Summary of Opinion — Company Appeal (AT) (Insolvency) No. 675 of 2020

Date of this order (virtual hearing): 22.01.2021. Impugned order dated: 15 June 2020 (Adjudicating Authority, NCLT Ahmedabad Bench). Bench: Justice Bansi Lal Bhat (Acting Chairperson); Kanthi Narahari (Member, Technical); Dr. Alok Srivastava (Member, Technical).

Factual and Procedural Background

The Appellant, an operational creditor, filed an application under Section 9 of the Insolvency and Bankruptcy Code, 2016 seeking initiation of the Corporate Insolvency Resolution Process against the Respondent corporate debtor. The Adjudicating Authority (National Company Law Tribunal), Ahmedabad Bench, by an order dated 15 June 2020, dismissed the Section 9 application on the ground that it was non-maintainable.

The appellant challenged that impugned order before the appellate forum (the present order dated 22.01.2021). The appellant's principal grievance on appeal was that the Adjudicating Authority dismissed the petition as non-maintainable without giving the appellant an opportunity to rectify alleged defects or shortcomings in the filing.

Legal Issues Presented

  1. Whether the Adjudicating Authority was justified in dismissing the Section 9 application as "non-maintainable" due to alleged defects in Form 5 (absence of signature by the authorised person, lack of notarization and omission of date), when a Board Resolution authorising filing under the IBC existed and advocates had signed the petition.
  2. Whether the Adjudicating Authority failed to comply with the proviso to Section 9(5) of the I&B Code by not giving the applicant an opportunity to rectify any defects in the application before rejecting it as incomplete or non-maintainable.
  3. What remedial relief should follow if the Adjudicating Authority erred by not providing an opportunity to cure defects (i.e., whether the impugned order should be set aside and the matter remitted for giving opportunity and for fresh decision on admission or rejection).

Arguments of the Parties

Appellant's Arguments

  • The Adjudicating Authority erred in dismissing the Section 9 application as non-maintainable for alleged defects in Form 5 (not being signed by the authorised person named in the Board Resolution, not notarized, and lacking a date), without first giving the appellant an opportunity to rectify such defects.
  • Because the filing was supported by a Board Resolution (dated 28.09.2018) authorising Mr. Praveen Kumar B. Mundra to institute proceedings under the IBC, and the petition bore signatures of two advocates (albeit without dates), there was insufficient justification to treat the application as non-maintainable rather than merely incomplete.

The opinion does not set out any detailed or specific arguments advanced by the Respondent in the record before this appellate forum.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The appellate court examined the impugned order, focusing on paragraphs 11 and 14. Paragraph 11 contained the Adjudicating Authority's finding of non-maintainability grounded on the absence of signature by the authorised person named in the Board Resolution, lack of notarization of Form 5 and omission of date, noting the petition was signed by two advocates instead.

Paragraph 14 made it clear that the petition was dismissed on maintainability grounds and stated that the Adjudicating Authority's observations did not constitute an opinion on the merits; it also indicated the petitioner could pursue its claim in an appropriate forum.

The appellate court took judicial notice of the Board Resolution dated 28.09.2018 authorising Mr. Praveen Kumar B. Mundra to file proceedings under the I&B Code. Given that the filing was backed by the Board Resolution and the petition bore signatures of advocates (albeit undated), the court found little justification to treat the defects as rendering the petition non-maintainable.

The court emphasized the legal distinction between an "incomplete" application and one that is "non-maintainable" (the latter having broader contours). It relied on the statutory scheme of Section 9(5) of the I&B Code, which prescribes that the Adjudicating Authority, before rejecting an application as incomplete under clause (ii)(a), must give notice to the applicant to rectify defects within seven days of receipt of such notice from the Adjudicating Authority (the proviso to Section 9(5)).

Applying that statutory mandate, the appellate court concluded that the Adjudicating Authority failed to provide the appellant the opportunity to cure the noted filing defects. Dismissing the application as non-maintainable for such a technical omission, without following the statutorily prescribed opportunity-to-rectify procedure, was not warranted.

Holding and Implications

Core Ruling: The appeal was disposed of in favour of the Appellant — the impugned order dated 15 June 2020 is set aside and the matter is remitted to the Adjudicating Authority with directions.

Specifically, the appellate court directed the Adjudicating Authority to allow the Appellant/Applicant an opportunity to rectify any defects in the application and thereafter to pass an order of admission or rejection on the merits in respect of initiation of the Corporate Insolvency Resolution Process. The appellate court made it explicit that it was not expressing any opinion on the merits of the underlying dispute.

Direct procedural consequences recorded in the opinion: a copy of the order was to be communicated to the Adjudicating Authority forthwith, and the parties were directed to appear before the Adjudicating Authority on 3rd February, 2021.

Implications: The decision's immediate effect is the vacatur of the NCLT's dismissal and remittal for compliance with the statutory rectification procedure under Section 9(5). The appellate court did not decide the substantive dispute and stated no opinion on merits; accordingly, no broader legal principle beyond enforcing the Section 9(5) proviso was laid down as a new precedent in this opinion.

This summary is based exclusively on the content of the provided opinion. No material beyond that opinion has been included or inferred.

To access the original judgment, please Sign In or Subscribe.

    Silvassa Cement Products Pvt. Ltd. v. Noor India Buildcon Pvt. Ltd. .

    (Through Virtual Mode) 22.01.2021: Application filed by the Appellant Operational Creditor under Section 9 of the Insolvency and Bankruptcy Code, 2016 seeking initiation of Corporate Insolvency Resolution Process against the Respondent Corporate Debtor stands dismissed by the Adjudicating Authority (National Company Law Tribunal), Ahmedabad Bench Ahmedabad Court II in terms of the impugned order dated 15th June, 2020 on the ground that the same was non-maintainable. The impugned order is assailed, inter-alia, on the ground that the Adjudicating Authority has violated the mandate of law in not providing opportunity to the Appellant for rectifying the defect or remove the shortcomings.

    2. After hearing learned counsel for the parties for a while, we find that the finding in regard to non-maintainability of the application is recorded in para 11 of the impugned order, which reads as under:- Contd./

    11. On perusal of the record it is found that Board Resolution was passed on 28.09.2018 authorising Mr. Praveen Kumar B. Mundra (Manager) to file/defend the legal proceedings and Insolvency and Bankruptcy Code on behalf of the company (Page No.16- Exhibit A) apart from other powers such as filing of Vakalatnama, engaging counsel etc. but, in the instant case Form 5 i.e. application is neither signed by authorised person named above nor it is notarized; rather the petition is signed by Mr. Niraj Shah and Mr. Dhruv K. Dave, advocates and date is also not mentioned. Thus, in view of the above, the petition is bad in the eye of law and it is not maintainable in view of the above case laws.

    3. Though some more observations have been made in regard to the operational debt in respect of which default is alleged in para 14, the finding is that the petition has been dismissed on the issue of maintainability taking into consideration provisions of I&B Code. Para 14 of the impugned order is extracted hereinbelow:-

    14. However, this will not stand in the way of the Petitioner approaching the appropriate forum seeking to enforce its claim against the Respondent as this petition has been dismissed on the issue of maintainability and taking into consideration the provisions of IB Code, 2016. The observations made by us on any other aspect would Company Appeal (AT) (Insolvency) No. 675 of 2020 not constitute an expression of opinion on the merit of controversy

    4. Reading Para 11 in juxtaposition with Para 14, it is absolutely clear that application has been dismissed on the issue of non-maintainability which relates to omission in appending of signatures on the application in the prescribed format in Form 5 and the same being notarized. We take notice of the fact that the Adjudicating Authority has noticed the Board Resolution passed on 28th September, 2018 authorising one Mr. Praveen Kumar B. Mundra, Manager to file legal proceedings including proceedings under I&B Code. Once the filing of the application under Section 9 was backed by the Board Resolution and Adjudicating Authority had noticed that two Advocates viz. Mr. Niraj Shah and Mr. Dhruv K. Dave had signed the petition, albeit without recording date, there was hardly any justification on this score for holding that the application was non-maintainable. Incompleteness is distinct from non-maintainability, the latter having broader contours. If, there was any shortcoming in regard to filing of Vakalatnama or making endorsement in regard to date in the prescribed format, Appellant could be provided an opportunity in terms of mandate of proviso under Section 9(5) of the I&B Code, which reads as under:-

    9. Application for initiation of corporate insolvency resolution process by operational creditor. Company Appeal (AT) (Insolvency) No. 675 of 2020

    x.x.x (5) The Adjudicating Authority shall, within fourteen days of the receipt of the application under sub-section (2), by an order

    (i) admit the application and communicate such decision to the operational creditor and the corporate debtor if, - (a) the application made under sub-section (2) is complete; (b) there is no [payment] of the unpaid operational debt; (c) the invoice or notice for payment to the corporate debtor has been delivered by the operational creditor; (d) no notice of dispute has been received by the operational creditor or there is no record of dispute in the information utility; and (e) there is no disciplinary proceeding pending against any resolution professional proposed under sub-section (4), if any.

    (ii) reject the application and communicate such decision to the operational creditor and the corporate debtor, if (a) the application made under sub-section (2) is incomplete; (b) there has been [payment] of the unpaid operational debt; (c) the creditor has not delivered the invoice or notice for payment to the corporate debtor; Company Appeal (AT) (Insolvency) No. 675 of 2020 (d) notice of dispute has been received by the operational creditor or there is a record of dispute in the information utility; or (e) any disciplinary proceeding is pending against any proposed resolution professional: Provided that Adjudicating Authority, shall before rejecting an application under sub-clause (a) of clause (ii) give a notice to the applicant to rectify the defect in his application within seven days of the date of receipt of such notice from the Adjudicating Authority.

    5. Thus, we find that the Adjudicating Authority who was required to pass the order of admission or rejection of the application being satisfied about the completion of the application and proof of debt and default as mandated under Section 9(5) has failed to provide opportunity of rectifying the defect as noticed and allowing the applicant to bring it in conformity with the requirements of law. Dismissal of application as being non-maintainable for such technical defect is not warranted. We accordingly, set aside the impugned order and remit the matter back to the Adjudicating Authority to allow the Appellant/Applicant opportunity of rectifying the defect, if any, in the application and thereafter pass order of admission or rejection in regard to initiation of Corporate Insolvency Resolution Process on merit. Appeal is disposed off with aforesaid observations. Company Appeal (AT) (Insolvency) No. 675 of 2020

    6. We make it clear that we are not expressing any opinion on the merits of the case.

    7. A copy of this order be communicated to the Adjudicating Authority forthwith. Parties are directed to appear before the Adjudicating Authority on 3rd February, 2021. [Justice Bansi Lal Bhat] Acting Chairperson [Kanthi Narahari] Member (Technical) [Dr. Alok Srivastava] Member (Technical) am/gc Company Appeal (AT) (Insolvency) No. 675 of 2020