
- The adjudicator adequately considered and dealt with the Defendant's argument regarding the Interim Payment Notice.
- The letter of 14 March 2022, although its appendix was not sent with the Notice, was incorporated by reference and had been previously sent to the Contract Administrator, a representative of the Defendant.
- The adjudicator found that the Notice met the contractual requirements for specification of sums claimed, providing sufficient detail to satisfy Clause 4.11.2.2 without requiring full breakdowns of time or rates.
- Enforcement of adjudicator decisions should be the norm unless there is a clear failure to exhaust jurisdiction or breach of natural justice.
- The Defendant's criticisms amounted to challenges on the correctness of the adjudicator's reasoning, which are irrelevant to enforcement.
- Summary decree was appropriate as there were no material factual disputes requiring proof.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Carillion Construction Limited v Devonport Royal Dockyard Limited [2005] EWCA Civ 1358 |
Adjudicator's decision enforcement; jurisdiction and natural justice standards |
Referenced to establish the court's approach to enforcement and jurisdictional limits on adjudicators. |
| Gillies Ramsay Diamond v PJW Enterprises Limited 2004 SC 430 |
Requirement for adjudicator to address all material issues and provide intelligible reasoning |
Applied to assess whether adjudicator failed to answer the question fully and intelligibly. |
| Construction Centre Group Limited v Highland Council 2002 SLT 1274 |
Adjudicator's jurisdiction and enforcement principles |
Supported the principle that failure to exhaust jurisdiction renders decision unenforceable. |
| Connaught Partnerships Limited (in administration) v Perth & Kinross Council [2013] CSOH 149 |
Obligation of adjudicator to deal with material lines of defence |
Used to define the scope of adjudication and necessity of addressing all defences. |
| Barhale Limited v SP Transmission plc [2021] CSOH 2 |
Adjudication enforcement and jurisdiction |
Referenced in context of adjudicator jurisdiction and enforcement standards. |
| Hochtief Solutions AG v Maspero Elevatori SpA [2021] CSIH 19 |
Adjudicator jurisdiction and enforcement |
Applied to confirm enforcement approach and jurisdictional limits. |
| NKT Cables A/S v SP Power Systems Ltd [2017] CSOH 38 |
Requirement for adjudicator to address all material defences explicitly or implicitly |
Used to support the principle that failure to address a defence means failure to exhaust jurisdiction. |
| Amec Group Limited v Thames Water Utilities Ltd [2010] EWHC 419 |
Adjudicator's duty to explain basis for decision |
Referenced regarding requirement for adjudicator to address defences. |
| Pilon Ltd v Breyer Group plc [2010] EWHC 837 |
Failure to exhaust jurisdiction renders adjudicator's decision unenforceable |
Supported the argument that failure to address defence invalidates decision. |
| SW Global Resourcing Ltd v Morris & Spottiswood Ltd [2012] CSOH 200 |
Presumption of regularity and adjudicator consideration of documents |
Referenced regarding adjudicator's presumed consideration of submissions and documents. |
| Atholl Developments (Slackbuie) Ltd, Petitioners [2010] CSOH 94 |
Policy of enforcing adjudicator decisions unless good reason not to |
Applied to affirm the policy favouring enforcement. |
| Miller Construction (UK) Limited v Building Design Partnership Ltd [2014] CSOH 80 |
Enforcement of adjudicator decisions |
Referenced in support of enforcement principles. |
| Morgan Sindall Construction & Infrastructure Ltd v Westcrowns Contracting Services Ltd [2017] CSOH 145 |
Enforcement of adjudicator decisions |
Referenced in support of enforcement principles. |
| Charles Henshaw and Sons Ltd v Stewart & Shields Ltd [2014] CSIH 55 |
Enforcement only refused for substantial merit, not technical objections |
Referenced to reject technical, unsubstantial objections to enforcement. |
| DC Community Partnerships Ltd v Renfrewshire Council [2017] CSOH 143 |
Adjudicator's presumption of regularity and reasoning sufficiency |
Used to support presumption that adjudicator considered relevant matters. |
| Henderson v 3052775 Nova Scotia Ltd [2006] UKHL 21 |
Principles governing summary decree |
Applied to the grant of summary decree in this case. |
| Grier v Chief Constable, Police Scotland [2020] CSOH 33 |
Summary decree principles |
Discussed in connection with summary decree application. |
| Promontoria (Chestnut) Ltd v Ballantyne Property Services [2020] CSOH 56; [2022] CSIH 17 |
Summary decree principles |
Applied to the present case’s summary decree considerations. |
| Muir Construction Limited v Kapital Residential Limited [2017] CSOH 132 |
Requirement for Interim Payment Notice to provide basis of calculation |
Distinguished by the adjudicator as relating to bare Pay Less Notice, not applicable here. |
| Tierney v GF Bisset (Inverbervie) Limited [2022] SAC (Civ) 3 |
Requirement for detail in payment notices |
Found not to assist the Defendant in this adjudication. |
| Grove Development Limited v S&T (UK) Ltd [2018] EWHC 123 (TCC) |
Incorporation by reference of previous documents in Interim Payment Notice |
Relied on by adjudicator to validate incorporation of 14 March 2022 letter by reference. |
Court's Reasoning and Analysis
The Court acknowledged the well-established principle that adjudicator decisions should generally be enforced unless there is a clear failure to exhaust jurisdiction or breach of natural justice. The Defendant contended that the adjudicator failed to address the critical issue of whether the Interim Payment Notice was invalid due to the appendix to the 14 March 2022 letter not being sent to the Quantity Surveyor, thereby failing to exhaust jurisdiction.
The Court examined the adjudicator's decision, particularly section 5, where the adjudicator identified the issues and specifically addressed the Defendant's argument that the Notice lacked an adequate basis of calculation. The adjudicator concluded that the 14 March 2022 letter, although its appendix was not sent with the Notice, was incorporated by reference and had been previously sent to the Contract Administrator, who had discretion over instructing the Quantity Surveyor.
The Court found that the adjudicator answered the question posed in its entirety and provided intelligible reasoning. The adjudicator’s conclusion that the Notice met the contractual standard for specification was clear and addressed the Defendant’s defence. The Defendant’s criticism amounted to disputing the correctness of the adjudicator’s reasoning, which is irrelevant to enforcement.
Accordingly, the Court held that the adjudicator had not failed to exhaust jurisdiction, and the defence based on jurisdictional failure was irrelevant. The Court further noted that summary decree was appropriate given the absence of material factual disputes.
Holding and Implications
The Court REFUSED the motion for summary decree as unnecessary, SUSTAINED the first plea-in-law of Company A, REPELLED the Defendant's pleas, and GRANTED decree de plano in favour of Company A for the sums claimed, with expenses.
The direct effect of this decision is to enforce the adjudicator’s decision and order payment to Company A. No new precedent was established; the ruling reaffirms the established legal principle that adjudicator decisions will be enforced unless there is a clear and plain failure to exhaust jurisdiction or breach of natural justice.