1. The Appellant filed an online RTI application dated 24.09.2021 seeking the following information:
“1. Pls. provide clause number of RFP where definition for Hard Copy of Original of all Documents uploaded on-line at time of bid submission is provided.
2. Pls. provide clause number of the RFP which prescribes any ink colour signature of documents by the Team leader & Traffic Planer.
3. Pls. provide the copy of Evaluation Committee Minutes and relevant Note Sheet wherein the decision of bid rejection and or disqualification pertaining to the A.K. Construction Manufacturers Pvt. Ltd. (hereinafter referred as AKCM) is taken.
4. Pls. provide the copy of all Minutes of Meeting of Evaluation Committee for Empanelment of Safety Consultants for NHAI.
5. Pls. provide the copy of file noting wherein constitution of Evaluation Committee and its mandate was approved.
6. Pls. provide the copy of relevant noting wherein two re-presentations dated 25.8.21 and 9.9.21 submitted by AKCM were dealt.
7. Provide copy of the pages of the noting filed and correspondence pages staring from receipt of bids, final declaration of results and dealing of representations against the disqualification of bidders.”
2. The CPIO furnished a point wise reply to the appellant on 20.10.2021 stating as under:—
“query no. 1 : - Provisions Of RFP were sell-explanatory and were already available on e-tender portal. However. Cause 7 of “Notice for empanelment of safety consultant” of RFP is self explanatory. The copy of the notice is annexed for information,
Query no. 2 : - Provisions of RFP were self-explanatory and were already available on e-tender, portal. However, Clause 20.2 (d) of “General information of RFP is self-explanatory. The copy of relevant clause is annexed for information.
Query no. 3 to 7 : - information sought may not be provided as per Section 8 (1) (d) of the RTI Act, 2005.
3. Being dissatisfied, the appellant filed a First Appeal dated 15.11.2021. FAA's order dated 02.12.2021 upheld the reply of the CPIO.
4. Feeling aggrieved and dissatisfied with the denial of information by the CPIO, the appellant approached the Commission with the instant Second Appeal.
Relevant Facts emerging during Hearing:
5. The following were present:—
Appellant: Present through intra-video conference.
Respondent: Manoj Kumar, GM (T) & CPIO present through intra-video conference.
The instant case has been heard on urgent hearing basis.
6. The Appellant reiterated the contents of his instant Appeal which is reproduced below in verbatim -
a. NHAI had called for an open RFP for of Empanelment of Safety Consultants for NHAI Projects (Tender ID 2020_NHAI_60322_1) in Oct 2020 and all bids were submitted in January 2021. It is important to mention that this RFP was only for Empanelment of Consultants and no financials bids were sought. The A.K. Construction Manufacturers Private Limited in short AKCM applied and undersigned singed all documents as its authorised signatory.
b. After much delay and deliberation, the evaluation of the RFP was completed, and we (AKCM) were selected as Technically Qualified Bidder in the month of July 2021. The Evaluation Committee of NHAI selected our firm, A.K. Construction Pvt. ltd. as a Successful Technical Qualified Bidder with a high technical score of 89/100. This score was even to our firm by the NHAI Evaluation Committee. Thereafter, on asking of the Road Safety Cell of NHAI, we had submitted our original bid documents for verification purposes and formal issue of our empanelment letter/Order with NHAI.
c. However, to our dismay the Safety Cell of NHAI at the behest of Dr. H.M Nagvi, CGM, NHAI & First RTI Appellant Authority disgualified us (AKCM) without putting the case to NHAI Evaluation Committee which was the only Competent Authority to decide on empanelment/disgualification of any firm.
d. At this stage it is important to mention that since inordinate delay took in announcing the results of Evaluation, which was much more than time taken in NHAI for similar nature if evaluation, undersigned wrote to Dr. H.M Nagvi, CGM, NHAI for early announcing results of Evaluation. This my reguest annoyed Dr. H.M Nagvi, so much that he saw to it that my firm is disgualified despite scoring high technical marks as mentioned in above para. Copy of my email letter dated 23.7.2021 at Annexure V.
e. The summarily disgualification of our selected firm (AKCM) was done at the level of a Deputy Manager, NHAI in Road Safety Cell NHAI under the direct instruction of Dr. H.M. Nagvi, CGM, NHAI of Road Safety Cell of NHAI. This is a violation of due process and public procurement procedure followed by NHAI as any final decision of qualification/disqualification is to be taken by the Evaluation Committee and not individual levels.
f. Moreover, we made several representations and also submitted affidavit & proposed in-person verification of our Key Resources/Team to satisfy any requirement/confusion that they might have. None of our letters were replied or acknowledged.
g. Despite our best efforts we were denied any opportunity and our two RTI regarding the procurement process that was followed were blatantly denied on false and frivolous grounds .Annexure II & IV refers.
D. The information which has been denied is detailed in Annexure I from Sl.no 3-7. As evident, the requested information is not covered under Section 81(D) of the RTI act 2005. “It should be noted that the information that is sought is only for the due process that was followed during the procurement process and not any “information including commercial confidence, trade secrets or intellectual property, the disclosure of which would harm the competitive position of a third party’.
7. In response to Appellant's contentions and at the instance of the Commission, the CPIO explained in great detail the reasons for disqualification of Appellant's firm on account of non-submission of the original scanned signature by the Appellant along with the documents. Further, in response to points no. 3-7 of RTI Application, he reiterated the denial of information under section 8(l)(d) of the RTI Act. However, at the behest of the Commission he agreed to provide a revised reply along with the relevant information concerning the Appellant only.
DECISION
8. The Commission observes from a perusal of records that blanket denial of information by the then CPIO in response to points no. 3-7 of RTI Application under Section of Section 8(l)(d) of RTI Act and also by the present CPIO during the hearing; was completely inappropriate in view of the fact the information as sought by the Appellant pertains to his own case where his firm has not been selected for the position of a ‘safety consultant’ and for which he has a constitutional right to know for the purpose of his own defence. The only pertinent exemption from disclosure of information against the instant RTI Application appears to be with respect to the names and identifying particulars of the review committee member(s) and/or other officers which may be reflected on the notings/comments/correspondences and cannot be divulged considering the exemptions envisaged under Section 8(1)(j) and Section 8(1)(g) of the RTI Act.
9. In view of the foregoing, the CPIO is directed to provide a revised point wise reply along with the relevant available information which will suffice the information sought for at points no. 3 - 7 RTI Application after redacting the names and identifying particulars of the officers/review committee members, if any, which may figure in the notings/comments/correspondences keeping in view the exemption clause of Section 8(1)(i) and 8(1)(g) of the RTI Act and can be severed in consonance with Section 10 of RTI Act.
10. The aforesaid reply/information shall be provided by the CPIO free of cost to the Appellant within 15 days from the date of receipt of this order under due intimation to the Commission.
11. Notwithstanding the aforesaid, the issue raised by the Appellant regarding rejection of his firm by the Committee members is a grievance which is not amenable under the RTI Act. In this regard, the Appellant is advised to pursue the matter through an administrative mechanism.
12. The appeal is disposed of accordingly.