O R D E R
This Miscellaneous Petition has been filed assailing the Award dated 29/03/2023 which was pronounced on 12/06/2023 by the Presiding Officer, Labour Court Sidhi, whereby the claim of the petitioner has been rejected.
2. It is the case of the petitioner that he was the workman in the respondents Department since 01/07/1999 working as a daily rated employee on the post of skilled labour with utmost honesty and sincerity. After continuously working for a long time, his services were orally terminated vide order dated 15/02/2018. He raised an industrial dispute regarding illegal termination before the Conciliation Officer who has ultimately referred the dispute to the Labour Court Sidhi which was registered as dispute case No.16/2020/IDR. On notice being issued, respondents filed the written statement before the Labour Court denying the claim of the petitioner. Respondents have neither filed any document
1
nor adduced any evidence before the Labour Court but despite of same, vide Award dated 29/03/2023, Labour Court has rejected the case of the petitioner on the ground that petitioner has failed to prove 240 days continuous working in the respondents Department.
3. It is argued that once there is a specific averment made by the petitioner with respect to his continuous working of 240 days in the respondents Department, the burden is shifted to the respondents to establish the same. Petitioner specifically contended that he was inducted on 01/07/1999 and continuously worked up to February, 2018 and on 15/02/2018, he was orally terminated. The Authorities have not followed the provisions of retrenchment in terms of Section 25-F(a), (b) and (c) of Industrial Disputes Act and without following the same, termination will be illegal. The Labour Court has failed to consider the aforesaid aspect of the matter. The Labour Court has found that except Ex.P/7 and P/8, no other document has been filed to show the continuous working from 01/07/1999 to 15/02/2018 and it is the case of the petitioner himself that he has been paid the minimum wages lastly Rs.6,500/-. It was further observed by the Labour Court that no other documents have been filed by the petitioner to substantiate the arguments to show his continuous working of 240 days in a calendar year and the entire burden is upon the petitioner to substantiate the same. Once the petitioner himself has failed to establish his working for 240 days continuously, then in all fairness, the Authorities prior to termination of his services should have at least issued a notice and followed the provisions contemplated under Section 25-F of Industrial Disputes Act for retrenchment. The Labour Court has failed to appreciate the fact that if documents Ex.P/7 & P/8 are seen, then it is an
2
admitted position that there is continuous working of petitioner for more than 240 days in a calendar year.
4. On notices being issued, respondents have marked their presence and supported the impugned Award. It is argued that heavy burden is on the petitioner to establish that he has worked for 240 days in a calendar year. Several documents have been produced by the petitioner before the Labour Court but Labour Court has found that no such document is available on record 240 days continuous working in a calendar year. The entire burden of proving the same is on the petitioner and he cannot shift the burden on respondents Department and say that they have not lead any evidence to discard the averments of the petitioner. The fact remains that the petitioner is required to prove his own case. The Labour Court has rightly found that except two documents i.e. Ex.P/7 & P/8, there is no document produced on record to show continuous working of more than 240 days in a calendar year. Under these circumstances, no illegality was committed by the Labour Court, therefore prayed for dismissal of the present Miscellaneous Petition.
5. Heard learned counsel for the parties and perused the record.
6. Apart from the admitted facts regarding initial induction of petitioner in respondents Department on 01/07/1999 and oral termination of the petitioner on 15/02/2018, as alleged by the petitioner, no other facts are admitted in the case. It is the case of the petitioner that he has continuously rendered his services from 01/07/1999 to 15/02/2018 and by oral termination order, his services have been dispensed with. The fact remains that petitioner is required to prove that he has worked for more than 240 days in a calendar year in terms of the judgment passed by Hon'ble Supreme Court in the case of Sub
3
Divisional Engineer Irrigation Project Yawatmal Vs. Sarang Mahotrao Gurnule reported in 2009 (120) FLR 114. Petitioner has produced certain documents in support of his case, however if the documents Ex.P/7 & P/8 filed before the Labour Court are seen, then it is clear that these are the certificates issued under the seal and signature of Assistant Engineer pointing out the fact that petitioner has continuously worked from the year 2006 to 2008 and 2009 to 2012 in the respondents Department. The relevant extract of both the certificates are as under:-
"izek.k i= izekf.kr fd;k tkrk gS fd Jh bUnzHkku ;kno firk Jh JhHkku ;kno yks-Lok-;k- foHkkx esa dk;Zjr jgdj yxkrkj gS.M iEi la/kkj.k dk dk;Z fd;k gS] ;s 2006 ls 2008 rd yxkrkj dk;Z fd;kA budk dk;Z larks'k tud jgkA buds Hkfo'; dh mTtoy dkeuk djrk gwaA
¼Ogh-,l- feJk½
lgk;d ;a=h
yksd Lok- ;ka- fo- mi [k.M
ftyk&lh/kh ¼e-iz-½
izek.k i=
izekf.kr fd;k tkrk gS fd Jh bUnzHkku ;kno firk Jh JhHkku ;kno xzke&iks- Fkkuk cgjh ftyk lh/kh }kjk yks-Lok- ;k- foHkkx esa gS.M iai eSdsfud ds lkFk jgdj gS.M iEi la/kkj.k dk dk;Z fd;k gS] budk dk;Z larks'k tud gSA ;s 2009 ls 2012 rd yxkrkj dk;Z fd;kA
¼Ogh-,l- feJk½
lgk;d ;a=h
yksd Lok- ;ka- fo- mi [k.M
ftyk&lh/kh ¼e-iz-½"
7. There is no dispute with respect to issuance of the documents by the Authority of the respondents. If these documents are perused, then it is clear that petitioner has continuously worked from 2006 to 2008 and
4
2009 to 2012 in the respondents Department. Thus, it is well established that petitioner has worked for more than 240 days in a calendar year in the respondents Department. There is no counter by the respondents to the aforesaid aspect. As the Authorities have not examined anyone on their behalf before the Labour Court, therefore Labour Court has wrongly taken note of the fact that no other document is placed on record by the petitioner to substantiate 240 days continuous working. In fact Ex.P/7 and P/8 are already on record. They are required to be countered by the respondents.
8. Under these circumstances, finding recorded by the Labour Court with respect to the fact that petitioner failed to prove continuous working for 240 days in a calendar year, is contrary to the documents Ex.P/7 & P/8. Therefore, impugned Award dated 29/03/2023 which was pronounced on 12/06/2023 is unsustainable. Accordingly, the same is
set aside. The Matter is remanded back to the Labour Court to re- appreciate the evidence available on record and Management be granted opportunity to lead evidence to substantiate their arguments. The entire exercise be completed within a period of 90 days from the date of receipt of certified copy of this order.
9. With aforesaid observations, petition is finally disposed off. No order as to costs.
(VISHAL MISHRA)
JUDGE
Shbhnkr
5