Faraday Development Ltd v. West Berkshire Council & Anor

Smart Summary

Factual and Procedural Background

This appeal concerns whether a local authority breached public procurement law by entering into a development agreement without following the required procurement process under Directive 2004/18/EC and the Public Contracts Regulations 2006. The appellant, Company A, challenged the decision of Defendant Council to enter into a development agreement with Company B for the disposal and development of industrial land in The City. The lower court dismissed Company A's judicial review claim, holding that the development agreement was neither a "public works contract" nor a "public services contract" under the relevant legislation, and that the council complied with its statutory duty to obtain best consideration. Permission to appeal was granted on grounds involving the interpretation and application of public procurement law to development agreements structured around options for land acquisition with contingent development obligations.

Legal Issues Presented

  1. Is the development agreement a "public works contract" as defined in Directive 2004/18/EC?
  2. Was it unlawful for the council to enter into the development agreement without following procurement procedures, effectively committing to a "public works contract"?
  3. If not a "public works contract," was the public procurement regime deliberately and unlawfully avoided?
  4. If not a "public works contract," is the development agreement a "public services contract"?
  5. Is the claim for a declaration of ineffectiveness precluded by the council's voluntary transparency notice?
  6. Is any claim seeking relief other than a declaration of ineffectiveness time-barred?

Arguments of the Parties

Appellant's Arguments

  • The development agreement constitutes a "public works contract" or "public services contract" under Directive 2014/24/EU and the 2015 regulations, requiring a procurement process.
  • The inclusion of a contingent obligation for development does not exclude the agreement from procurement requirements; contingent obligations are still legally enforceable once triggered.
  • The council unlawfully committed itself to entering a "public works contract" by granting Company B an option to draw down land and thereby trigger binding development obligations.
  • The development agreement was structured to avoid the procurement regime unlawfully, contrary to the anti-avoidance principle in EU law.
  • The voluntary transparency notice issued by the council was invalid and did not preclude a declaration of ineffectiveness.
  • Claims for relief other than a declaration of ineffectiveness are not time-barred.

Respondent's Arguments

  • The development agreement is not a "public works contract" because Company B was not under an enforceable obligation to carry out works at the time the agreement was entered into; it was free to "walk away".
  • The agreement falls outside the procurement regime as it does not impose mutually enforceable obligations to carry out works.
  • The council did not unlawfully commit itself to a future "public works contract"; the decisive moment for procurement obligations is the date of entering into the agreement.
  • The council's purpose in structuring the agreement was lawful commercial flexibility, not unlawful avoidance of procurement rules.
  • The development agreement is not a "public services contract" as the service obligations are ancillary and inseparable from the main object of redevelopment works.
  • The voluntary transparency notice complied with procedural requirements and precludes a declaration of ineffectiveness.
  • Claims other than for a declaration of ineffectiveness are time-barred under the relevant regulations and procedural rules.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Risk Management Partners Ltd. v Brent London Borough Council [2011] UKSC 7 Broad object of public procurement legislation is to ensure fair competition and award to best offer. Confirmed the fundamental principles underlying the Directive 2004/18/EC and the 2006 regulations.
Helmut Müller GmbH v Bundesanstalt für Immobilienaufgaben [2011] PTSR 200 (C-451/08) A "public works contract" requires that the contractor assume a legally enforceable obligation to carry out works. Held that absence of enforceable obligation excludes a contract from being a public works contract; emphasized mutual binding obligations.
Auroux v Commune de Roanne [2007] ECR I-385 (C-220/05) Definition of "public works contract" includes contracts where the contractor subcontracts works and the authority does not own the work. Supported the principle that contracting authorities entrusting works must comply with procurement rules.
European Commission v Spain [2011] 3 C.M.L.R. 43 (C-306/08) Urban land-use agreements are generally not public works contracts unless they confer contractual obligations for works. Warned against over-extension of procurement rules to planning powers and land transactions.
Remondis GmbH v Region Hannover ECLI:EU:C:2016:985 (C-51/15) Multi-stage operations must be assessed as a whole to determine if they constitute a public contract. Confirmed need to consider the entire contractual arrangement, including subsequent stages, for procurement obligations.
Midlands Co-operative Society Ltd. v Birmingham City Council [2012] EWHC 620 (Admin) Planning obligations that do not impose enforceable obligations to carry out works do not engage procurement rules. Held that absence of enforceable obligation to carry out works means no public works contract.
AG Quidnet Hounslow LLP v London Borough of Hounslow Council [2012] EWHC 2639 (TCC) Careful drafting to avoid enforceable obligations can exclude an agreement from procurement legislation. Confirmed that absence of obligation to develop site excludes the contract from procurement rules.
Ministero dell'Interno v Fastweb SpA [2015] PTSR 111 (C-19/13) Requirements for voluntary transparency notices and limits on their effect in procurement law cases. Emphasized strict interpretation of exceptions and need for clear justification to preclude ineffectiveness.
Cookson & Clegg Ltd. v Ministry of Defence [2005] EWCA Civ 811 Availability of alternative remedies precludes judicial review claims in procurement cases. Confirmed procedural rules limiting remedies and time limits for procurement challenges.
Hotel Loutraki (Cases C-145/08 and C-149/08) Mixed contracts must be assessed as indivisible wholes with classification based on main object. Applied to reject classification of contract as public services contract where main object was share acquisition.

Court's Reasoning and Analysis

The court began by examining the definitions in Directive 2004/18/EC and the 2006 regulations, focusing on whether the development agreement constituted a "public works contract" or "public services contract." It noted that a "public works contract" requires the contractor to assume a legally enforceable obligation to carry out works of pecuniary interest. The agreement at issue included contingent obligations contingent on Company B exercising options to draw down land, after which binding obligations to develop would arise.

The court distinguished this from previous cases where no enforceable obligations existed at the time of contract. It acknowledged that contingent obligations are generally not sufficient to constitute a public works contract if the contractor can unilaterally decide not to perform works. However, the court found that the development agreement was structured so that once the option was exercised, mutually binding obligations would come into effect, constituting a public works contract.

Importantly, the court held that the decisive moment for procurement obligations is the date the development agreement was entered into. At that time, the council committed itself contractually to entering into a public works contract upon option exercise, without conducting a procurement process. This effectively committed the council to future unlawful procurement conduct.

The court rejected the argument that the council deliberately and unlawfully avoided procurement rules, finding no evidence of bad faith or sham arrangements. It also held that the development agreement was not a "public services contract" because the service obligations were ancillary to the main object of redevelopment works.

Regarding the voluntary transparency notice, the court found that while procedural requirements were met, the notice failed to provide an adequate description and justification of the contract's object, rendering it invalid to preclude a declaration of ineffectiveness.

On time limits and remedies, the court accepted that claims other than for a declaration of ineffectiveness were precluded or time-barred under the relevant regulations and procedural rules, but allowed some discretion for extensions due to late disclosure of the agreement.

Holding and Implications

The court's final decision was to ALLOW THE APPEAL.

The council's development agreement, by committing to enter into a public works contract upon the option being exercised without conducting a public procurement process, breached the requirements of Directive 2004/18/EC and the Public Contracts Regulations 2006. The voluntary transparency notice was invalid to preclude a declaration of ineffectiveness. The court recognized that the council's arrangement did not amount to deliberate avoidance or sham, but nonetheless was unlawful under procurement law.

This decision directly affects the parties by recognizing that the development agreement falls within the procurement regime and that the council failed to comply with its obligations. The court did not establish new legal principles but applied and clarified existing ones concerning contingent obligations and multi-stage contracts in public procurement law. The question of appropriate relief was reserved for further submissions.

To access the original judgment, please Sign In or Subscribe.

Faraday Development Ltd v West Berkshire Council & Anor