Mr. Pratap Venugopal, appearing for the appellant, submits that the principal ground raised in the appeal is denial of principles of natural justice in as much as the appellant was not afforded opportunity of being heard before the impugned order was passed.
2. It is submitted by Mr. Venugopal that the impugned order was passed in the matter of the draft PPA of existing Hydel Station between the Karnataka Power Transmission Corporation Limited(KPTCL) and the appellant. Before approval of the PPA, the Karnataka Electricity Regulatory Commission (Commission for short) issued advertisement in the English and Kannad dailies. No objection was received by the Commission. It is contended by the appellant that the impugned order dated 10/04/2003 was passed without affording to the appellant any opportunity to put-forth its views/clarifications on the modifications intended by the Commission.
3. Mr. Anand K. Ganesan, advocate representing the respondent Karnataka Power Transmission Commission Limited(KPTCL) does not have any objection to the prayer. The Commission represented by Mr. S. Balaji is prepared to take the directions as per the prayer made today. No other respondent has put in appearance.
4. Having heard parties counsel, we think it will be appropriate for the Commission to re-determine the issue of approval of the PPA after affording to the appellant an opportunity to present its views and submissions to the Commission.
5. Accordingly, we allow the appeal and set-aside the impugned order and direct the Karnataka Electricity Regulatory Commission (KERC) to pass a fresh order within two months hereof on the PPA between the appellant and the respondent no. 2(KPTCL) after affording an opportunity to the appellant to make its submission/clarifications in respect of the PPA.