P. Sam Koshy, J.:— The limited relief sought for by the petitioner in the present writ petition is for appropriate direction to the respondent no. 4 & 5 for finalising and closing of the contract entered into between the petitioner with respondents and for final settlement of bills qua the work that has been executed by the petitioner.
2. Matter relates to the work for upgradation and renewal of Uslapur-Daija Road.
3. Contention of petitioner is that except for some minor works, the substantial work has already been executed by the petitioner. That the non completion of minor work was on account of administrative reasons and petitioner as such was not responsible or could not have done unless the respondent State would have made the execution of the work free from all disputes and hurdles.
4. Learned counsel for the petitioner therefore submits in the given factual backdrop where he has substantially concluded the work except for some minor work which was left to be done carried out at that point of time, the petitioner wants tender to be finalized and settled after due verification of actual works completed by the petitioner.
5. Learned State counsel submits that there seems to be already correspondence being made by the petitioner with respondents in this regard and certain preliminary enquiry, discussions have already been taken place as would be evident from the documents enclosed with the writ petition.
6. Learned Additional AG further submits that Clause 28 of the agreement also speaks of availing arbitration clause for resolving the dispute, wherein certain mechanism available is prescribed in the said agreement itself which the petitioner has to avail first before respondents could take a decision finally on the request so made by the petitioner.
7. Considering the nature of dispute that petitioner has with the respondents and nature of relief that he seeks, this Court is of the opinion that since the matter is already under process and under consideration by the respondents in this regard, let petitioner once again approach respondent no. 4 & 5 in this regard by moving an appropriate fresh application in respect of closure and settlement of Contract and for also final settlement of bills unpaid, if any.
8. Let petitioner move an appropriate application to respondent no. 4 & 5 within a period of three weeks in addition to the representations which he has already made. The respondent no. 4 & 5 in turn shall scrutinize the said claim and after due verification of facts shall take an appropriate decision for closure of contract as also for the settlement of final bills itself at the earliest preferably within a further period of 60 days from the date petitioner makes the representation to the respondent no. 4 & 5.
9. Learned counsel for the petitioner submits that there are certain penalty clause which the respondents have imposed while granting extension of time. However, those extensions were sought by the petitioner because of the hurdles that had arisen on the part of the respondents and that it was not the fault on the part of the petitioners in execution of work which had caused the delay but were all because of administrative reasons.
10. Given the fact that extension of time has already been granted by the respondents, it would be more appropriate for leaving that issue open for the petitioner to raise it before respondent no. 4 & 5 in the representation that he is suppose to make.
11. The writ petition therefore stands disposed of.