Aniruddha Bose, J.:— The petitioner in this proceeding questions the legality of the process for making provisional assessment in relation to allegations of theft of electricity by the petitioner.
Referring to the provisions of sub-Sections (5) and (6) of Section 154 of the Electricity Act, 2003, Mr. Sanyal has argued that the recovery ought to have been effected by making appropriate application before the special Court. In this regard he has relied on a judgement of the Supreme Court in the case of Executive Engineer, Southern Electricity Supply Company of Orissa Ltd. (Southco v. Seetaram Rice Mill reported in (2012) 2 SCC 108.
On being prima facie satisfied with the case of the petitioner that the recovery proceeding in this case ought not to have been made through the provisions specified in Section 126 of the Electricity Act, 2003 but in terms of sub-Section (5) and (6) of Section 154 of the said Act, I restrain the Assessing Officer from proceeding further against the petitioner in this matter, on condition that the petitioner shall deposit a sum of Rs. 1,20,000/-. The supply line of the petitioner shall remain undisturbed upon payment of the aforesaid sum provided the petitioner continues pay the running bills on month by month basis. The deposit of Rs. 1,20,000/- shall be made by 23 May, 2014. It is also made clear that such payment shall be made without prejudice to the rights and contentions of the parties.
Let affidavit-in-opposition be filed by 13 June, 2014; Reply thereto, if any, be filed by 20 June, 2014.
Let this matter appear in the list on 26 June, 2014 under the heading “Specially Fixed For Orders”.
I make it clear that however pendency of this proceeding shall not prevent the distribution company from approaching the Special Court in terms of the provisions.