In this petition, the petitioner, Power Grid Corporation of India Ltd has sought approval for tariff in respect of 400/220 kV 315 MVA Transformer at Jeypore in Eastern Region for the period 1.10.2002 to 31.3.2004 based on terms and conditions of tariff contained in the Commission's notification dated 26.3.2001, (hereinafter referred to as “the notification dated 26.3.2001”).
2. The petitioner was entrusted with the implementation of 400/220 kV 315 MVA Transformer at Jeypore in Eastern Region. The administrative approval and expenditure sanction was initially accorded by the Central Government in Ministry of Power vide its letter dated 2.11.1999 at an estimated cost of Rs. 876.00 lakh, including IDC of Rs. 79.00 lakh, based on 3rd quarter 1998 price level. As per the investment approval, the project was to be commissioned within 24 months from that date. The actual date of commercial operation of the transmission assets is 1.10.2002
3. Based on the above-noted facts, the petitioner has sought approval for transmission charges for the period from 1.10.2002 to 31.3.2004 as under on the total cost of Rs. 757.31 lakh:
(Rs. in lakh)
Transmission Tariff
2002-2003
2003-2004
Interest on Loan
27.80
53.97
Interest on Working Capital
1.42
3.01
Depreciation
13.55
28.40
Advance against Depreciation
0.00
0.48
Return on Equity
7.41
20.63
O & M Expenses
18.07
38.31
Total
68.24
144.80
4. In addition, the petitioner has prayed for approval of other charges like Foreign Exchange Rate Variation, Income Tax, incentive, Development Surcharge, late payment surcharge, other statutory taxes, levies, cess, filing fee, etc in terms of the notification dated 26.3.2001
5. The petitioner has claimed interest on working capital as per the details given below:
(Rs. in lakh)
2002-2003
2003-2004
Maintenance Spares
0.00
0.00
O & M expenses
3.01
3.19
Receivables
22.75
24.13
Total
25.76
27.33
Rate of Interest
11.00%
11.00%
Interest (Annual)
2.83
3.01
Interest (Pro rata)
1.42
CAPITAL COST
6. As laid down in the notification dated 26.3.2001, the project cost as approved by CEA or an appropriate independent agency, other than Board of Directors of the generating company, as the case may be, shall be the basis for computation of tariff.
7. As noted above, the original investment approval for the 315 MVA Transformer at Jeypore in Eastern Region was accorded by the Central Govt. in Ministry of Power vide letter dated 2.11.1999 at an estimated cost of Rs. 876.00 lakh at 3rd quarter 1998 price level. As per the auditor's certificate furnished by the petitioner on 20.9.2004, the estimated completion cost of the project is Rs. 757.31 lakh. Based on the audited expenditure details submitted by the petitioner, the gross block, including IDC of Rs. 53.65 lakh (indicated in the Auditor's certificate), is worked out as under:
Expenditure up to the date of commercial operation (30.9.2002)
:
Rs. 747.73 lakh
Gross block on the date of commercial operation
:
Rs. 747.73 lakh
Expenditure from DOCO to 31.3.2003
:
Rs. 9.58 lakh
Gross block as on 31.3.2003
:
Rs. 757.31 lakh
Total Estimated completion cost
:
Rs. 757.31 lakh
(The above includes initial spares for Rs. 46.72 lakh)
8. As on 1.10.2002, the date of commercial operation, the petitioner has incurred a total expenditure of Rs. 747.73 lakh. The additional expenditure of Rs. 9.58 lakh incurred during the tariff period is less than 20% of the approved project cost it is not being considered for the purpose of tariff.
9. In view of the above, the tariff is being computed based on the gross block of Rs. 747.73 lakh as on the date of commercial operation as claimed by the petitioner.
SOURCES OF FINANCING. DEBT - EQUITY RATIO
10. As per Para 4.3 of the notification dated 26.3.2001, capital expenditure of the transmission system shall be financed as per approved financial package set out in the techno-economic clearance of CEA or as approved by an appropriate independent agency, as the case may be. Debt-equity ratio or financial package for the asset covered in the present petition are not given separately. The petitioner has claimed tariff by taking debt and equity in the ratio of 88.25:11.75 Since the debt-equity ratio claimed by the petitioner is favourable to the respondents, the same has been considered for determination of tariff in the present petition. Based on this ratio, a total loan of Rs. 659.88 lakh and equity of Rs. 87.85 lakh, as on the date of commercial operation are being considered.
INTEREST ON LOAN
11. As provided in the notification dated 26.3.2001, interest on loan capital is to be computed on the outstanding loans, duly taking into account the schedule of repayment, as per financial package approved by CEA or any independent agency. In keeping with this provision, while calculating Interest on loan, closing balance of the notional loan as on 31.3.2001 has been taken as opening balance of the loan as on 1.4.2001
12. The interest on loan has been worked out by considering the gross amount of loan, repayments for the years 2002-2003 and 2003-2004 and rates of interest as per the loan details submitted by the petitioner under affidavit dated 16.2.2005
13. The details of calculation of interest on loan are as given below:
Calculation of Interest on Loan
(Rs. in lakh)
Details of Loan
2002-2003
2003-2004
No. of days in the Year
365
366
ADB-I (Foreign Currency Loan)
Gross Loan -Opening
548.88
548.88
Cumulative Repayment up to Previous period
10.27
14.01
Net Loan-Opening
538.62
534.87
Repayment during the year-1st June
0.00
3.94
538.62
530.93
Repayment during the year-1 December
3.75
4.14
Net Loan-Closing
534.87
526.79
Rate of Interest
7.89%
7.89%
Interest
21.09
41.83
Repayment Schedule
Half Yearly Instalments-1.6.2001, 1.12.2001, 1.6.2002, 1.12.2002, 1.6.2003 & 1.12.2003
Bond-IX
Gross Loan -Opening
65.00
65.00
Cumulative Repayment up to Previous Year
0.00
0.00
Net Loan-Opening
65.00
65.00
Repayment during the year
0.00
6.50
Net Loan-Closing
65.00
58.50
Rate of Interest
12.25%
12.25%
Interest
3.97
7.48
Repayment Schedule
10 Annual Instalments from 22.8.2003
Bond-X
Gross Loan -Opening
46.00
46.00
Cumulative Repayment up to Previous Year
0.00
0.00
Net Loan-Opening
46.00
46.00
Repayment during the year
0.00
0.00
Net Loan-Closing
46.00
46.00
Rate of Interest
10.90%
10.90%
Interest
2.50
5.01
Repayment Schedule
12 Annual Instalments from 21.6.2004
Total Loan
Gross Loan -Opening
659.88
659.88
Cumulative Repayment up to Previous Year
10.27
14.01
Net Loan-Opening
649.62
645.87
Repayment during the year
3.75
14.58
Net Loan-Closing
645.87
631.29
Interest
27.56
54.32
14. The petitioner has submitted loan details for the assets commissioned after 31.3.2002 vide affidavit dated 16.2.2005 In the calculations, the interest on loan has been worked by considering the gross amount of loan, repayment for the year 200203 to 2003-2004 and rate of interest etc. as worked out from the loan details for the assets commissioned after 31.3.2002 as submitted by the petitioner. It is noted that in case of ADB-I loan as per affidavit dated 16.2.2005, gross allocated amount is 11.28 lakh US while as per petition the same is shown as outstanding at the beginning of 2002-2003. As repayment of ADB-I loan commences from 1.6.2001 while the date of commercial operation of the transmission asset covered under this petition is 1.10.2002, allocated instalments of ADB-I loan before the date of commercial operation have been adjusted by considering gross allocated amount as per loan reconciliation statement for 2002-2003, for tariff calculations.
15. ADB-1 loan carries floating rates of interest. For the purpose of computation of interest on loan, the interest rates as submitted by the petitioner have been taken into consideration. In view of this, any changes/resetting of the interest rate of the above loans during the tariff period covered in this petition would be settled mutually between the parties and in case of their inability to do so, any one of them may approach the Commission for the appropriate decision.
DEPRECIATION
16. Based on the notification dated 26.3.2001, the petitioner is entitled to claim depreciation. The salient provisions for calculation of depreciation as per the notification dated 26.3.2001 are reproduced below:
(i) The value base for the purpose of depreciation shall be the historical cost of the asset.
(ii) Depreciation shall be calculated annually as per straight-line method at the rate of depreciation as prescribed in the Schedule attached to the notification dated 26.3.2001 dated 26.3.2001
Provided that the total depreciation during the life of the project shall not exceed 90% of the approved original cost. The approved original cost shall include additional capitalisation on account of foreign exchange rate variation also.
(iii) On repayment of entire loan, the remaining depreciable value shall be spread over the balance useful life of the asset.
(iv) Depreciation shall be chargeable from the first year of operation. In case of operation of the asset for part of the year, depreciation shall be charged on pro-rata basis.
(v) Depreciation against assets relating to environmental protection shall be allowed on case-to-case basis at the time of fixation of tariff subject to the condition that the environmental standards as prescribed have been complied with during the previous tariff period.
17. The petitioner has claimed the depreciation on the capital expenditure of Rs. 757.31 lakh in accordance with the above principles.
18. Based on the above, depreciation for individual items of capital expenditure has been calculated on the capital cost of Rs. 747.73 lakh as considered by us for the purpose of tariff at the rates as prescribed in the notification dated 26.3.2001 While approving depreciation component of tariff, the weighted average depreciation rate of 3.60% has been worked out. The calculations in support of weighted average rate of depreciation of 3.60% are appended hereinbelow:
(Rs. in lakh)
Capital Cost
Approved cost
Rate of Depreciation
Depreciation
Capital Expenditures as on 30.9.2002
Land
0.00
0%
0.00
Building & Other Civil Works
0.00
1.80%
0.00
Sub-Station Equipment
747.73
3.60%
26.92
Transmission Line
0.00
2.57%
0.00
PLCC
0.00
6.00%
0.00
Total
747.73
876.00
26.92
Weighted Average Rate of Depreciation
3.60%
19. Accordingly, depreciation has been allowed as calculated below:
(Rs. in lakh)
2002-2003
2003-2004
Rate of Depreciation
3.60%
Depreciable Value (90% of the Gross Block)
672.96
Balance Useful life of the asset
Remaining Depreciable Value
672.96
659.50
Depreciation
13.46
26.92
ADVANCE AGAINST DEPRECIATION
20. In addition to allowable depreciation, the petitioner becomes entitled to Advance Against Depreciation when originally scheduled loan repayment exceeds the depreciation allowable as per schedule to the notification. Advance Against Depreciation is computed in accordance with the following formula:
AAD = Originally scheduled loan repayment amount subject to a ceiling of 1/12th of original loan amount minus depreciation as per schedule.
21. The petitioner has claimed Advance Against Depreciation on the basis of
(i) 1/12th of gross loan worked out as per the gross block admitted by the Commission in the petition for previous tariff setting,
(ii) Repayment of loans during the year and in case of foreign currency loan multiplying the repayment with exchange rate as on 31.3.2001 and depreciation on FERV as repayment during the year in the case of notional loan, and
(iii) depreciation as claimed in the petition.
22. The entitlement of the petitioner has been considered in accordance with the notification dated 26.3.2001 In the calculation, Advance Against Depreciation has been worked out on the basis of gross loan and repayment and depreciation as worked out above. The petitioner's entitlement to Advance Against Depreciation has been calculated as shown below:
(Rs. in lakh)
Advance Against Depreciation
2002-2003
2003-2004
1/12th of Gross Loan(s)
54.99
54.99
Scheduled Repayment of the Loan(s)
3.75
14.58
Minimum of the above
3.75
14.58
Depreciation during the year
13.46
26.92
Advance Against Depreciation
0.00
0.00
OPERATION & MAINTENANCE EXPENSES
23. In accordance with the notification, Operation and Maintenance expenses, including expenses on insurance, if any, are to be calculated as under:
i) Where O&M expenses, excluding abnormal O&M expenses, if any, on sub-station (OMS) and line (OML) are separately available for each region, these shall be normalised by dividing them by number of bays and line length respectively. Where data as aforesaid is not available, O&M expenses in the region are to be apportioned to the sub-station and lines on the basis of 30:70 ratio and these are to be normalised as below:
O&M expenses per Unit of the line length in Kms (OMLL) = Expenses for lines (OML)/Average line length in Kms (LL)
O&M expenses for sub-stations (OMBN) = O&M expenses for substations (OMB)/Average number of bays (BN)]
ii) The five years average of the normalised O&M expenses for lines and for bays for the period 1995-1996 to 1999-2000 is to be escalated at 10% per annum for two years (1998-1999 and 1999-2000) to arrive at normative O&M expenses per unit of line length and per bay for 1999-2000.
iii) The normative O&M per unit length and normative O&M per bay for the year 1999-2000 for the region derived in the preceding paragraph is to be escalated @ 6% per annum to obtain normative values of O&M expenses per unit per line length and per bay in the relevant year. These normative values are to be multiplied by line length and number of bays (as the case may be) in a given system in that year to compute permissible O&M expenses for the system.
iv) The escalation factor of 6% per annum is to be used to revise normative base figure of O&M expenses. Any deviation of the escalation factor computed from the actual inflation data that lies within 20% of the notified escalation factor of 6% shall be absorbed by utilities/beneficiaries.
24. The different elements of Operation & Maintenance expenses have been considered in the succeeding paragraphs in the light of provisions of the notification dated 26.3.2001 based on the data available since 1995-1996.
Employee Cost
25. The petitioner has, inter alia, claimed incentive and ex gratia as a part of employee cost. The petitioner was asked to specify the amount of minimum statutory bonus paid to its employees under the Payment of Bonus Act. The petitioner vide its affidavit dated 6.2.2003 has stated that the incentive paid to employees does not include minimum statutory bonus. The petitioner has further stated that the ex gratia was being paid in lieu of bonus, as is customary and a normal practice followed in private and public sectors. The petitioner has also furnished a write-up on Incentive scheme in support of the claim. It has been clarified on behalf of the petitioner that even the top management of the petitioner company is paid incentive and ex gratia included as a part of employee cost in O&M expenses claimed. The payment of incentive other than the statutory minimum bonus is at the discretion of the petitioner company and should be borne out of its profits or incentive earned from the respondents for higher availability of the Transmission System. In view of the above, the incentive and ex gratia payments made by the petitioner to its employees have been kept out of consideration for calculation of employee cost.
26. The petitioner was directed to furnish details of the arrears on account of pay and allowances for the period prior to 1995-1996, but paid between 1995-1996 to 19992000. The petitioner has submitted the details of such arrears, amounting to Rs. 48.21 lakh and Rs. 53.17 lakh paid for Eastern Region during 1995-1996 and 1996-1997. Similarly, the arrears for the previous years included in the employee cost for 1995-1996 and 1996-1997 for Corporate Office were stated to be Rs. 9.61 lakh and Rs. 35.60 lakh. The petitioner has also submitted that the arrears on account of pay revision from 01.01.97 to 31.03.2000 have been paid during the years 2000-01 and 2001-2002 also. The amounts of these arrears as claimed by the petitioner are Rs. 159.26 lakh and Rs. (-) Rs. 4.39 lakh for Eastern Region and Rs. 297.13 lakh and Rs. 109.95 lakh for the Corporate Office for the years 2000-01 and 2001-2002 respectively. The petitioner has prayed that the arrears on account of pay and allowances for the period prior to 19951396 should be deducted while those pertaining to the period from 1995-1996 to 19992000 but paid subsequent to 1999-2000 should be added to O&M charges. The petitioner has argued that since these pay arrears pertain to the period being considered for fixation of normative O&M, the arrears should be considered while fixing the normative O&M. We find the submission of the petitioner to be logical and have considered the submission in the calculation of employee cost.
Repair & Maintenance Expenses
27. WBSEB has stated that the petitioner has not furnished sufficient explanation for about 81% increase in repair and maintenance expenses during 1997-1998 over those of 1996-1997. It is noted that the petitioner has explained that this variation is due to major repair in Kahalgaon-Biharshariff line due to collapse of tower. Major repair is not a regular phenomenon, and hence expenses on this account have to be excluded from the process of normalisation. Therefore, “repair and maintenance” expenses in 1998-1999 have been limited to Rs. 399.68 lakh (20% over and above the “repair and maintenance” expenses for the year 1996-1997). However, if any major repairs are undertaken during the tariff period covered by this order, the petitioner may approach the Commission with proper justification to claim the actual expenses as a part of O&M expenses.
Power Charges
28. In case of Corporate Office, the power charges as claimed by the petitioner have been considered in the calculation of O&M expenses. In case of Eastern Regional Transmission System (ERTS) the petitioner was directed to submit break up of power charges between substation facilities and the residential colonies. The petitioner in its affidavits filed in these proceedings has submitted the break up. Since, power charges for residential quarters in the colony are recoverable from the employees, such charges amounting to Rs. 13.96 lakh, Rs. 15.19 lakh, Rs. 22.4 lakh, Rs. 48.77 lakh and Rs. 32.47 lakh for the five years from 1995-1996 to 1999-2000 have been deducted from the total power charges claimed by the petitioner for the purpose of normalisation.
Insurance
29. It has been noted that the petitioner has a policy of self-insurance for which it has created the insurance reserve. The insurance charges claimed by the petitioner are credited to the insurance reserve. The petitioner was directed to furnish the management policy on creation of insurance reserve, items of loss secured and the conditions thereto. The petitioner has submitted insurance policy of the petitioner company under affidavit dated 6.2.2003 The key features of the policy submitted by the petitioner are as under:
(a) Insurance reserve is created @ 0.1% on gross value of fixed assets at the close of the year, to meet the future losses arising from uninsured risks, except machinery breakdown for valve hall of HVDC, and fire risk of HVDC equipment and SVC sub-stations.
(b) The policy generally covers following:
(i) Fire, lightning, explosion/implosion, and bush fire
(ii) Natural calamity: flood, earthquake, storm, cyclone, typhoon, tempest, hurricane, tornado, subsidence and landslide
(iii) Riot, strike/ malicious and terrorist damage
(iv) Theft, burglary, Missile testing equipment, impact damage due to rail/ road or animal, aircraft and articles dropped there from.
(c) The losses of assets caused by the above causes are adjusted against insurance reserve as per the corporation guidelines.
(d) The amount so set aside in the insurance reserve has not been separately claimed from the respondents and the expenses have been met from the permitted O&M charges under the tariff.
30. The petitioner has stated that the policy of self-insurance has also been followed by NHPC, where 0.5% per annum of the gross block of O&M projects is transferred to self-insurance reserve account. It has also been informed that the rate of 0.1% as booked under O&M expenses towards self-insurance reserve is lower than the insurance premium (0.22%) being charged by the insurance companies for the risks covered in the self-insurance policy. In support of this claim, the petitioner has placed on record a letter from Reliance General Insurance Company quoting for the insurance rate of the assets covered in the self-insurance policy of the petitioner company.
31. In view of the explanation furnished on behalf of the petitioner, the insurance charges as claimed have been considered in O&M expenses. We, however, make it explicit that the self-insurance provided by the petitioner is for replacement of the damaged assets and the beneficiaries shall not be charged anything in case of damage due to any of the events mentioned in the insurance policy.
32. In case of Training & Recruitment expenses, Communication expenses, Traveling, Rent, and Miscellaneous Expenses as claimed by the petitioner have been considered for calculation, both in the case of the ERTS as well as Corporate Office.
Other Expenses
33. In case of ERTS, the petitioner has stated that the provisions are made for the losses and shortage of store materials and for the doubtful advances paid to contractors. Since all these items are controllable by the petitioner and reflect the managerial efficiency of the petitioner, the provisions made in case of ERTS on this account have not been considered as admissible for reimbursement. In case of Corporate Office, the following expenses have not been admitted for reimbursement:
(a) Donation of Rs. 0.05 lakh, Rs. 30 lakh, Rs. 34.78 lakh and Rs. 600.03 lakh for the years 1995-1996, 1996-1997, 1898-1999 and 1999-2000, as these donations are not related to transmission business. The expenditure on account of the donations need be borne by the petitioner out of other profits of the corporation.
(b) Provisions of Rs. 1107.61 lakh, Rs. 385.8 lakh and Rs. 0.27 lakh for the year 1996-1997, 1997-1998 and 1999-2000. These provisions were made for the loss of stores in Eastern Region and North Eastern Region, for bad and doubtful debt in Northern Region and for shortage of store in North Eastern Region. The petitioner has stated that provision of loss of store in Eastern Region (Rs. 863.16 lakh in 1996-1997) and provision of bad and doubtful debt in Northern Region (Rs. 385.80 lakh in 1997-1998) were written back during subsequent years in the regional books of account. In view of this, the petitioner has submitted that these expenses need not be considered while fixing the O&M of the respective regions. As all these items are controllable by the petitioner and reflect the managerial efficiency. However, an amount of Rs. 11.14 lakh on account of fire at the corporate office in 1998-1999 has been considered as admissible under the head provisions.
(c) Legal expenses amounting to Rs. 2.65 lakh in the Corporate Office on legal opinion on CERC matters have not been allowed in line with the Commission's policy of allowing only the fees for the petitions filed in the Commission. However, other legal expenses for disputes related to compensation, contracts, service matters and labour cases have been admitted.
Recoveries
34. The details of the recoveries for the ERTS and the Corporate Office were furnished by the petitioner vide affidavit dated 6th February 2003. The petitioner in the aforesaid affidavit also furnished the “complete details” of the recoveries for the ERTS. According to the petitioner, the income from sale of bid documents has already been adjusted for under the sub-head Tender Expenses under the head Other Expenses. Hence, income under this sub-head has not been considered in the recovery for the ERTS as well as Corporate Office. Similarly, electricity charges recovered/recoverable from employees residential buildings and other residential buildings have not been considered under the head “recovery” as the power charges for colony consumption have been deducted in case of the ERTS.
Allocation of Corporate Office Expenses to Various Regions
35. The petitioner has submitted the method for allocation of Corporate Office expenses to various Regions. The key steps in the apportionment of Corporate Office expenses among the regions are as under:
i) Expenses booked under Training & Recruitment, Directors sitting fees, provisions, R&D, Write off of fixed assets/ non-operating expenses and donations are considered exclusively as O&M expenses.
ii) After deducting these exclusive O&M expenses, the balance Corporate Office expenses are allocated in the ratio of Transmission charges to annual Capital outlay to obtain expenses allocated to O&M and construction activity.
iii) The allocation to O&M activity obtained in step (ii) is added to exclusive O&M expenses obtained in step (i) to arrive at total O&M expenses in the Corporate Office.
iv) RLDC expenses are then deducted from the total O&M expenses obtained in step (iii) to arrive at O&M expenses allocated to transmission business.
v) O&M expenses allocated to transmission business are then allocated to various regions in the ratio of their respective transmission charges.
36. The methodology adopted by the petitioner for allocation of Corporate Office O&M expenses has been approved and followed in the calculation of O&M expenses. The comparative statement of O&M expenses claimed by the petitioner and those allowed and considered for the years 1995-1996 to 19992000 for the purpose of computation of O&M expenses for the tariff period are given herein below:
DETAILS OF O&M EXPENSES FOR POWERGRID SYSTEM IN EASTERN REGION
(All Figures in Rs. in lakh)
1995-1996
1996-1997
1997-1998
1998-1999
1999-2000
Items
As per Petitioner
As allowed for
As per Petitioner
As allowed for
As per Petitioner
As allowed for
As per Petitioner
As allowed for
As per Petitioner
As allowed for
Employee Cost
1003.20
843.52
1236.89
1108.76
1672.90
1600.67
1970.16
1907.01
2551.38
2167.94
Repair & Maintenance
263.18
263.18
333.07
333.07
602.04
399.68
407.97
407.97
533.34
533.34
Power Charges
302.04
288.08
367.49
352.30
400.30
377.90
378.85
330.08
407.02
374.55
Training & Recruitment
15.17
15.17
9.14
9.14
5.12
5.12
18.25
18.25
2.32
2.32
Communications
106.71
106.71
99.94
99.94
113.20
113.20
112.85
112.85
86.81
86.81
Travelling
193.08
193.08
191.47
191.47
228.42
228.42
236.18
236.18
270.55
270.55
Printing & Stationery
15.82
15.82
15.84
15.84
18.06
18.06
20.69
20.69
16.00
16.00
Rent
14.06
14.06
13.64
13.64
16.16
16.16
16.33
16.33
15.76
15.76
Miscellaneous Expenses
210.50
210.50
269.26
269.26
283.90
283.90
375.72
375.72
533.27
533.27
Insurance
6.78
6.78
7.99
7.99
98.26
98.26
102.58
102.58
104.55
104.55
others
76.41
71.51
64.24
60.17
176.36
120.52
493.99
395.28
75.44
75.44
Corporate Expenses Allocation
536.01
524.66
414.68
204.09
391.89
338.04
349.15
348.38
402.73
325.67
TOTAL
2742.96
2553.07
3023.65
2665.67
4006.61
3599.94
4482.72
4271.32
4999.17
4506.20
Less: Recoveries
23.78
64.49
13.18
10.01
15.64
Net O&M Expenses
2742.96
2529.29
3023.65
2601.18
4006.61
3586.76
4482.72
4261.31
4999.17
4490.56
NOTE: Only charges for power consumption at sub-stations has been considered admissible
Method of Normalizing O&M Expenses
37. The following formulae for calculation of normative O&M expenses as per the notification, as amended vide Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (Second Amendment) Regulations, 2003 published in the Gazette of India on 2.6.2003 have been followed
Where:
AVOMLL and AVOMBN are average normalized O&M expenses per Ckt. km of line length and per bay respectively.
OMLi and OMSi are O&M expenses for the lines and for the substations for the i year respectively.
LLi and BNi are the total line length in Ckt. km and total number of bays in the ith year respectively.
38. In the process of normalisation, abnormal expenses such as expenses on account of additional security have to be deducted as per the notification, for which the petitioner may file separate petition. Accordingly, the amount of Rs. 23.33 lakh, Rs. 0.68 lakh, Rs. 24.78 lakh and Rs. 143.56 lakh spent on CISF security at Salakati Substation of the Chukha Transmission System for the years 1996-1997 to 1999-200 has been deducted from the total O&M expenses for the region.
39. As per the above method, AVOMLL and AVOMBN are calculated based on the data for the years 1995-1996 to 1999-2000. These normalised averages correspond to the year 1997-1998. After escalating these averages by 10% per annum for two years, the normative O&M expenses for the base year 1999-2000 have been obtained. Normative O&M expenses for subsequent years are obtained by escalating these normative figures by 6% per annum. Following table gives comparison of the normative O&M expenses as calculated by the petitioner and as per our calculations allowed for the base year i.e 1999-2000 and afterwards:
NORMALIZED O&M EXPENSES FOR EASTERN REGION
(All Figures in Rs. in lakh)
S. No.
Items
1995-1996
1996-1997
1997-1998
1998-1999
1999-2000
Total for five years 95-96 to 99-00
99-00
2000-2001
2001-2002
2002-2003
2003-2004
1
Total O&M expenses(Rs. Lakhs)
2529.29
2601.18
3586.76
4261.31
4490.56
2
Abnormal O&M expenses
0.00
23.33
0.68
24.78
143.56
192.35
3
Normal O&M expenses (S. NO. 1 -S. NO. 2)
2529.29
2577.85
3586.08
4236.53
4347.00
4
OML (O&M for lines) = 0.7 × S. No. 3
1770.50
1804.49
2510.25
2965.57
3042.90
12093.71
5
OMS (O&M for substation) = 0.3×S. NO. 3
758.79
773.35
1075.82
1270.96
1304.10
5183.02
6
Line length at beginning of the year in Kms.
4418.70
4418.70
4418.70
4482.70
4665.70
7
Line length added in the year in Kms.
0.00
0.00
64.00
183.00
86.00
8
Line length at end of the year in Kms.
4418.70
4418.70
4482.70
4665.70
4751.70
9
LL (Average line length in the Region)
4418.70
4418.70
4450.70
4574.20
4708.70
22571.00
10
NO. of bays at beginning of the year
76
88
88
90
92
11
NO. of bays added in the year
12
0
2
2
1
12
NO. of bays at the end of the year
88
88
90
92
93
13
BN (Average number of bays in the Region)
82.0
88.0
89.0
91.0
92.5
442.50
14
AVOMLL(OML/LL)
0.40
0.41
0.56
0.65
0.65
2.668
15
AVOMBN(OMS/BN)
9.25
8.79
12.09
13.97
14.10
58.194
16
NOMLL(allowable O&M per unit of line length)
0.5335
0.5869
0.6456
0.6456
0.6843
0.7254
0.7689
0.8150
17
NOMBN(Allowable O&M per bay)
11.6389
12.8028
14.0831
14.0831
14.9280
15.8237
16.7731
17.7795
18
NOMLL(as calculated by petitioner)
0.6000
0.7300
0.7700
0.8200
0.8700
0.9200
19
NOMBN(as calculated by petitioner)
13.0500
15.7900
16.7400
17.7400
18.8000
19.9300
40. The differences in NOMLL and NOMBN as calculated by the petitioner and as allowed are mainly on account of certain expenses disallowed by us as explained in preceding paragraphs. Using these normative values, O&M charges have been calculated.
41. In our calculations the escalation factor of 6% per annum has been used. In accordance with the notification, if the escalation factor computed from the observed data lies in the range of 4.8% to 7.2%, this variation shall be absorbed by the petitioner. In case of deviation beyond this limit, adjustment shall be made on by applying actual escalation factor arrived at on the basis of weighted price index of CPI for industrial workers (CPMW) and index of selected component of WPI (WPI_TR).
42. The petitioner has claimed O&M expenses for 2 bays, which have been considered for calculation of O&M expenses.
43. O&M expenses allowed are given hereunder:
2002-2003 (Pro rata)
2003-2004
Line length in ckm
No. of bays
O&M expenses (Rs. in lakh)
Line length in ckm
No. of bays
O&M expenses (Rs. in lakh)
0
2
16.77
0
2
35.56
RETURN ON EQUITY
44. In accordance with the notification, the petitioner is entitled to return on equity at the rate of 16% per annum. For the purpose of tariff equity of Rs. 87.85 lakh has been considered. On the above basis, the petitioner shall be entitled to return on equity of Rs. 7.03 lakh during 2002-2003 (part of the year) and Rs. 14.06 lakh during 2003-2004.
INTEREST ON WORKING CAPITAL
45. As provided in the notification, the interest on working capital shall cover:
(a) Operation and maintenance expenses (cash) for one month;
(b) Maintenance spares at a normative rate of 1% of the capital cost less 1/5th of the initial capitalised spares. Cost of maintenance spares for each subsequent year shall be revised at the rate applicable for revision of expenditure on O & M of the transmission system; and
(c) Receivables equivalent to two months' average billing calculated on normative availability level, which is 98%.
46. In keeping with the above methodology, working capital has been worked out, on the basis of capital expenditure as on the date of commercial operation. The value of maintenance spares has been escalated @ 6% per annum for the years 2002-2003 and 2003-2004. Deduction of 1/5th of the initial capitalised spares has been considered in the calculations. As it results in negative quantity, spares have been considered ‘nil’ for calculation of interest on working capital. The petitioner has claimed interest on working capital at the rate of 11%, based on annual SBI PLR for the year 2002-2003, and the same has been allowed. The detailed calculations in support of interest on Working Capital are as under:
Interest on Working Capital
(Rs. in lakh)
2002-2003
2003-2004
Rate of Escalation for maintenance spares
6%
6%
Maintenance Spares
1%
7.48
Less Capitalised Initial Spares
9.34
0.00
0.00
O & M expenses
2.80
2.96
Receivables
22.06
22.27
Total
24.86
25.24
Rate of Interest
11.00%
11.00%
Interest
37.1
2.78
TRANSMISSION CHARGES
47. In the light of above discussion, we approve the transmission charges as given in the Table below:
(Rs. in lakh)
Transmission Tariff
2002-2003
2003-2004
Interest on Loan
27.56
54.32
Interest on Working Capital
1.37
2.78
Depreciation
13.46
26.92
Advance against Depreciation
0.00
0.00
Return on Equity
7.03
14.06
O & M Expenses
16.77
35.56
Total
66.19
133.64
48. In addition to the transmission charges, the petitioner shall be entitled to other charges like income-tax, incentive, surcharge and other cess and taxes in accordance with the notification dated 26.3.2001 subject to directions if any, of the superior courts. The petitioner shall also be entitled to recovery of filing fee of Rs. 2 lakh, which shall be recovered from the respondents in five monthly installments of Rupees forty thousand each and shall be shared by the respondents in the same ratio as other transmission charges.
49. The petitioner is already billing the respondents on provisional basis in accordance with the Commission's interim order. The provisional billing of tariff shall be adjusted in the light of final tariff now approved by us.
50. The transmission charges approved by us shall be included in the regional transmission tariff for Eastern Region and shall be shared by the regional beneficiaries in accordance with the notification dated 26.3.2001
51. This order disposes of Petition No. 139/2002.