Persimmon Homes (North East) Ltd & Ors v. Blyth Valley Borough Council

Smart Summary

Factual and Procedural Background

This case concerns a claim brought by three housing developers pursuant to section 113 of the Planning and Compulsory Purchase Act 2004 seeking to quash a policy known as Policy H4 in the Core Strategy produced by the Defendant Council. The Core Strategy is a Development Plan Document (DPD) adopted by the Defendant Council in July 2007 following an independent examination by an Inspector in early 2007. Policy H4 sets the proportion of affordable housing required in any housing development within the Defendant's district.

The claim challenges the legality of Policy H4 on the basis that it was not prepared in accordance with the statutory requirements, particularly the requirement to consider economic viability as set out in Planning Policy Statement 3 (PPS3), which was published after the Core Strategy had been submitted for examination. The procedural history includes the preparation of the Core Strategy, various consultations, independent examination by an Inspector, and subsequent adoption by the Council. The claimants contend that the target for affordable housing set by Policy H4 (30%) was not supported by a proper viability assessment and thus the policy is unlawful.

Legal Issues Presented

  1. Whether Policy H4 in the Core Strategy was prepared within the appropriate powers under the Planning and Compulsory Purchase Act 2004.
  2. Whether the Defendant Council complied with the procedural and substantive requirements, including having regard to relevant national policies and guidance, particularly the requirement in PPS3 to assess economic viability when setting affordable housing targets.
  3. Whether the Inspector’s examination and subsequent recommendation regarding Policy H4 were lawful and sound, despite the Core Strategy having been submitted before PPS3 came into force.
  4. Whether the absence of a detailed economic viability assessment renders Policy H4 unlawful and subject to quashing under section 113 of the Act.

Arguments of the Parties

Appellant's Arguments

  • The affordable housing target of 30% set by Policy H4 was not supported by a proper economic viability assessment as required by paragraph 29 of PPS3.
  • The Housing Needs Survey (HNS) relied upon by the Council did not address economic viability and predated PPS3, making it an inadequate evidence base.
  • Previous Inspectors had discredited the HNS as a sound evidence base, and there was insufficient information to rationally determine the appropriate percentage target.
  • The 30% figure was arbitrary and effectively “plucked out of the air,” relying only on comparability with a neighbouring district’s target rather than robust evidence.
  • The Inspector failed to properly consider the absence of viability evidence and should have adjourned the examination to obtain further evidence or recommended withdrawal of the policy.
  • The policy is unlawful because it sets a target that does not comply with relevant Government guidance and thus should be quashed.

Defendant's Arguments

  • The Core Strategy was prepared and submitted before PPS3 was published, so the Council could not have had regard to the viability requirements in PPS3 at the time of preparation.
  • The Council relied on the existing Housing Needs Survey and its own experience, including a viability-based figure of 40% from Dr Fordham, to justify the 30% target.
  • The Inspector was entitled to rely on the material before him, and the policy was a target, not an inflexible requirement, with site-specific viability to be considered at the planning application stage.
  • The appellants did not produce any detailed viability evidence to challenge the 30% target before the Inspector or the Council.
  • The policy was subject to extensive consultation with stakeholders, including developers, during its preparation.
  • The Inspector’s approach was lawful and consistent with the statutory framework and relevant guidance.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court began by outlining the statutory framework under the Planning and Compulsory Purchase Act 2004, emphasizing the procedural requirements for preparing Development Plan Documents, including the need for front-loading and compliance with national policies and guidance. The Court noted that the Core Strategy, once adopted, forms part of the Development Plan and must be accorded significant weight in planning decisions under section 38(6) of the Act.

The Court then examined the relevant national policy guidance, particularly PPS3, which came into force after the Core Strategy was submitted for examination. PPS3 requires local planning authorities to set affordable housing targets based on an informed assessment of economic viability, including consideration of site thresholds and proportions. The Court found that the Defendant Council's Policy H4 did not comply with this requirement, as it was based on a Housing Needs Survey from 2004 that addressed need but not viability, and no detailed viability evidence was produced.

The Court reviewed the Inspector’s report and noted that the Inspector accepted the 30% target as a realistic compromise between the 10% and 40% options, but acknowledged that the target was to be applied flexibly with site-specific viability considerations at the planning application stage. The Inspector also recommended that the Council undertake further viability studies and a Strategic Housing Market Assessment (SHMA) after adoption.

Despite these findings, the Court held that the absence of a proper viability assessment at the plan-making stage meant that the 30% target was legally flawed. The Court acknowledged arguments that the policy was only a target and that site-specific viability would be considered later, but emphasized that the starting point must itself be sound and lawful. The Court found the policy to be tainted by error of law because it failed to comply with the relevant national policy guidance requiring viability assessment.

The Court considered whether the Inspector should have adjourned the examination or required further evidence but concluded that the failure to comply with the viability requirement was a fundamental flaw. The Court also noted the new statutory presumption of soundness under section 113 but found that the claimants had demonstrated substantial prejudice from the flawed policy.

Holding and Implications

The Court held that Policy H4 in the Core Strategy was unlawful and quashed it in part, specifically the provisions setting the affordable housing target and related paragraphs in the supporting text.

The direct consequence of this decision is that the Defendant Council must reconsider and re-determine the affordable housing target in accordance with proper viability assessments and relevant national policy guidance. The Court acknowledged that until a new policy is adopted, the Council remains entitled to require affordable housing on a case-by-case basis, considering individual site circumstances.

No new precedent was established beyond the application of existing statutory and policy requirements to the facts of this case. The Court granted leave to appeal due to the novelty of the statutory presumption of soundness under section 113 and the potential differing interpretations of its application.

To access the original judgment, please Sign In or Subscribe.

Persimmon Homes (North East) Ltd & Ors v Blyth Valley Borough Council

Contains public sector information licensed under the Open Justice Licence v1.0.

Use AI to get other relevant cases.

Comments

Persimmon Homes (North East) Ltd & Ors v Blyth Valley Borough Council
(May 20, 2008)