Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Indian contract Act and illustration (a) to section 73
  • section 73 of the Indian contract Act
  • Indian contract Act, section 73,
  • SECTION 73 CONTRACT ACT
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Indian contract Act and illustration (a) to section 73
  • section 73 of the Indian contract Act
  • Indian contract Act, section 73,
  • SECTION 73 CONTRACT ACT
Smart Summary

Concise Analytical Summary of the Provided Opinion

Factual and Procedural Background

The plaintiffs are a firm doing business in Mysore and Madras that in 1913 obtained from the Mysore Government an Abkād contract and arranged with the defendants in Madras for the defendants to import molasses for the plaintiffs for use in the plaintiffs' Bangalore factories. Under two contracts the defendants were bound to ship 800 tons of solid Java molasses in October 1914 (to arrive in Madras in November 1914). Because of shipping dislocation following the outbreak of war in August 1914, the defendants failed to make the October shipment, committing a breach of contract.

The plaintiffs sued for damages. At first instance the learned Judge awarded the plaintiffs the amount paid under protest for certain detained shipments (Rs. 2,725-15-6) but granted only nominal damages (Rs. 100) for the main claim (alleged difference between contract price and market price for the 800 tons). The plaintiffs appealed under the Letters Patent seeking substantially higher damages for the non-delivery. The appeal was argued before Wallis, C.J., and Sadasiva Ayyar, J., whose opinions are included in the record.

Legal Issues Presented

  1. What is the proper measure of damages under section 73 of the Indian Contract Act and its illustrations where goods contracted for are not deliverable because of the seller's breach and there is effectively no market at the place of delivery?
  2. To what extent must a buyer mitigate loss by procuring substitute goods, and how does that mitigation duty affect the measure of damages where there is either a local market, a nearest practical market, or no market at the place of delivery?
  3. How should a court compute damages (for non-delivery) where evidence of the relevant market price at the appropriate place and date is imperfect or incomplete?

Arguments of the Parties

Appellants' (Plaintiffs') Arguments

  • The plaintiffs claimed damages representing the difference between the contract price and the market price for 800 tons of molasses in November 1914 (stated as Rs. 23,000 in their pleading) because the defendants failed to ship the October consignment.
  • The plaintiffs also sought recovery of Rs. 2,725-15-6 paid under protest to the defendants for other shipments detained.
  • Plaintiffs' counsel (Mr. Chamier) put forward calculations estimating a c.i.f. Java–Madras price on 29 November 1914 of Rs. 2-8-7 per cwt, from which a large difference with the contract price was claimed. The plaintiffs relied on documentary material including Exhibit G (defendants' October letter quoting Rs. 2-9-3 per cwt ex war risk) and Exhibit G1 as evidence of higher prices at the relevant time.

Respondents' (Defendants') Position

  • The defendants did not tender evidence as to the prevailing Java c.i.f. prices or prevailing freight rates for the relevant period (October–November 1914).
  • Defendants had offered to combine shipments (ship October consignment with November consignment) or make an early December shipment — offers that the court regarded as relevant to mitigation and to whether plaintiffs suffered actual loss.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Dunkirk Colliery v. Lever Cited in relation to the Explanation to section 73 (mitigation principle). The Explanation is said to be in accordance with the decision; used to support mitigation duty language in the section.
British Westing House Electric & Manufacturing Co. Ltd v. Underground Electric Railways Co. of London Ltd (House of Lords) Principle that plaintiff must take reasonable steps to mitigate loss; Lord Haldane's statement on compensation and mitigation. Quoted to explain that damages are compensation for pecuniary loss but qualified by a duty on plaintiff to mitigate; used to interpret s.73 Explanation.
Jamal v. Moolla Dawood Sons and Co. (Judicial Committee) Affirmation of the mitigation principle and application of market-price rule for non-delivery. Referred to as recent authority laying down the law to the same effect as Lord Haldane's dictum; applied to support use of market-price test where a market exists.
Rodocanachi v. Milburn Rule that where there is a market at place of delivery (and seller has no notice of buyer's resale contract), market price is the test for damages on failure to deliver. Cited as foundational for applying market-price test in non-delivery cases where a market exists; used to contrast with the present "no market" situation.
Williams Brothers v. Agius (House of Lords) Approval of the Rodocanachi rule concerning market-price measurement. Used to support the market-price rule where applicable.
Erie County Natural Gas and Fuel Co. v. Carroll (Lord Atkinson) Observation that where there is no market the buyer may procure substitute but is not necessarily bound to do so. Quoted to show that procuring a substitute is permissible as mitigation, but not strictly obligatory in all cases.
Borries v. Hutchinson; Hinds v. Liddell Where buyer was under contract to resell, the resale price is evidence of the value of the goods at place and time of delivery. Referred to as authority that resale price may be used as evidence of value when goods are purchased for resale.
Stroms Bruks Aktie Bolag v. John and Peter Hutchinson Approval of Blackburn, J.'s judgment in O'Hanlon; supports resale-price/value approach. Cited to endorse the English approach that resale price can indicate value where buyer intended resale.
O'Hanlon v. Great Western Ry. Co. Statement that the natural and fair measure of damages is the value of the goods at the time and place where they ought to have been delivered (value to the owner). Used as precedent for valuing goods for buyer's use at the contract time/place; also for hypothetical-market calculation where no actual local market exists.
Portman v. Middleton Example where plaintiff recovered price and extra cost of procuring substitute but not special damages unknown to defendant. Used to illustrate limits of recoverable damages for special losses not known to the defendant.
Smeed v. Foord Seller held liable for natural consequences of delay (deterioration of wheat owing to delay in supplying threshing machine). Relied upon to show that natural consequences of delay or non-supply may be recoverable as damages.
Gee v. Lancashire & Yorkshire Railway Co. Held that as a matter of law it could not be said that stoppage of buyer's mills was necessarily a natural consequence of delay in delivering cotton. Referred to as an example limiting automatic attribution of all consequential losses to seller's breach.
Elbinger Actien-Gesellschafft v. Armstrong Where no market exists for an article, the contract-versus-market-price rule is inapplicable; damages awarded as reasonable result of delay. Used to show that courts will award damages reflecting reasonable loss where no market-value test is possible.
Wertheim v. Chicoutimi Pulp Co. (House of Lords) Case of late delivery; regarded as consistent with illustration (a) to section 73. Referred to by the Court as consistent with the interpretation adopted from illustration (a) of section 73.
Jugmohandas v. Nusserwanji Jenkins Where there was no ready market rate, courts must have recourse to some other test and examine facts to fix reasonable compensation. Quoted to support taking other facts and materials into account where no market rate exists and to justify resorting to alternative measures of value.

Court's Reasoning and Analysis

The court's analysis proceeds from the statutory text of section 73 of the Indian Contract Act and the Explanation appended to it. The guiding structure of reasoning in the opinions is as follows:

  1. Statutory baseline: Section 73 requires compensation for pecuniary loss that "naturally arises in the usual course of things" from a breach or such loss as the parties knew when they made the contract was likely to result. The Explanation requires taking into account "the means which existed of remedying the inconvenience" caused by non-performance (mitigation).
  2. Role of authority: The Explanation and mitigation principle cited are said to accord with prior authorities (e.g., Dunkirk Colliery, British Westing House) and later decisions (Jamal), establishing that a plaintiff must take reasonable steps to mitigate loss and cannot recover loss caused by his neglect to mitigate.
  3. Market vs. no-market distinction: Where a market exists at place of delivery, the ordinary rule (derived from Rodocanachi and approved authorities) is to measure damages by the difference between contract price and market price on the date of delivery. This treats the market price as the objective test for value in non-delivery cases.
  4. When there is no market at the place of delivery, several approaches have been identified in the authorities:
    • The buyer may (if reasonable and calculated to diminish loss) procure a substitute at higher cost and recover the difference.
    • Where the goods were for resale, the resale price (or contract resale price) can be evidence of the goods' value.
    • In absence of direct market data, courts may attempt to estimate a reasonable value (for example, by reference to nearest practical market plus carriage and importer’s profit — the "hypothetical market" approach seen in O'Hanlon) or resort to the illustration(s) appended to s.73.
  5. Application to this case:
    • The judges agreed that Madras had no market for the particular goods; Java would be the nearer and appropriate market to consider for substitutes in the facts of this case.
    • Wallis, C.J., emphasised that the court is bound by the Indian Contract Act and Illustration (a) to section 73, which states that the proper measure in such circumstances is the sum by which the contract price falls short of the price for which the purchaser might have obtained similar goods at the time they ought to have been delivered. He accepted and followed that illustration as the applicable rule.
    • Although plaintiffs' counsel provided calculations to estimate a Java c.i.f. price (Rs. 2-8-7 per cwt) for 29 November 1914, those figures — particularly the freight components — were not proved; defendants had not tendered contrary evidence but the asserted Java c.i.f. price was not established to the court's satisfaction.
    • Notwithstanding imperfect proof, the court considered the documentary material (including the defendants' own Exhibit G quoting Rs. 2-9-3 per cwt ex war risk and Exhibit G1) and concluded that there was sufficient evidence to justify a specific award: that the hypothetical value of 800 tons in Madras at the end of November exceeded the c.i.f. contract price by not less than Rs. 5,000.
    • Sadasiva Ayyar, J., after discussing the conceptual difficulties of awarding consequential damages where no market exists and giving an illustrative hypothetical, reached a similar conclusion that Illustration (a) authoritatively interprets s.73 for "no market" cases and that Rs. 5,000 was a reasonable award on the evidence before the court (accepting that plaintiffs could and should have adduced further evidence but that some materials did exist to sustain a quantified award).
  6. Practical consequences considered by the court: The judges noted that, apart from the statutory illustration and authorities, the plaintiffs had been admittedly well stocked and could have accepted defendants' offers to combine shipments or to ship in early December — factors relevant to mitigation and to the finding that no actual loss was proved on a strict demonstration of actual expenditure. Nonetheless, the court applied illustration (a) and the evidence before it to award substantial but not the full claimed amount.

Holding and Implications

Final ruling: The appeal was allowed to the extent described and damages for the breach of contract were increased from the nominal sum awarded at trial to an award of Rs. 5,000. The respondents were ordered to pay the costs of the appeal. The memorandum of objections was dismissed with costs.

Implications:

  • The court applied section 73 of the Indian Contract Act together with illustration (a) to that section as the governing measure of damages in a "no market at place of delivery" case: i.e., damages are the amount by which the contract price falls short of the price at which the purchaser might have obtained goods of like quality at the time they ought to have been delivered.
  • The court reaffirmed the mitigation principle (that plaintiffs must take reasonable steps to minimize loss) but also recognised that where evidence of actual substitute purchase or precise market figures is imperfect, the court may, on available materials (including quotations from the defendant and other documentary evidence), make a reasonable quantified award rather than confine itself to nominal damages.
  • No new law was formulated; the decision follows and applies the statutory text and existing authorities (including Illustration (a) to s.73 and cited English and Judicial Committee cases) to the facts of the case. The direct effect is the grant of Rs. 5,000 in damages and costs to the plaintiffs; the opinion does not purport to set a novel precedent beyond applying the statute and the existing line of authorities to these facts.

Lawyers' firms recorded in the opinion: Short and Bewes & Co. for the appellants; King and Partridge for the respondents.

    Hajee Ismail v. Messes Wilson & Co.

    Wallis, C.J:— The plaintiffs in this case are a well-known firm carrying on business in Mysore and Madras. In 1913 they obtained from the Mysore Government the Abkād contract for Mysore and arranged with the defendants who carry on business in Madras that they should go on importing molasses for them in the same way as they had done for the previous holders of the contr Act. Admittedly the goods contracted for were intended for use by the plaintiffs in their factories at Bangalore. Owing to the disorganization of shipping consequent on the outbreak of the war at the beginning of August 1914, the defendants were unable to ship 800 tons from Java in the month of October 1914 as they were bound to do under their contract. This was a breach of contract for which admittedly they are bound so compensate the plaintiffs in damages, and the main question argued before the learned Judge and before us is as to the measure of damages. The learned Judge awarded the plaintiffs only nominal damages on the ground that they had failed to put before him the proper materials for estimating the damages, and the plaintiffs have appealed. The law as to this subject is to be found in section 73 of the Indian contract Act and the Explanation thereto. Under the body of the section the damages are to be those which naturally arise in the usual course of things from the breach or which the parties knew when they made the contract to be likely to result from the breach. By the Explanation, the means which existed of remedying the incovenience caused by the non-performance of the contract must be taken into account. The Explanation is in accordance with the decisions in Dunkirk Colliery v. Lever(1), and the decision of the House of Lords in British Westing House Electric and Manufacturing Company, Limited v. Underground Electric Railways Company of London, Limited(2). In that case Lord Haldane, L.C, observed:—

    “The fundamental basis is thus compensation for pecuniary loss naturally flowing from the breach; but this first principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach and debars him from claiming any part of the damage which is due to his neglect to take such steps.”

    The law was recently laid down to the same effect by the Judicial Committee in Jamal v. Moolla Dawood Sons and Co.(3). The rule that, where there is a market at the place of delivery, the damages are the difference between the contract price and the market price at the date of delivery may be regarded as an application of the principle embodied in the Explanation that the buyer must take the necessary steps to minimize the damage. Where there is a market and the seller has no notice of any contract entered into by the buyer, the market price in the case of failure to deliver is the test by which to estimate the value of the goods, independently of any circumstances peculiar to the buyer and so independently of any contract made by him for sale of the goods. This is the rule in Rodocanachi v. Milburn approved by the House of Lords in Williams Brothers v. Agius and applied by the Judicial Committee under the Indian contract Act in Jamal v. Moolla Dawood Sons and Co.. This is the rule in cases of non-delivery. It has recently been stated in the House of Lords that there is a difference where delivery is only delayed, but that is not the case here, and, also, we are bound by the terms of the Indian contract Act.

    When there is no market for the goods at the place of delivery, the buyer may procure a substitute at a higher cost if it is a reasonable and business like thing to do and calculated to diminish the loss, and may recover the difference in price as damages from the seller. It has not yet been decided that he is bound to do so and apparently he may refrain from doing so and rely on his claim for damages, See the observations of Lord Atkinson in Erie County Natural Gas and Fuel Company v. Carroll(4).

    Where there is no market, Mr. Mayne says:

    “the principle upon which the damages are to be assessed is exactly the same. They are to be taken at the value of the article at the date of breach. But the mode of estimating this value is different, for there is no market price which can be quoted.”

    Where the buyer was under a contract to resell, as in Borries v. Hutchinson(5), and Hinds v. Liddell(6) the resale price is evidence of the value of the goods at the place and time of delivery as observed by Mr. Mayne and as recently held in Stroms Bruks Aktie Bolag v. John and Peter Hutchinson(7), which approved the judgment of Blackburn, J., as he then was, in O'Hanlon v. G.W Ry. Co.(8), that the natural and fair measure of damages is the value of the goods at the time and place at which they ought to have been delivered to the owner, which I read as meaning the value of the goods to the owner of such goods at the time and place they ought to have been delivered. In that case also, the goods were intended for re-sale by the buyer.

    Where, as in the present case, the article is purchased not for sale but for use to the knowledge of the sellers, Mr. Mayne observes:

    “Damages will also be assessed with reference to its value to the purchaser. But its value will be determined by other considerations, that is to say, by the use for which it was intended, the loss which followed from its not being supplied, and the profit which would have been made out of it if it had been delivered in time.”

    In Portman v. Middleton, where the defendant failed to deliver a fire box, the plaintiff recovered the price and the extra cost of procuring a substitute but not the special damages of which the defendant had no notice. In Smeed v. Foord, the defendant who had failed to supply on the due date a threshing machine was held liable for the deterioration of the wheat owing to its being stacked and injured by rain as that was a natural consequence of the delay in supplying the machine according to the contract. In Gee v. Lancashire and Yorkshire Railway Co., as I read it, all that was ruled was that it could not be held as a matter of law that, the stoppage of the buyer's mills was a natural consequence of the seller's delay in delivering cotton under his contract. In Elbinger Actien-Gesellschafft v. Armstrong Blackburn, J., as he then was, delivering the judgment of the Court of Queen's Bench observed that

    “where, from the nature of the article, there is no market in which it can be obtained, the rule as to the difference of contract and market prices is inapplicable”

    and the plaintiffs were allowed to retain the damages awarded them as the reasonable result of the delay in delivery. We have not been referred to any case in which a different test was applied in the case of non-delivery as distinguished from late delivery of goods intended for use.

    As regards goods intended for resale where there is no market price at the place of delivery, in O'Hanlon v. G.W Ry. Co. (which was a case of non-delivery by a carrier, but that appears to make no difference) the value of the goods was arrived at by taking into account the wholesale price at the place of manufacture and adding to it the cost of carriage to the place of delivery and the profit which a hypothetical importer at the place of delivery might be expected to charge. This hypothetical market price is by no means so satisfactory a measure of damages as the real market price where it exists, and is only applicable in the absence of other evidence of value, such as the price at which the buyer had contracted to resell. It is especially unsatisfactory in cases like the present where it takes nearly a month from the date of order to procure the goods at the place of delivery. Logically, the price at the date when the goods would have had to be ordered so as to reach the place of delivery on the contract date would seem to be the price to be regarded, rather than the price at the contract date which the learned Judge has adopted; bat, in the case of goods purchased for use, whichever date be taken, and whether in the present case the price be taken at Calcutta, or at Java, damages assessed on this basis bear no real relation to the buyer's actual loss, and as in the present case, give him heavy damages where he has sustained no real loss. I think therefore there is much to be said in favour of adopting Mr. Mayne's rule, and have felt considerable doubt on the question. In this Court however we are governed by the Indian contract Act and illustration (a) to section 73 says that the measure of damages in this case is the sum by which the contract price falls short of the price for which the purchaser might have obtained goods of like quality at the time when they ought to be delivered.

    On a careful consideration of the question, I have not found sufficient reason for refusing to follow the rule laid down in the illustration which also appears from the latest edition of Sedgwick on Damages to be the accepted rule in America.

    In the present case the learned Judge finds, and I entirely agree with him, that the plaintiffs sustained no actual loss from the defendants' failure to ship the October consignment, as they were admittedly well stocked. They might therefore without any prejudice to themselves have accepted the defendants' offers to ship the October consignment along with the November consignment, or their subsequent offer about the 29th November to forward it by an early shipment in December. These considerations however are inapplicable if the rule in illustration (a) is to be strictly applied, as I think it should be.

    In arriving at the price for which the goods might have been obtained on the date of delivery, I entirely agree with the learned Judge that we should look prima facie at the cost of obtaining them from Java, and not from Calcutta which gets its supplies from Java, especially as the evidence is that the goods can be obtained as quickly from Java as from Calcutta. Obviously, the market price at Java would ordinarily be less than at Calcutta. It is quite clear that the shipping and insurance difficulties consequent of the outbreak of war in August 1914 must have caused an advance of the prices ruling in Java and Calcutta over those at which the plaintiffs purchased before the war. Exhibit G shows that the defendants were asking Rs. 2-9-3 per cwt., ex war risk on the 29th October 1914, about the time when the hypothetical dealer in Madras might be expected to purchase the goods in Java to have them ready in Madras on the 29th November which the learned Judge has fixed as the date of delivery in Madras. Though the plaintiffs have only tendered evidence as to the prices ruling in Calcutta, and the defendants have abstained from tendering any evidence on the subject, Mr. Chamier, for the plaintiffs, has put before us certain calculations from which he estimates the c.i.f Java Madras price on November 29th at Rs. 2-8-7 per cwt. This figure he arrived at by deducting the freight to Calcutta, as spoken to in evidence, and adding the freights from Java to Madras, but these are not proved to have been the prevailing freight either at the end of October or of November 1914, and I agree with the learned Judge that the c.i.f prices from Java are not accurately proved. I think therefore that Mr. Chamier is not entitled to judgment as claimed by him for Rs. 8,800 as the difference on 800 tons between Rs. 2-8-7 per cwt., his estimated c.i.f price from Java on the 29th November and the c.i.f contract price of Rs. 1-15-6 plus Rs. 250, importer's profit and Rs. 33 lading charges, in all Rs. 9,083. On the other hand, looking at the evidence as a whole, and especially at Exhibit G1, I think there is evidence from which I am justified in concluding that the hypothetical value of 800 tons in Madras at the end of November must have exceeded the c.i.f contract price by not less than Rs. 5,000. It is very likely that the figure would be higher if all the evidence were before us, but we are agreed that sum may safely be awarded on the evidence before us. I would accordingly allow the appeal and increase the damages to Rs. 5,000. The respondents will pay the costs of the appeal. The memorandum of objections is dismissed with costs.

    Sadasiva Ayyar, J.:— Plaintiffs are the appellants. The defendants under two contracts with the plaintiffs were bound to ship 800 tons of solid Java molasses in October 1914 at Java to arrive in Madras in November 1914, the plaintiffs to take delivery at Madras paying Rs. 1-15-6 per cwt. The defendants failed to make the October shipment and thus committed breach of the contract. The plaintiffs sue for recovery of (a) Rs. 23,000 alleged to be the difference “between the contract price and the market price” of the 800 tons of molasses in November 1914 when the molasses ought to have been delivered at Madras by the defendants, and (b) Rs. 2,725-15-6 being the sum paid under protest by the plaintiffs to the defendants owing to the illegal detention by the defendants of some other shipments under the contracts till that sum was paid to the defendants.

    The learned Judge on the Original Side gave a decree for the Rs. 2,725-15-6 claimed under the heading (b) on account of the sum paid under protest, but gave only Rs. 100 as nominal damages in respect of the Rs. 23,000, damages claimed under heading (a). Hence the plaintiffs have appealed under the Letters Patent, the appeal being valued at Rs. 21,000 evidently because the plaintiffs' contention in appeal is that the learned Judge on the Original Side ought to have given them Rs. 21,100 as damages instead of only Rs. 100 under the heading (a).

    As stated by my Lord in his judgment, the law as to this subject is to be found in the Indian contract Act, section 73, and in the illustrations thereto. The plaintiffs are, by the section, entitled to have

    “compensation for the loss or damage caused” to them “by the breach, the loss or damage being such as naturally arose in the usual course of things from such breach or which the parties knew when they made the contract to be likely to result from the breach of it.”

    Though there are 18 illustrations (a) to (r) appended to section 73, none of them refers in terms to a case where there is no market for the goods at the place of delivery mentioned in the contract. (Three of the illustrations namely, (e), (c) and (q) expressly refer to “market price” as one of the essential ingredients to be considered in arriving at the damages). If there was no illustration at all which could be reasonably held to govern the facts of this case and if the body of the section alone remained for consideration on the question of the amount of damages which the plaintiffs are entitled to, there seems much to be said in favour of the view that, as there is no market for the goods at the place of delivery, and as the pecuniary loss naturally flowing from such a breach cannot therefore be estimated with reference to the market price, the plaintiffs ought to prove that “damages” capable of calculation in some other reasonable manner naturally flowed and was sustained by them from such breach or prove (the second alternative mentioned in section 73) that both themselves and the defendants knew that some other damage was likely to result from the breach of the contract and the amount of such damage. This latter alternative right is, in my opinion, given by the section only as an additional right to that given by the clause which gives compensation for “the loss or damage which naturally arose in the usual course of things” from such breach, such additional right to be availed of at the plaintiffs' option.

    Assuming, as I said before, that none of the illustrations to the section throws any light on the dispute in this case in which there is no market for the goods at the place of delivery, I agree with my lord that the plaintiffs have not proved that any loss or damage naturally arising in the usual course of things from the breach of the plaintiffs' contract has been caused to them, nor (in the alternative) any loss or damage which both parties knew when they made the contract to be likely to result from its breach.

    The English cases (see Hinde v. Liddell and Elbinger Actien-Gesellschafft v. Armstrong no doubt decide that in such a case (which we might shortly call “no market case”) the damages must be calculated on the basis of the value fixed by the price which would actually have to be paid for the best and nearest available substitute. Some of the English cases, if I may say so with respect, use the expression “market-value” in a loose manner and lay down that the market-value for the calculation of damages must be ascertained in particular modes where there is no market at all for the goods at the place of delivery: see Wertheim v. Chicoutimi Pulp Company.

    I agree with Komabaswami Sastriyar, J., that the English and Indian cases do not lay down any inflexible rule that in estimating damages in “no market” cases that “one has to go to the place which is nearest to the place where the breach occurred” and where there is a market. I agree with him that

    “It is not the nearest market that always governs but the place where, having regard to all the facts of a particular case, the plaintiff would without any material inconvenience to himself procure the goods in a manner that would throw the least amount of hardship on the other party.”

    In the present case, it was to Java and not to Calcutta that the plaintiffs should have turned to if they really wanted to procure molasses as a substitute for the molasses contracted for.

    I further agree with Kumaraswami Sastriyar, J., that the fact that the plaintiffs did not make any purchase of molasses as a substitute for the molasses contracted for or that they have not proved that they suffered a pie of actual damage through the breach of contract does not disentitle them if the English and American law applies to this case from recovering the difference between the Java price in October 1914 plus the cost of carriage to Madras and the contract price. As I said already, it may be a question whether if the body of the section 73 stood alone, such a difference in a “no market” case could be treated as loss or damages arising naturally from the breach. I shall take an extreme case to illustrate what is in my mind, as extreme cases sometimes bring out clearly the principle in dispute. Suppose A at Madras wishes to bring up a wild animal found in Australia as a household pet; there being no market for such an animal at Madras, he enters into a contract with B of Australia through B's agent at Madras in March 1917 for delivery to him at Madras of the animal, the price to be Rs. 300 payable to B's agent at Madras on delivery in September 1917. B illegally repudiates the contract in July 1917 and thus commits a breach. If A had taken other steps in July or August 1917, be could have obtained a similar wild animal from Australia delivered at Madras in September at a cost of Rs. 500. A does not take any such steps but makes a demand for Rs. 200 as damages payable to him and he dies (say) three days after the date fixed for the delivery of the animal to him at Madras under the contract. A's sod and heir C does not himself care to have any such animal as a pet. Is C entitled to recover rupees 200 as damages from B for breach of the contract according to section 73 of the contract Act? Section 73, as I said before, speaks of loss or damage which naturally arose from such breach using the word ‘arose’ in the past tense. Can we say that Rs. 200 was the damage which had naturally arisen to A by his not having had a pet wild animal by him during the three days between the date fixed for delivery of the same under the contract and A's death or to A's son and heir by not having inherited a wild animal which be does not want? If, of course, he had tried to obtain a substitute and had obtained it at a cost of Rs. 500, the loss of Rs. 200 might be said to have naturally arisen. Apart from authority therefore and on the language of the body of the section 73 alone, I would be inclined to think that no damages at all can be claimed.

    But I think illustration (a) to section 73 authoritatively interprets what the legislature meant by the phrase “loss or damage which naturally arose in the usual course of things from a breach of the contract” in a “no market” case also. That illustration is as follows: “(a) A contracts to sell and deliver 50 maunds of saltpetre to B, at a certain price to be paid on delivery. A breaks his promise. B is entitled to receive from A, by way of compensation, the sum, if any, by which the contract price falls short of the price for which B might have obtained 50 maunds of saltpetre of like quality at the time when the saltpetre ought to have been delivered.” It will be seen that the language of the illustration is absolutely general and wide and it makes no exception on account of special circumstances like the following (a) a case where B could have used some other substitute for the saltpetre, (b) a case where B was made a gift of 50 maunds of saltpetre as substitute on the date fixed for delivery by A, (c) where there was no market at all for the saltpetre at the place of delivery. The law as stated in the illustration gives an unconditional right to B to get the difference between the contract price and the cost which he would have had to incur to obtain the like quantity of saltpetre with, of course, the least amount of hardship to A. I think this illustration is fully consistent with the English law as laid down in the House of Lords case Wertheim v. Chicontimi Pulp Company though that case was a case of breach by late delivery and not a case of no delivery at all. So also in Jugmohandas v. Nusserwanji Jenkins, C.J, and Chandavarkar, J., construe section 73 of the contract Act similarly—

    “There was no ready market rate. We, therefore, must have recourse to some other test.”

    And then the learned Judges consider all the facts including a statement prepared by the plaintiff himself in that case as to what he considered reasonable compensation from another party who committed a similar breach of contract with plaintiff. Where there are absolutely no materials not forward by the plaintiff to indicate what it would have cost him to obtain similar goods in the cheapest manner, it may be that only nominal damages would have to be allowed. But where there are some materials, the Court should, I think, as a jury try to arrive at the cost at which the plaintiff could have got other similar goods for the contracted date of delivery and give him the difference, if any, between that and the contracted price. In the present case, we have got the facts that the defendants themselves wrote the letter (Exhibit G) in October 1914 wherein they offer to deliver molasses at Rs. 2-9-3 per cwt in November. If we take that rate as the rate at which the plaintiffs would have been obliged to pay if they had attempted to obtain 800 tons or 16,000 cwts in substitute for the molasses contracted for, then the damages which they would be entitled to would be 16,000 × Rs. 2-9-3 − Rs. 1-15-6 (9 annas 9 pies or Rs. 9,750). But it appears that the plaintiffs themselves considered the price Rs. 2-9-3 as too high a quotation and that the price of molasses was probably rising even between the beginning of October and the end of October at Java.

    I might here remark that the plaintiffs might have let in evidence as to why they considered Rs. 2-9-3 as too high or what they considered as a fair price and the defendants might also have let in evidence as to how they arrived at the figure Rs. 2-9-3 and what the real price was of molasses at Java and what, with the freight and reasonable commission to importers the cost per cwt would have come to when delivered at Madras. I therefore agree with my Lord that under the circumstances Rs. 5,000 must be taken as a reasonable amount to be awarded to the plaintiff as damages in this case.

    I would in the result allow the appeal to the extent of this amount of Rs. 5,000 minus Ss. 100, nominal damages allowed under this head by the learned trial Judge with the costs of the appeal. The memorandum of objections is dismissed with costs.

    Short and Bewes & Co., Solicitors for Appellants.

    King and Partridge, Solicitors for respondents.

    K.R