Factual and Procedural Background
By a construction contract dated 26 March 2015, the Plaintiff ("Grove") engaged the Defendant ("S&T") to design and build a new hotel at an airport terminal. The contract sum was approximately £26.4 million, with a contractual completion date of 10 October 2016. Practical completion was not achieved until 24 March 2017.
Since completion, there have been three adjudications between the parties addressing issues such as the incorporation of a Schedule of Amendments into the contract, entitlement to an extension of time, and the validity of a Pay Less Notice issued by Grove. The third adjudication found the Pay Less Notice invalid, which, if enforced, entitled S&T to payment exceeding £14 million under interim application no. 22. Grove anticipated this adverse result and commenced CPR Part 8 proceedings.
The court was tasked with determining four issues arising from the Part 8 proceedings, S&T's counterclaim, and enforcement action related to the third adjudication:
- Whether Grove's Pay Less Notice complied with contractual requirements;
- Whether the third adjudication's decision in favor of S&T should be enforced even if the Pay Less Notice complied;
- Whether Grove is entitled at this stage to commence a separate adjudication regarding the 'true' value of interim application 22;
- Whether Grove's notices concerning liquidated damages were properly issued.
The court analyzed the relevant contract terms, the factual background including the sequence of adjudications and notices, and the parties' submissions before reaching its conclusions.
Legal Issues Presented
- Did Grove's Pay Less Notice comply with Clause 4.10.2.1's requirement to specify the basis of calculation?
- Should the third adjudication award be enforced even if the Pay Less Notice complied with contractual requirements?
- Is Grove entitled to initiate a separate adjudication to determine the 'true' valuation of interim application 22?
- Were Grove's liquidated damages notices served in a proper and effective sequence under Clause 2.29?
Arguments of the Parties
Plaintiff's (Grove) Arguments
- The Pay Less Notice validly specified the basis of calculation by referring to a detailed spreadsheet sent five days earlier, which contained comprehensive valuation details.
- Incorporation of a prior document by reference is a common and accepted practice and does not invalidate the Pay Less Notice.
- The third adjudicator erred in requiring the detailed calculation to be included within the Pay Less Notice itself.
- Following payment of the sum stated as due, Grove is entitled to commence a separate adjudication to determine the 'true' value of the interim application.
- The liquidated damages notices were served in the correct sequence and timing as required by the contract, and any delay between notices does not invalidate them.
Defendant's (S&T) Arguments
- The Pay Less Notice was invalid because it did not include the detailed calculation within the notice itself but only referred to it, contrary to the contract's use of the word "specify".
- Incorporation by reference without re-sending the detailed calculation document is insufficient and risks uncertainty and satellite disputes.
- The Pay Less Notice was served out of time if the Schedule of Amendments is not incorporated into the contract.
- The third adjudication decision should be enforced despite the Pay Less Notice's content because Grove failed to comply with the time limits in the unamended JCT conditions.
- The deduction notice for liquidated damages was invalid as it was sent before S&T had sufficient time to read and understand the preceding warning notice, breaching the required sequence.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Mannai Investment Co Limited v Eagle Star Life Insurance Co Limited [1997] 1 AC 749 |
Objective construction of notices and contracts based on how a reasonable recipient would understand them. |
Adopted to interpret the Pay Less Notice and the incorporation by reference issue. |
| Jawaby Property Investment Limited v The Interiors Group Limited [2016] EWHC 557 (TCC) |
Practical approach to the validity of pay less notices, avoiding artificial or contrived arguments. |
Supported the court's practical interpretation of the Pay Less Notice. |
| Thomas Vale Construction Plc v Brookside Syston Limited [2006] EWHC 3637 |
Rejecting fine textual analysis of withholding notices when the purpose is clear. |
Used to reject Defendant's narrow interpretation of the Pay Less Notice. |
| Windglass Windows Limited v Skyline Construction Limited [2009] EWHC 2022 (TCC) |
Courts take a practical view of withholding/pay less notices and will not allow form-based complaints. |
Supported the court's rejection of Defendant's form-based objections. |
| Henia Investments Limited v Beck Interiors Limited [2015] EWHC 2433 (TCC) |
Validity of pay less notices tested by adequacy to provide an agenda for adjudication on valuation. |
Informed the court's reasoning on the sufficiency of the Pay Less Notice. |
| Surrey and Sussex Healthcare NHS Trust v Logan Construction (Southeast) Limited [2017] EWHC 17 (TCC) |
Similar approach to pay less notice validity as Henia. |
Reinforced the practical approach to notice construction. |
| Caledonian Modular Limited v Mar City Developments Limited [2015] BLR 694 |
Contractors must set out interim payment claims clearly; employers must be given reasonable notice. |
Supported the court's view on clarity and incorporation by reference. |
| Systems Pipework Limited v Rotary Building Services Limited [2017] EWHC 3235 (TCC) |
Payment notices must specify the sum due and payable; partial calculations insufficient. |
Distinguished from the present case where the Pay Less Notice was adequate. |
| Muir Construction Limited v Kapital Residential Limited [2017] CSOH 132 |
Pay Less Notices must specify the basis of calculation so the recipient can understand it. |
Distinguished as the Pay Less Notice here did specify the basis by reference to a detailed document. |
| Henry Boot Construction Limited v Alstom Combined Cycles Limited [2005] 1 WLR 3850 |
Court and adjudicators have power to determine the 'true' value of certificates, notices, or applications. |
Supported the court's conclusion that Grove can commence adjudication on the 'true' value. |
| Banner Holdings Limited v Colchester Borough Council [2010] EWHC 139 |
No limitation on the nature or scope of disputes referable to adjudication under s.108 of the 1996 Act. |
Confirmed the broad adjudicator jurisdiction relevant to Issue C. |
| Carillion Construction Limited v Devonport Royal Dockyard Limited [2005] EWCA Civ 1358 |
Principles on enforcement of adjudicator decisions and finality subject to court review. |
Supported rejection of Defendant's attempt to enforce the third adjudication decision. |
| University of Brighton v Dovehouse Interiors Limited [2014] EWHC 940 (TCC) |
Scope of adjudication defined by the notice of adjudication. |
Confirmed that the third adjudication was limited to the Pay Less Notice content issue. |
| Rupert Morgan Building Services v Jervis [2003] EWCA Civ 1563 |
Interim certificates are not conclusive; employers can challenge overpayment by adjudication or court. |
Key authority supporting Grove's right to challenge the 'true' valuation after payment. |
| Harding v Paice [2015] EWCA Civ 1231 |
Employers entitled to start a second adjudication on 'true' valuation after invalid Pay Less Notice. |
Binding authority confirming Grove's right to a second adjudication. |
| Brown v Complete Building Solutions Limited [2016] EWCA Civ 1 |
Second adjudicator has jurisdiction if dispute is different from first adjudication. |
Confirmed that valuation dispute not decided in third adjudication and is referable. |
| Adam Architecture Limited v Halsbury Homes Limited [2017] EWCA Civ 1735 |
Employer must pay in absence of valid withholding notice and can recover overpayment later. |
Affirmed the 'pay now, argue later' principle applied by the court. |
| ISG Construction Limited v Seevic College [2015] 2 All ER Comm. 545 |
Employer deemed to have agreed valuation if failing to serve notices in time (TCC decision). |
Disagreed with by the court as inconsistent with first principles and binding authorities. |
| Galliford Try Building Limited v Estura Limited [2015] EWHC 412 (TCC) |
Similar to ISG; employer deemed agreement on valuation absent notices. |
Disagreed with by the court for same reasons as ISG. |
| Kilker Projects Limited v Purton [2016] EWHC 2616 (TCC) |
Second adjudication on value permissible for final payments but not interim payments. |
Partially consistent with court's conclusions; case concerned final payment. |
| Kersfield Developments v Bray and Slaughter Limited [2017] EWHC 15 (TCC) |
Limits on second adjudication jurisdiction for interim payments. |
Disagreed with by the court as contrary to first principles and Court of Appeal authorities. |
| Imperial Chemical Industries Limited v Merit Merrell Technology Limited (No. 2) [2017] EWHC 1763 (TCC) |
Employer has accrued right to recover overpayment before final certificate; supports second adjudication. |
Endorsed by the court as consistent with first principles and Court of Appeal decisions. |
| Aspect Contracts (Asbestos) Limited v Higgins Construction Plc [2015] UKSC 38 |
Employer entitled to recover overpayment by implied contractual mechanism or restitution. |
Supported the court's rejection of argument that no repayment mechanism exists. |
Court's Reasoning and Analysis
The court began by examining the terms of the contract, particularly the provisions relating to Pay Less Notices and liquidated damages. It found that the Pay Less Notice issued by Grove on 18 April 2017 validly specified the basis of calculation by clear reference to a detailed spreadsheet sent five days earlier, rejecting the adjudicator's narrow interpretation that the detailed calculation had to be included within the notice itself.
The court emphasized a practical and objective approach to notice construction, consistent with established authority, and rejected arguments based on hypothetical risks and dictionary definitions that would lead to artificial or contrived results. It held that incorporation by reference is a common and accepted practice in such contracts.
Regarding enforcement of the third adjudication decision, the court held that the first adjudicator's binding determination that the Schedule of Amendments was incorporated into the contract meant the Pay Less Notice was served in time, and thus the third adjudication decision finding it invalid is no longer binding or enforceable.
On the right to commence a separate adjudication concerning the 'true' value of interim application 22, the court undertook a detailed analysis of first principles, statutory provisions, the contract's language, and binding Court of Appeal authorities. It concluded that, although the employer must pay the sum stated as due in the contractor's interim application when the Pay Less Notice is deficient or absent, the employer retains the right to initiate a separate adjudication to determine the true valuation of the works.
The court rejected the contrary line of reasoning in some TCC cases that the employer is deemed to have agreed the valuation stated in the interim application by failing to serve the required notices. It found this notion unsupported by the contract, the 1996 Act, or the Scheme and inconsistent with the objective facts of the case.
On the issue of liquidated damages notices, the court held that the contract requires a warning notice and a deduction notice to be served in sequence but does not specify a minimum interval between them. Grove sent both notices on the same day, with S&T receiving them in the correct order. The court found this sufficient to satisfy the contract's requirements and rejected the argument that the notices were invalid because S&T had insufficient time to digest the warning notice before receiving the deduction notice.
Holding and Implications
The court's final rulings are as follows:
- Issue A: The Pay Less Notice issued by Grove was valid as it properly specified the basis of calculation by reference to a previously sent detailed spreadsheet.
- Issue B: The third adjudication decision finding the Pay Less Notice invalid is no longer binding or enforceable because the Schedule of Amendments was incorporated into the contract, rendering the Pay Less Notice timely.
- Issue C: Grove is entitled to commence a separate adjudication to determine the 'true' value of interim application 22 after paying the sum stated as due.
- Issue D: Grove's liquidated damages notices were properly issued in the correct sequence, and the timing between them does not render them invalid.
The direct effect of this decision is that Grove's Pay Less Notice stands as valid and enforceable, the third adjudication award in favor of S&T is unenforceable, and Grove retains the right to challenge the valuation of interim application 22 through further adjudication. The decision clarifies the interpretation of pay less notices and the scope of adjudication rights under the 1996 Act and JCT contracts, but does not establish new binding precedent beyond the application of existing principles to the facts.