AMICUS AI
Citation Codes
Neutral Citations
2019 INSC 347
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 5, Limitation Act
  • Section 1942 days (Limitation Act)
  • Section 5 of the Limitation Act
  • Haryana Urban Development Authority Act, 1977
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2019 INSC 347
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 5, Limitation Act
  • Section 1942 days (Limitation Act)
  • Section 5 of the Limitation Act
  • Haryana Urban Development Authority Act, 1977
Smart Summary

Facts:

This case arises from civil suit proceedings initiated by the respondent against the appellant, HUDA. The appellant filed an appeal challenging the decision of the High Court, which denied their request for condonation of a significant delay in filing their appeal.

Issue:

Whether the delay of 1942 days (approximately 4 years and 6 months) in filing the appeal can be condoned under Section 5 of the Limitation Act, based on the explanations provided by the appellant.

Holding:

The High Court's decision to deny the condonation of delay was upheld, as the appellant failed to provide a sufficient cause for the inordinate delay.

Reasoning:

The High Court found that a delay of 1942 days is excessively long and characterized as wholly inordinate. The explanations provided by HUDA for this delay were deemed insufficient and unconvincing. The court emphasized that the reasons cited did not meet the threshold of "sufficient cause" as required by Section 5 of the Limitation Act. Consequently, the High Court's refusal to condone the delay was justified and warranted.

Conclusion:

The appeals filed by HUDA were dismissed, affirming the High Court's ruling on the matter of delay. The court's decision reinforces the necessity for appellants to provide compelling reasons when seeking to condone delays in legal proceedings.

Disposition:

Appeals dismissed.

To access the original judgment, please Sign In or Subscribe.

    Estate Officer, Haryana Urban Development Authority And Another v. Gopi Chand Atreja .

    Abhay Manohar Sapre, J.— These appeals are directed against the final judgment and orders dated 23-1-2008 and 5-5-2008 passed by the High Court of Punjab and Haryana at Chandigarh in HUDA v. Gopi Chand Atreja RSA No. 4110 of 2007 and HUDA v. Gopi Chand Atreja RA-RS No. 23-C of 2008 in RSA No. 4110 of 2007 respectively whereby the High Court dismissed the second appeal as well as the review application filed by the appellants herein.

    2. These appeals involve a short point as would be clear from the facts mentioned hereinbelow.

    3. The appellant herein is the Haryana Urban Development Authority (hereinafter referred to as “HUDA”). They are the defendants whereas the respondent is the plaintiff in the civil suit out of which these appeals arise.

    4. The respondent filed a civil suit being Civil Suit No. 305 of 2000 in the Court of Civil Judge (Junior Division), Karnal against the appellant (HUDA) claiming a decree for declaration with consequential relief of permanent and mandatory injunction in relation to the suit land. The suit was decreed by the trial court on contest vide judgment/decree dated 1-5-2001.

    5. The appellant-defendants felt aggrieved and filed first appeal being Civil Appeal No. 92 of 2001 in the Court of Additional District Judge, Karnal. By the judgment dated 7-2-2002, the first appellate court dismissed the appeal and affirmed the judgment/decree of the trial court.

    6. The appellants felt aggrieved and filed second appeal in the High Court of Punjab and Haryana at Chandigarh. Since the appeal filed by the appellant was barred by 1942 days, the appellants filed an application under Section 5 of the Limitation Act and prayed for condoning the delay in filing the second appeal.

    7. By the impugned order dated 23-1-2008 RSA No. 4110 of 2007, the High Court rejected the application and declined to condone the delay. The High Court held that the cause pleaded by the appellants for condoning the delay is not a sufficient cause. As a consequence, the second appeal was also dismissed as being barred by limitation. Challenging the said order, the appellants filed a review petition. By order dated 5-5-2008 RA-RS No. 23-C of 2008 in RSA No. 4110 of 2007, the High Court also dismissed the review petition. Against the orders dated 23-1-2008 RSA No. 4110 of 2007 and 5-5-2008 RA-RS No. 23-C of 2008 in RSA No. 4110 of 2007, the appellant-defendants have filed these appeals by way of special leave in this Court.

    8. So, the short question, which arises for consideration in these appeals, is whether the High Court was justified in dismissing the appellants' second appeal on the ground of limitation.

    9. In other words, the question that arises for consideration in these appeals is whether the High Court was justified in not condoning the delay of 1942 days in filing the second appeal by the appellant-defendants.

    10. Heard Mr Vishwa Pal Singh, learned counsel for the appellants and Mr Gagan Gupta, learned counsel for the respondent.

    11. Having heard the learned counsel for the parties and on perusal of the record of the case, we find no merit in these appeals. In our view, the delay of 1942 days in filing the second appeal in the High Court was rightly not condoned by the High Court for the reasons mentioned below:

    11.1. First, the delay was inordinate;

    11.2. Second it was not properly explained; and

    11.3. Third, the ground alleged in support of application filed under Section 5 of the Limitation Act did not constitute a sufficient cause.

    12. The appellant HUDA is a statutory authority created under the Haryana Urban Development Authority Act, 1977. It has its well-established Legal Department to look after the legal cases filed by HUDA and against HUDA in various courts. They have a panel of lawyers to defend their interest in courts. It is not in dispute that the appellants had been contesting the civil suit and the first appeal since inception. The appellants were, therefore, fully aware of the adverse orders passed in the first appeal against them. There was, therefore, no justification on their part to keep quiet for such a long time and not to file the appeal within 90 days or/and re-file it immediately after curing the defects. If, according to the appellant HUDA, their lawyer did not take timely steps, which resulted in causing delay in its filing/refiling, then, in our view, it cannot be regarded as a sufficient cause within the meaning of Section 5 of the Limitation Act.

    13. In our view, it was equally the duty of the appellants (their legal managers) to see that the appeal be filed in time. If the appellants noticed that their lawyer was not taking interest in attending to the brief in question, then they should have immediately engaged some other lawyer to ensure that the appeal be filed in time by another lawyer.

    14. In our view, it is a clear case where the appellant HUDA i.e. their officers, who were in charge of the legal cell failed to discharge their duty assigned to them promptly and with due diligence despite availability of all facilities and infrastructure. In such circumstances, the officers in charge of the case should be made answerable for the lapse on their part and make good the loss suffered by the appellant HUDA.

    15. A delay of 1942 days (4 years 6 months), in our view, is wholly inordinate and the cause pleaded for its condonation is equally unexplained by the appellants. In any case, the Explanation given does not constitute a sufficient cause within the meaning of Section 5 of the Limitation Act. It was, therefore, rightly not condoned by the High Court and we concur with the finding of the High Court.

    16. The appeals, thus, fail and are accordingly dismissed.