Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Judges
Acts
  • Section 24(2)
  • The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
  • Section 31 of the 1894 Act
  • Sections 32 and 33
  • Section 31(2) of the 1894 Act
  • Section 24 of the 2013 Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Judges
Acts
  • Section 24(2)
  • The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
  • Section 31 of the 1894 Act
  • Sections 32 and 33
  • Section 31(2) of the 1894 Act
  • Section 24 of the 2013 Act
Smart Summary

Factual and Procedural Background

An award under the Land Acquisition Act, 1894 was passed on 18-11-1995 in respect of the appellants’ land. However, until 31-01-2014 neither was the compensation paid or deposited in court nor was it received by the appellants, who also retained physical possession of the land. After the enactment of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“the 2013 Act”) on 01-01-2014, the appellants approached the court contending that the acquisition had lapsed under Section 24(2). The present civil appeals were heard after leave was granted.

Legal Issues Presented

  1. Whether, in view of Section 24(2) of the 2013 Act, land acquisition proceedings initiated under the 1894 Act lapse when (a) compensation has neither been paid nor deposited and (b) physical possession remains with the landowner for five years or more before 01-01-2014.

Arguments of the Parties

Appellants' Arguments

  • Because no compensation had been paid or deposited and they remained in possession, Section 24(2) of the 2013 Act rendered the acquisition proceedings void.

Respondents' Position

The respondents did not contest the appellants’ reliance on Section 24(2).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Pune Municipal Corporation v. Harakchand Misirimal Solanki (2014) 3 SCC 183 Interprets Section 24 of the 2013 Act; clarifies that acquisition lapses if compensation has not been “paid,” meaning neither offered nor deposited as required. The Court adopted this construction to conclude that, because no compensation had been deposited or received and possession remained with the appellants, the acquisition had lapsed.

Court's Reasoning and Analysis

The Court revisited Section 24 of the 2013 Act, noting its overriding effect through the non-obstante clause. Citing Pune Municipal Corporation, it reiterated that:

  • Where an award is five years or more old and either physical possession has not been taken or compensation has not been paid, the acquisition “shall be deemed to have lapsed” (Section 24(2)).
  • “Paid” requires deposition of compensation in court or actual payment to the landowner; mere tender or offer is insufficient.

Applying these principles, the Court observed:

  • The award dated 18-11-1995 was more than five years old on 01-01-2014.
  • No compensation had been paid or deposited at any time up to 31-01-2014.
  • Physical possession remained with the appellants.

Because both statutory contingencies were met, Section 24(2) mandated that the acquisition proceedings be deemed to have lapsed.

Holding and Implications

The civil appeals were allowed and the land acquisition declared lapsed.

Immediate effect: the appellants retain their land free from the impugned acquisition; no costs were awarded. The decision applies the Supreme Court’s earlier interpretation in Pune Municipal Corporation but does not establish a new legal principle beyond reaffirming that precedent.

    Bimla Devi And Others v. State Of Haryana And Others

    Order

    1. Leave granted. It is a common ground of the parties that the award was passed on 18-11-1995 and the compensation has not been paid nor deposited in the court nor received by the appellants till date i.e 31-1-2014 and even the physical possession of the land in question is with the appellants as on date.

    2. The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short “the 2013 Act”) came into effect on 1-1-2014. It is submitted by the appellants and not contested by the respondents that in view of Section 24 of the 2013 Act, the land acquisition proceedings have lapsed.

    3. In a recent decision of this Court in Pune Municipal Corpn. v. Harakchand Misirimal Solanki (2014) 3 SCC 183, a three-Judge Bench speaking through one of us (R.M Lodha, J.) considered the scope of Section 24, particularly the meaning of the expression “compensation has not been paid” in Section 24(2) of the 2013 Act and held as under:( & 17)

    “10. Insofar as sub-section (1) of Section 24 is concerned, it begins with non obstante clause. By this, Parliament has given overriding effect to this provision over all other provisions of the 2013 Act. It is provided in clause (a) that where the land acquisition proceedings have been initiated under the 1894 Act but no award under Section 11 is made, then the provisions of the 2013 Act shall apply relating to the determination of compensation. Clause (b) of Section 24(1) makes provision that where land acquisition proceedings have been initiated under the 1894 Act and award has been made under Section 11, then such proceedings shall continue under the provisions of the 1894 Act as if that Act has not been repealed.
    11. Section 24(2) also begins with non obstante clause. This provision has overriding effect over Section 24(1). Section 24(2) enacts that in relation to the land acquisition proceedings initiated under the 1894 Act, where an award has been made five years or more prior to the commencement of the 2013 Act and either of the two contingencies is satisfied viz. (i) physical possession of the land has not been taken, or (ii) the compensation has not been paid, such acquisition proceedings shall be deemed to have lapsed. On the lapse of such acquisition proceedings, if the appropriate Government still chooses to acquire the land which was the subject-matter of acquisition under the 1894 Act then it has to initiate the proceedings afresh under the 2013 Act. The proviso appended to Section 24(2) deals with a situation where in respect of the acquisition initiated under the 1894 Act an award has been made and compensation in respect of a majority of landholdings has not been deposited in the account of the beneficiaries then all the beneficiaries specified in Section 4 notification become entitled to compensation under the 2013 Act.
    ***
    17. While enacting Section 24(2), Parliament definitely had in its view Section 31 of the 1894 Act. From that one thing is clear that it did not intend to equate the word ‘paid’ to ‘offered’ or ‘tendered’. But at the same time, we do not think that by use of the word ‘paid’, Parliament intended receipt of compensation by the landowners/persons interested. In our view, it is not appropriate to give a literal construction to the expression ‘paid’ used in this sub-section [sub-section (2) of Section 24]. If a literal construction were to be given, then it would amount to ignoring procedure, mode and manner of deposit provided in Section 31(2) of the 1894 Act in the event of happening of any of the contingencies contemplated therein which may prevent the Collector from making actual payment of compensation. We are of the view, therefore, that for the purposes of Section 24(2), the compensation shall be regarded as ‘paid’ if the compensation has been offered to the person interested and such compensation has been deposited in the court where reference under Section 18 can be made on happening of any of the contingencies contemplated under Section 31(2) of the 1894 Act. In other words, the compensation may be said to have been ‘paid’ within the meaning of Section 24(2) when the Collector (or for that matter Land Acquisition Officer) has discharged his obligation and deposited the amount of compensation in court and made that amount available to the interested person to be dealt with as provided in Sections 32 and 33.

    4. In view of the above legal position and the fact that the award was passed on 18-11-1995 and the compensation has not been paid nor deposited in the court nor received by the appellants till 31-1-2014 and the physical possession is also with the appellants as on date, the subject acquisition has to be held to have been lapsed. We hold accordingly.

    5. The civil appeals are allowed as above with no order as to costs.