Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • provisions of Rule 17 of the Rules. Rule 17 of Rule
  • provision of Section 5 of Indian Contract Acts
  • provision of sub-rule (4) of Rule 7 of the Rules
  • Section 79 of the Assam Forest Regulation
  • Rule 17 read with sub-rule; (4) of Rule 7,
  • provisions of the Indian Contract Act
  • provision of the Indian Contract Act,
  • provisions of Indian Contract Act,
  • Sec. 5 of the Contract Act
  • provision of Rule 17
  • Sub-Rule (4) of Rule 7
  • schedule 4, rule 7
  • sub-rule (4) Rule 7
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • provisions of Rule 17 of the Rules. Rule 17 of Rule
  • provision of Section 5 of Indian Contract Acts
  • provision of sub-rule (4) of Rule 7 of the Rules
  • Section 79 of the Assam Forest Regulation
  • Rule 17 read with sub-rule; (4) of Rule 7,
  • provisions of the Indian Contract Act
  • provision of the Indian Contract Act,
  • provisions of Indian Contract Act,
  • Sec. 5 of the Contract Act
  • provision of Rule 17
  • Sub-Rule (4) of Rule 7
  • schedule 4, rule 7
  • sub-rule (4) Rule 7
Smart Summary

Structured Summary of the Opinion (S.K. Homchaudhuri, J.)

Factual and Procedural Background

The writ petition challenges notice/order No. B/18,717-18/7(a) dated 19.7.80 issued by the Divisional Forest Officer, Cachar Division, Silchar, which demanded that the petitioner pay Rs. 30,075 as the difference between the amount he had offered in a tender (Rs. 36,575) for settlement of the Nunoi C.S (2nd year lease) Bamboo Mahal and the amount realized by the government on resale after alleged cancellation.

The petitioner had submitted a tender in response to a sale notice dated 17.12.76 for settlement of the Mahal for the period 1.4.77 to 31.3.78, offering Rs. 36,575. Before acceptance, by application dated 21.3.77 the petitioner sought to withdraw his tender, explaining that mature bamboo had already been removed and the remaining bamboo was not extractable. Despite this, the Department (Respondent No. 4) communicated provisional confirmation of settlement and repeatedly asked the petitioner to sign the agreement and deposit security and instalments; the petitioner did not do so.

The petitioner appealed to the Government of Assam against settlement; the Government rejected the appeal by order dated 12.7.78 but allowed the petitioner an opportunity to operate the Mahal if he paid dues and refixed the period (1.7.78–30.6.79). Subsequent communications demanded payment; a resale notice was issued on 23.2.79 and the Department warned that any shortfall on resale would be recoverable from the petitioner. By the impugned notice dated 19.7.80, the Department demanded Rs. 30,075 and threatened recovery through Bakijai proceedings. The petitioner filed the present writ petition seeking to set aside that notice/order.

Legal Issues Presented

  1. Whether the petitioner, having withdrawn his tender before acceptance, was liable to pay the difference between his tendered amount and the proceeds of resale under the Assam Sale of Forest Coupes and Mahal by Tender System Rules, 1977 (in particular sub-rule (4) of Rule 7 and Rule 17).
  2. Whether the declaration required by sub-rule (4) of Rule 7 (that a tenderer will not withdraw and will make good any deficiency if he withdraws) can be enforced so as to negate the statutory right under Section 5 of the Indian Contract Act to revoke an offer before acceptance.
  3. Whether Rule 17 (which exposes a successful tenderer to liability on cancellation and resale for the remaining period) applies where there was no completed sale to the petitioner because he withdrew before acceptance, and where resale occurred after the originally fixed settlement period had expired.

Arguments of the Parties

Petitioner's Arguments

  • The petitioner withdrew his tender by application dated 21.3.77 well before its acceptance by the authorities, and therefore he was not liable to pay any amount demanded subsequently.
  • Because the offer was revoked before acceptance, no sale to the petitioner was ever completed, and Rule 17 (which applies to cancellation and resale after a completed sale) cannot be invoked against him.
  • Any demand to make good a deficiency after resale is not applicable where there was no accepted sale; the resale in the record was also after the expiry of the settlement period (sale period had been 1.4.77 to 31.3.78), undermining the Rule 17 premise of resale for the remaining settlement period.

Respondents' / Government Advocate's Arguments

  • The settlement was governed by the Assam Sale of Forest Coupes and Mahal by Tender System Rules, 1977 (“the Rules”), and the sale notice was issued under those Rules.
  • The petitioner had made the prescribed declaration under schedule 4, Rule 7 (sub-rule (4)) when submitting the tender; that declaration purported to bind him not to withdraw and to make good any deficiency after resale.
  • Relying on sub-rule (4) of Rule 7 and Rule 17 (read with schedule 4, rule 7), the petitioner was liable to pay the difference between his tender offer and the amount realized on resale.
  • The Government Advocate contended that because the Rules are local rules framed specifically for forest settlement, the provisions of the Indian Contract Act (including Section 5) could not be made applicable to these settlements and therefore could not be invoked to permit withdrawal of the tender before acceptance.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court examined the applicable statutory and rule provisions and the temporal facts surrounding withdrawal, acceptance, and resale. The analysis proceeded in the following steps:

  1. The court identified Section 5 of the Indian Contract Act as the relevant statutory rule on revocation: a proposal may be revoked at any time before communication of its acceptance is complete as against the proposer. The petitioner had revoked his offer by application dated 21.3.77, before acceptance; therefore he had the statutory right to withdraw.
  2. The court considered the Rules: Rule 7 (sub-rule (4)) required a declaration by the tenderer that he would not withdraw during the time required for intimation of acceptance or afterwards if accepted, and that if he did withdraw he would be liable to pay the whole sum or such amount as the Conservator/Government considered necessary to make good the loss and damages. Rule 17 provided liability only where a tenderer whose tender has been accepted fails to pay security/instalments or execute the agreement, permitting cancellation and resale "for the remaining part of the coupe or mahal period" at the risk of such tenderer, with differential recoverable if resale proceeds were less.
  3. The court found an inconsistency between sub-rule (4) of Rule 7 and Rule 17. Rule 17 imposes liability after a sale has been completed and then cancelled/resold for the remaining settlement period; sub-rule (4) of Rule 7 purports to impose liability even where a tender is withdrawn before any acceptance or completed sale.
  4. Applying Section 5 of the Indian Contract Act, the court concluded that the petitioner's revocation before acceptance was effective: "the petitioner revoked his proposal/offer well before acceptance thereof." Because revocation was lawful under the Contract Act, the "contract of sale of the Mahal" could not be enforced against him and he could not be saddled with liability to make good any deficiency arising from resale.
  5. The court rejected the Government Advocate's contention that the local Rules could displace the statutory right under the Contract Act. The court held that a statutory right under the Contract Act could not be overridden by a local rule. Accordingly, sub-rule (4) of Rule 7, "so far as it is contrary to and/or comes in conflict with" the provisions of the Indian Contract Act, was declared inoperative and void.
  6. The court also observed an additional factual difficulty with the Department's position: the resale notice was issued on 23.2.79 which was after the original settlement period (1.4.77 to 31.3.78) had expired; Rule 17 contemplates resale for the remaining part of the settlement period, a condition not met here.
  7. On these consolidated legal and factual bases, the court concluded that the impugned demand that the petitioner pay Rs. 30,075 was arbitrary, illegal and void.

Holding and Implications

Holding: The writ petition is allowed; the impugned notice/order dated 19.7.80 demanding Rs. 30,075 is set aside and the Rule is made absolute.

Direct implications and consequences:

  • The petitioner is not liable to pay the demanded amount of Rs. 30,075 arising from the Department's calculation of the difference between his tender and the resale proceeds.
  • The court declared that sub-rule (4) of Rule 7 of the Assam Sale of Forest Coupes and Mahal by Tender System Rules, 1977, insofar as it conflicts with the provisions of the Indian Contract Act (notably Section 5), is inoperative and void and cannot be enforced to deny a tenderer's statutory right to revoke an offer before acceptance.
  • The court noted the resale occurred after the settlement period ended, undermining the applicability of Rule 17 (which limits resale-based liability to the remaining settlement period), and this factual circumstance supported the conclusion that Rule 17 could not be applied to saddle the petitioner with liability here.
  • No costs were awarded (the court "make[s] no order as to costs").

Broader implications:

The opinion limits the enforceability of a local rule provision that would operate to extinguish the statutory right of revocation under the Indian Contract Act; however, the opinion does not purport to formulate a general new precedent beyond the facts found and the textual conflict described. The decision's immediate effect is confined to declaring the particular sub-rule of the local Rules inoperative to the extent it conflicts with the statutory provisions of the Contract Act and to setting aside the specific demand on the petitioner.

    Abdus Salam Choudhury v. The State Of Assam & Others

    S.K Homchaudhuri, J.:— This writ petition is directed against the notice/order No. B/18,717-18/7(a) dated 19.7.80 issued by the Divisional Forest Officer, Cachar Division, Silchar asking the petitioner to pay a sum of Rs. 30075/- being the difference of an amount offered by the petitioner for settlement of the Nunoi C.S (2nd year lease) Bamboo Mahal and the amount received by the Department on the sale of the said mahal after cancellation of the alleged settlement with the petitioner.

    In response to a sale notice dated Silchar, the 17th December, 1976 issued by the Respondent No. 4, the Divisional Forest Officer, Silchar inviting tender for settlement of different Bamboo Mahals including Nunoi C.S (2nd year lease) Bamboo Mahal for the period from 1.4.77 to 31.3.78, the petitioner submitted tender for settlement of the Nunoi Mahal offering an amount of Rs. 36,575/-.

    The petitioner states after submission of the tender, on careful inspection of the inner part of the said Mahal, having found that clumps of mature bamboo were taken away by the newly appointed Forest Contractor and that it was not possible to extract left over mature bamboos from the deep forest, the petitioner before consideration and acceptance of his offer made in the tender by an application dated 21.3.77 addressed to the Respondent No. 3 to withdraw his offer requesting that his tender might be cancelled. Inspite of the fact that the petitioner withdrew his offer by the application dated 21.3.77 well before acceptance thereof, the respondent No. 4 vide Memo No. B/8959/60/7(a) dated 28.4.77 intimated the petitioner that the provisional settlement of the Mahal in question made vide letter No. FGM. 24.C/6/77-78/1393 dated 7.4.77 by the Conservator of Forests stood confirmed and asked the petitioner to sign an agreement on or before 6.5.77 and to deposit the first instalment of Rs. 9,146/- and also the security money amounting to Rs. 1,929/-. That was followed by another letter dated 1.7.77 directing the petitioner to pay the first kist money within 7 days. The petitioner neither signed the agreement nor made any deposit. The respondent No. 4 by a letter dated 26.7.77 intimated the petitioner that the Conservator of Forests had rejected the prayer of withdrawal of tender made vide the application dated 21.3.77 The respondent No. 4 again by letter dated 9.8.77 asked the petitioner to deposit the first kist money and the security money within 7 days failing which it was threatened that necessary action would be taken against the petitioner. The petitioner preferred an appeal before the Government of Assam for setting aside the order of settlement. By an order dated 12.7.88, the Government rejected the petitioner's appeal and intimated that if the petitioner wanted to operate the Mahal, he should be given a chance by refixing the period of settlement from 1.7.78 to 30.6.79 provided he paid the security money and kist money before 30.7.78 failing which Mahal should be put to resale at the risk of the petitioner. The petitioner filed application for review of the order of the Government dated 12.7.78 However, the Government by order dated 9.8.78 asked the petitioner to deposit the kist money and the security money within 7 days and further intimated that the Mahal would be put to resale at the risk of the petitioner, in case of his failure to make the deposit.

    Ultimately, on 23.2.79 sale notice of the Mahal was issued and the Respondent No. 4 by letter dated 26.2.79 intimated the petitioner that in case the sale proceeds of the Mahal was lesser than the amount offered by him, the Government dues would be recovered from the petitioner. The petitioner by the application dated 12.3.79 replied to the said letter denying his liability.

    By a letter dated 30.5.79, the Respondent No. 4 intimated the petitioner that he was liable to pay the full amount of Rs. 36,575/-, he offered in his tender under Section 79 of the Assam Forest Regulation and asked him to deposit the amount within 10 days. That was followed by another letter dated 6.11.79 asking the petitioner to deposit an amount of Rs. 36,575/- within 10 days. The petitioner by an application dated 13.11.79, intimated the Respondent No. 4 that his application for review was pending disposal by the Government. Thereafter, on, 20.12.79, the respondent No. 4 again asked the petitioner to deposit an amount of Rs. 36,575/- within 10 days. Ultimately, by the impugned notice/order dated 19-7-80, the respondent No. 4 intimated the petitioner that as directed by the Government, the petitioner was to deposit a sum of Rs. 30,075/- being the difference of the amount offered by the petitioner and the amount received by the Government on resale within 10 days. In the said letter, it was further intimated that if the petitioner failed to deposit the said amount, as directed, action would be taken to recover through Bakijai proceeding. Being aggrieved, the petitioner has approached this court by this writ petition with the prayer of setting aside the impugned notice/order.

    It is submitted by the petitioner that he having withdrawn his offer to get the settlement of the Mahal well before the acceptance thereof by the respondent No. 3 and 4, he is not liable to pay any amount to the Government as demanded by the respondent No. 4 in the impugned letter/notice. It is disputed by the respondents that the petitioner's application dated 21-3-77 withdrawing his tender offering Rs. 36,575/- for settlement of the Mahal was received by the appropriate authorities before consideration and acceptance thereof. The learned Government advocate however, has submitted that the Settlement of the Mahal was governed by the provisions of Assam Sale of Forest Coupes and Mahal by Tender System Rules, 1977, hereinafer mentioned as the ‘Rules’ and the sale notice was issued under the provision of the said rules. It is further submitted that the petitioner also made a declaration as provided under schedule 4, rule 7 of the rule, while he submitted his tender and that having made such declaration in his tender, under Rule 17 read with sub-rule; (4) of Rule 7, the petitioner is liable to pay the difference of the amount offered by the petitioner and the amount received after the resale of the Mahal.

    Rule 17 provided:—

    “Cancellation and resale for failure to pay security-instalments and to execute agreement. If the tenderer whose tender has been accepted fails to pay the security or to pay the instalment on due dates mentioned in R. 15 or to execute agreement mentioned in R. 16, the sale of the coupe or mahal shall be liable to be cancelled and the coupe or mahal shall be resold for the remaining part of the coupe or mahal period at the risk of such tenderer as regards the loss to Government and if the proceeds on resale are less than the value at which it originally sold, the difference shall be realisable from him, and further the earnest money shall be forfeited and the whole of the fixed security deposit or part thereof as may be necessary, shall be adjusted against the dues”.

    Rule 7 provides:—

    “Tender and its enclosure—(1) There shall be a seperate tender for each coupe or mahal or lot with the requisite court fee affixed to it.

    (2) Each tender shall be in the tender form as in Appendix-II.

    (3) The tenderer shall also state in the tender the price which he offers to pay.

    (4) He shall also make a declarations as follows:—

    “I agree that I will not withdraw the tender offered by me during the time that will be required for intimation of acceptance the tender for coupe/mahal being given to me; nor will I withdraw if afterwards should my tender be accepted. If I withdraw the tender, then I am liable to pay the whole sum of the tender or such amount on account of deficiency as in the opinion of the Conservator of Forests or Government, as the case may be, considered necessary to make good the whole of the loss and damages that may be suffered by Government in consequence thereof and I shall pay the same and if I fail to pay it, then it will be recovered from me as arrear of land revenue”.

    As per provision of Rule 17 the Sale of coupe or mahal is liable to be cancelled due to failure on the part of the tenderer to deposit security money/kist money etc. and the mahal/- coupe shall be resold for the remaining part of the settlement period at the risk of such tenderer.

    Unless sale of Mahal or Coupe is complete, the question of cancellation of sale and re-sale thereof cannot and does not arise. Here in the instant case, the petitioner admittedly withdrew his offer made in his tender well before acceptance there of by the settling authorities and as such, there could not be any sale of the Mahal to the petitioner and the question of cancellation of sale and re-sale thereof at the risk of the petitioner for the remaining part of the settlement period of mahal could not and did not arise. Besides, the period of settlement in the instant case was from 1.4.77 to 31.3.78 and the notice for resale of the mahal in question was issued of 23.2.79 long after the expiry of the settlement period, although Rule 17 contemplates resale of the Mahal in respect of the remaining part of the settlement period. The learned Government Advocate pracing reliance of sub-rule (4) Rule 7 has submitted that since the petitioner in his tender made a declaration as contemplated under sub-rule (4) Rule 7 he is liable to make good the loss suffered by the Government even though he withdrew his tender before acceptance thereof, inasmuch as per as declaration, the petitioner bound himself to pay the whole sum of the tender or such amount on account of deficiency after resale.

    It appears that the contents of declaration as provided under Sub-Rule (4) of Rule 7 is inconsistent with the provisions of Rule 17 of the Rules. Rule 17 of ‘Rule’ saddled a tenderer with the liability to make good the loss after a sale of Mahal or coupe is cancelled and is resold for the remaining part of the settlement period of the Mahal or coupe, whereas the declaration as provided in Sub-Rule (4) of Rule 7 makes a tenderer liable to make good the loss before a sale of the Mahal is made and even in case the tender is withdrawn before acceptance thereof.

    Under the provision of Section 5 of Indian Contract Acts a proposal may be revoked at any time before communication of its acceptance is complete as against the proposer, but not afterwards. Admittedly, the petitioner withdrew his offer made in his tender by the application dated 21.3.77 well before acceptance thereof. In other words, the petitioner revoked his proposal/offer well before acceptance thereof. Under the provision of the Indian Contract Act, the petitioner has the statutory right to withdraw/revoke his offer for getting settlement of the mahal or coupe before acceptance thereof by the settling authorities. It being a statutory right of the petitioner under the provisions of the Indian Contract Act entitling him to withdraw/revoke his offer/proposal made in his tender before acceptance thereof by the authorities and the petitioner having done so in the instant case, the contract of sale of the Mahal in question for the settlement period could not be enforced on the petitioner and he cannot be saddled with the liability to make good the deficiency. The settling authorities were is no way prejudiced or inconvenienced by the withdrawal of the offer made by the petitioner in his application dated 21.3.77 before consideration of tenders. The settling authorities could either settle the Bamboo Mahal in question to other suitable tenderer or could call for fresh tenders, if other tenders were not found acceptable. Instead, the settling authorities, purported to accept the offer of the petitioner which stood legally revoked and insisted on enforcement thereof and ultimately saddled the petitioner with the liability to pay Rs. 30,075/- by the impugned notice/order.

    The learned Government Advocate, however, contended that the Rules being local rule framed specially for the purpose of Settlement of the Forest coupes and Mahal, provisions of Indian Contract Act, cannot be made applicable in respect of settlement of the Mahal with the Forest Contractor.

    We are unable to accept the submission of the learned Government Advocate. We hold that the petitioner's statutory slight under the provision of Contract Act, cannot be overridden or taken away by the provision of the local Rules framed by the State Government regulating the settlement/sale of Mahal/Coupe to the forest Contractors. We hold that the provision of Sub-Rule (4) of Rule 7 of the Rules so far as it is contrary to and/or comes in conflict with the provisions of the Indian Contract Act, is inoperative and void and cannot be enforced and that the petitioner under Sec. 5 of the Contract Act has the right entitling him to withdraw/revoke his offer/proposal made in his tender before acceptance thereof by the settling authorities and having done so by his application dated 21-3-77 the petitioner is not liable to pay the difference between the amount he offered and the amount received by the settling authority after resale of the Mahal. The impugned demand notice/order asking the petitioner to pay Rs. 30,075/- is, therefore arbitrary, illegal and void and is hereby set aside.

    The petition is allowed. Rule is made absolute. However, we make no order as to costs.