Smart Summary

Summary of Opinion — I.A. No.421 of 2013 in DFR No.1975 of 2013 (Appellate Tribunal for Electricity)

Factual and Procedural Background

This application concerns an interlocutory petition to condone a delay of 385 days in filing an appeal against the Tariff Order dated 13.7.2012. The Applicant/Appellant is recorded as North Municipal Corporation of Delhi (listed under the heading with the Delhi Electricity Regulatory Commission). Respondents include Tata Power Delhi Distribution Limited, BSES Rajdhani Power Limited and BSES Yamuna Power Limited. The grievance was that the Tariff Order of 13.7.2012 changed the Applicant's category from the highest slab of Domestic Tariff to a non-domestic (High Tension) tariff for the financial year 2012-13. The Applicant filed a review petition (challenging the tariff) which was dismissed on 3.7.2013; the Appeal was filed on 13.9.2013. The present Application sought condonation of the inordinate delay in filing that Appeal.

Legal Issues Presented

  1. Whether the delay of 385 days in filing the Appeal against the Tariff Order dated 13.7.2012 should be condoned.

Arguments of the Parties

Applicant's Arguments

  • The Applicant stated it became aware of the Tariff Order only in February 2013, and thereafter filed a Review Petition challenging the Tariff; the Review was dismissed on 3.7.2013, and the Appeal was filed on 13.9.2013. On this basis, the Applicant sought condonation of the delay (asserting bona fide reasons).

3rd Respondent's Arguments

  • The 3rd Respondent argued the Applicant had knowledge of the Tariff Order much earlier: a bill reflecting the non-domestic High Tension tariff was raised immediately after the Tariff Order of 13.7.2012; the Applicant did not dispute this billing. The 3rd Respondent further pointed out that the Review Petition was filed only on 11.6.2013 after a long delay (nearly one year), and the Appeal was filed on 13.9.2013 after about two months from dismissal of the Review. There was no adequate explanation for these delays; therefore condonation should be refused.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court reviewed the affidavits, additional affidavit and the reply filed by the 3rd Respondent and proceeded through the following reasoning:

  • The Tariff Order imposing non-domestic tariff was dated 13.7.2012. The Respondent produced evidence that a bill reflecting the non-domestic High Tension tariff was issued to the Applicant immediately thereafter; the Applicant did not dispute issuance of that bill. On that factual basis the Applicant's claim that it first learned of the Tariff Order in February 2013 was held to be factually incorrect.
  • Even assuming the Applicant's acknowledged date of knowledge (February 2013), the Applicant waited until 11.6.2013 — about four months — to file the Review Petition; the Applicant did not explain this period of inaction.
  • The Review Petition filed on 11.6.2013 was disposed of promptly on 3.7.2013. Nevertheless, the Appeal was filed only on 13.9.2013 (about two months and ten days later); this delay was also unexplained.
  • The Tariff year for which the change was made (2012-13) ended on 31.3.2013. The Applicant sought retrospective revision of tariff after the relevant year had concluded. The Court accepted the Respondent's submission that revising tariff for a past year at this stage would prejudice the Respondent and would make it impracticable to change tariffs for all consumer categories.
  • On the cumulative facts — the billing evidence, unexplained gaps in filing review and appeal, and prejudice/impracticability of retrospective revision — the Court concluded the Applicant failed to show sufficient cause or bona fide diligence to justify condoning the inordinate delay.

Holding and Implications

The Application to condone the delay of 385 days is dismissed; consequently, the Appeal is rejected.

Implications:

  • Direct effect: The Applicant's request for condonation was refused and the substantive Appeal challenging the Tariff Order dated 13.7.2012 has been rejected (i.e., it will not be admitted for consideration because of the uncondoned delay).
  • No broader or novel precedent was articulated in the opinion; the decision rests on the Court's application of established principles relating to condonation of delay, the factual finding about prior billing, unexplained delay in filing review/appeal, and the practical prejudice of retrospective tariff revision.

Outcome dated: 5th Feb, 2014. Bench: Justice M. Karpaga Vinayagam (Chairperson) and Rakesh Nath (Technical Member).

To access the original judgment, please Sign In or Subscribe.

    North Municipal Corporation Of Delhi v. Delhi Electricity Regulatory Commission

    I.A.No.421 of 2013 IN DFR No.1975 of 2013 Page 1 of 6

    Appellate Tribunal for Electricity (Appellate Jurisdiction) I.A. No.421 of 2013

    IN

    DFR No.1975 of 2013 Dated:5th Feb, 2014 Present: HON'BLE MR. JUSTICE M KARPAGA VINAYAGAM, CHAIRPERSON HON'BLE MR. RAKESH NATH, TECHNICAL MEMBER

    1. Delhi Electricity Regulatory Commission, In the Matter of:

    North Municipal Corporation of Delhi Dr. S.P.M Civic Centre,

    Minto Road,

    New delhi-110 002

    …Appellant/Applicant

    Versus

    Vinayamak Bhawan,

    "C" Block, Shivalik, Malviya Nagar, New Delhi-110017

    2. Tata Power Delhi Distribution Limited., Grid Sub-Station Building,

    Hudson Lines, Kingsway Camp,

    Delhi-110 009

    3. BSES Rajdhani Power Limited BSES Bhawan, Nehru Place, New Delhi-1110 009

    4. BSES Yamuna Power Limited., Shakti Kiran Building Karkardooma

    Delhi

    ...Respondent(s)

    1

    Counsel for the Appellant(s) : Mr. B P Agarwal Mr. Ujjwal Kr. Jha

    Counsel for the Respondent(s): Mr. Manu Seshadri for R-1 Mr. Alok Shankar for R-2

    Mr. Hasan Murtaza

    Mr. Aditya Panda for R-3 & 4

    O R D E R

    1. This is an Application to condone the delay of 385 days in filing the Appeal against the Order dated 13.7.2012.

    PER HON'BLE MR. JUSTICE M. KARPAGA VINAYAGAM,

    CHAIRPERSON

    2. Aggrieved by the Impugned Order by which the category of the Appellant falling under the highest slab of Domestic Tariff was changed into non-domestic tariff in the Tariff Order dated 13.7.2012 in respect of the Financial Year 2012-13, the Applicant has filed this Appeal.

    3. There is a delay of 385 days in filing the Appeal. Therefore, the Applicant has filed this Application to condone the said delay giving explanation for the delay.

    4. According to the Applicant, although the Impugned Order was passed on 13.7.2012, the Applicant came to know about the order only in February, 2013, thereafter, the Applicant filed a Review Petition challenging the said Tariff

    2

    Order but the same was dismissed on 3.7.2013, thereupon, the Appeal was prepared and the same was filed on 13.9.2013 and that therefore, the delay which was due to bona fide reasons may be condoned.

    5. Opposing this Application, with vehemence, the 3rd Respondent contended that even though the Main Order was passed on 13.7.2012, the Applicant filed a Review Petition only on 11.6.2013 after a long delay i.e. nearly one year, thereafter, i.e. within three weeks, the Review Petition was dismissed on 3.7.2013 by the Delhi Commission and then after two months, the Appeal has been filed on 13.9.2013 and as such, there was no proper explanation for this inordinate delay and hence the Application to condone the delay may be dismissed.

    6. We have considered the submissions made by both the parties and also perused the Affidavit as well as the Additional Affidavit filed by the Applicant and the reply filed by the Distribution Licensee, the 3rdRespondent.

    7. On going through the Affidavits, reply and other records, we are of the opinion that the Applicant has failed to show sufficient cause to condone the inordinate delay of 385 days in filing the Appeal and therefore, this Application is liable to be dismissed. The detailed reasons are as follows:

    3

    (a) The main tariff order allowing the Respondent to charge the Applicant on non domestic tariff was passed as early as on 13.7.2012. According to the Applicant, it came to know about the Tariff Order dated 13.7.2012 only in February, 2013 when the objections with regard to category were invited for the determination of new tariff for the Financial Year 2013-14. This statement of the Applicant is found to be factually wrong.

    (b) According to the Respondent, in pursuance of the Tariff Order dated 13.7.2012, the Respondent raised a bill immediately thereafter mentioning the tariff category as a non domestic High Tension and issued to the Applicant. This fact, pointed out by the Respondent, has not been disputed by the Applicant. Therefore, the contention of the Applicant that it came to know about the order only in February, 2013, is baseless.

    (c) Even assuming that the Applicant came to know about the order only in February, 2013, the Applicant filed the Review Petition only on 11.6.2013 i.e. after about four months. This period has not been explained as to why the Applicant

    4

    took time to file the Review in June, 2013, even though the Applicant admitted that it came to know about the Impugned Order in February, 2013 itself.

    (d) The Review Petition which was filed on 11.6.2013 before the Delhi Commission had been disposed of without any delay on 3.7.2013 itself. Even then, the Appeal has been filed only on 13.9.2013 after about 2 months and 10 days. This delay also has not been explained.

    (e) The main Tariff Order was passed on 13.7.2012 in respect of the Financial Year 2012-13. This period of Tariff year was already over on 31.3.2013. The Applicant received the bills immediately after the Tariff Order was passed on 13.7.2012 at non-domestic tariff according to the Tariff Order dated 13.7.2012. Nevertheless, the Applicant had chosen to file the Review only on 11.6.2012 i.e. after the tariff period was over. Now in the present Appeal, the Applicant is seeking for a retrospective revision of the tariff after the year in question was already over. The learned Counsel for the Respondent has correctly pointed out that any revision of tariff of the past year at this stage would cause prejudice to the Respondent and in

    5

    that event, the tariff for all categories of consumers will have to undergo a change which is impracticable at this stage.

    8. In view of the above, we are not inclined to accept the explanation offered by the Applicant in the Affidavit especially when it reflects lack of bona fide and lack of diligence. Hence, this Application to condone the delay of 385 days is dismissed.

    9. Consequently, the Appeal is also rejected.

    (Rakesh Nath) (Justice M. Karpaga Vinayagam) Technical Member Chairperson

    Dated:5thFeb, 2014 √REPORTABLE/NON-REPORTABALE