K. Kannan, J (oral).
1. All the appeals are connected and are disposed of by a common order.
2. The appeals are at the instance of the State challenging the award of compensation determined by the Reference Court on a reference under Section 18 of the Land Acquisition Act. The Collector had determined the compensation at Rs. 4,50,000/- per acre for chahi land and relatively less amount for different categories of land. The compensation was with reference to an acquisition of 16 kanals 6 marlas of land for setting up Khalsa Heritage Museum in Village Mataur through a notification under Section 4 on 22.12.1999 In the manner of determination of the compensation the Reference Court has followed a judgment rendered by this Court in RFA No. 4176 of 2012 where for the same purpose of acquisition brought through a notification made one year earlier, the High Court had fixed a compensation fo Rs. 33,750 per marla. Since the instant notification was for a period more than one year, the Reference Court added 10% of the value as determined already and provided for a compensation of Rs. 37,125/- per marla.
3. Learned counsel appearing on behalf of the State challenges the determination on: i) the compensation assessed is several times more than the compensation assessed by the Collector already. ii) There had been a delay for 152 days in making the reference. iii) There was no basis given for escalation of 10%.
2. I do not find any of the objections would merit acceptance. The determination of compensation ought not to be merely seen as grossly high in relation to the compensation fixed by the Collector but it has to be assessed in the light of the objective materials brought before the Court. If the High Court had already rendered a judgment determining compensation in relation to property acquired for the same purpose one year earlier at Rs. 33,750/-, per marla it shall be surely made a guide for the Reference Court to follow and redetermine the compensation on that basis. The comparison must be only with reference to the determination made by the High Court itself and cannot be stated to be high by only making reference to the Collector's award. Even the percentage of increase that has been provided by the Reference Court cannot be said to be high, for, the Supreme Court has held in General Manager, Oil & Natural Gas Corporation Ltd. v. Ramesh Bhai Jivan Bhai Patel(2008) 14 SCC 745 that an escalation up to 10 to 15% could be provided, however, the time from the date of determination to an earlier case is not more than four years. In this case, the gestation was only a year and if the Reference court had provided for a 10% escalation, I will not find it to be erroneous.
4. Even an objection regarding delay in reference cannot merit acceptance, for, I do not find any discussion on the same by the Reference Court. If this were stated to be a fallability in the order, I will not find the delay of 152 days as extraordinary to knock out the case at the threshold without entering an adjudication on objective materials brought before the Court. There always existed a power to condone delay in making reference under Section 18 and I wold assume the discretion as having been exercised, although not specifically stated so in the order.
5. The awards passed by the Court below are maintained and all the appeals by the State are dismissed.