R.H Zaidi, J.:— Heard learned counsel for the petitioner and Mr. Rajesh Tandon, Advocate, appearing for the respondent No. 3.
2. By means of this petition filed under Article 226 of the Constitution of India petitioner challenges the validity of the order dated 15.10.1993 whereby the suit filed by contesting respondent No. 3 was decreed by the trial Court and the judgment and order dated 18.7.2000 whereby the revision filed by the petitioner against the judgment and decree passed by the trial Court, was dismissed by the Court below.
3. It appears that plaintiff respondent filed a suit, which was decreed on 6.12.1983 for ejectment and recovery of rent. The said decree has become final. However, it has been stated that after the said decree was passed, parties entered into a compromise on the basis of which the petitioner was permitted to continue in occupation of the building in question. Thereafter it was on 3.12.1987 a notice of demand and termination of tenancy was served by the respondent upon the petitioner. It was claimed that the building in question was a new construction over which the provisions of the U.P Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972 (U.P Act No. XIII of 1972), for short the Act, had no application. The petitioner gave reply of the aforesaid notice controverting the facts stated therein. Thereafter, plaintiff respondent No. 3 filed a Suit No. 14 of 1988 for the above mentioned relief. The petitioner in the said suit filed his written statement controverting the facts stated in the plaint and denying the claim of the plaintiff respondent. The trial Court on the basis of the pleadings of the parties framed relevant issues.
4. Parties to the suit produced evidence, oral and documentary, in support of their cases. From the evidence on record, the trial Court came to the conclusion that the building in question was a new construction which was completed in the year 1980 (on 1.4.1980 being the date of first assessment) and that the provisions of the Act had no application over the building in question. Having recorded the said finding, the suit was decreed by the trial Court by its judgment and decree dated 15.10.1993 Challenging the validity of the said decree, the petitioner filed a revision before the Court below. The Court below affirmed the findings recorded by the trial Court and dismissed the revision by its judgment and order dated 18.7.2000 Hence, the present petition.
5. Learned counsel for the petitioner urged that in the earlier Suit No. 115 of 1982, the landlord respondent admitted that the building in question was constructed in the year 1978. The said admission was binding upon him, therefore, the Courts below had no jurisdiction to decide the date of completion of the construction of the building in accordance with clause (a) of Explanation I to sub-section (2) of Section 2 of the Act. The Courts below have erred in law in decreeing the suit and dismissing the revision filed by the petitioner, therefore, the judgments and decrees passed by the Courts below were liable to be set aside. Reliance in support of his submission is placed by learned counsel for the petitioner upon decision in Hriday Narain v. Maloo Lal Srivastava . 1986 12 ALR 131..
6. On the other hand, learned counsel appearing for the contesting respondent supported the validity of the judgment and decree passed by the Courts below. It was submitted that the date of completion of construction of the building in question was to be determined in accordance with the provisions of Section 2 and not on the basis of any other material. Reliance in support of this submission is being placed in Raj Kumar Sharma v. District Judge, Haridwar . 1993 22 ALR 38 Sum It was also urged that even if the period is counted from 1978, present suit was filed on 14.1.1988, even then 10 years were not completed and the suit filed by the plaintiff respondent was legally maintainable.
7. I have considered the submissions made by learned counsel for the parties and also perused the record.
8. The date of completion of construction is to be calculated/determined in accordance with clause (a) of Explanation I to sub-section (2) of Section 2 of the Act, which reads as under:—
“2. Exemptions from operation of Act.—(1) ….
(2) ………
Explanation 1.—For the purposes of this section,—
(a) the construction of a building shall be deemed to have been completed or otherwise recorded by the local authority having jurisdiction, and in the case of building subject to assessment, the date on which the first assessment thereof comes into effect, and where the said dates are different, the earliest of the said dates, and in the absence of any such report, record or assessment, the date on which it is actually occupied not including occupation merely for the purposes of supervising the construction or guarding the building under construction for the first time:
Provided that there may be different dates of completion of construction in respect of different parts of a building which are either designed as separate units or are occupied separately by the landlord and one or more tenants or by different tenants.”
9. The date of completion of construction, according to the findings recorded by the Courts below was 1.4.1980 which was the date of first assessment of the building in question subject to municipal assessment. This Court in Raj Kumar Sharma (supra) ruled as under:—
“19. If the language used in Explanation I to Section 2(2) of the Act is examined in the light of the principles indicated above, it will be apparent that the statutory fiction employed therein read with the use of the words ‘in the absence of any such report, record of assessment’ contained therein leave no manner of doubt that in the presence of an assessment of a building subject to assessment, only it is this date as one which has to be taken to be the date which furnishes the starting point for computing the period of exemption and the other factors such as the date of occupation etc. lose all significance. As a matter of fact the effect of the words ‘in the absence of’ as used in Explanation I to Section 2(2) was noticed by the Apex Court in its decision in the case of Om Prakash Gupta v. Digvijendra Singh,3 which was the case decided by a Bench of the three Hon'ble Judges of the Supreme Court. In that case, the building in question was shown to have been occupied on 16.6.1967, however, it was assessed for the first time on 1.4.1968 The question which had come for consideration was as to whether in the presence of the assessment dated 1.4.1968 the date of occupation of the building i.e, 16.6.1967 could be taken to be the date providing the starting point for computing the period of exemption. The Hon'ble Supreme Court while interpreting the explanation to Section 2(2) of the Act observed that primarily the language employed is the determining factor of the intention of the Legislature. It was further observed that the first and primary rule of construction is that the intention of the Legislature must be found in the words used by the Legislature itself. The Apex Court found that the language of sub-section (2) of Section 2 of the Act was implicit and unambiguous and further that it was not capable of two interpretations. Having come to the aforesaid conclusion, the Apex Court observed that the date of occupation could be taken to be the date of completion of the construction only when there was no report or record of the completion of the construction or no assessment thereof. Since in that the assessment was there it was held that the date of the first assessment was to be deemed to be the date of completion of the construction. It is obvious from a perusal of the aforesaid decision that in the presence of the first assessment the date of occupation of the building during the period anterior to the first assessment was held to be of no significance whatsoever.”
10. The aforesaid decision has been based on the decision of the Apex Court in Om Prakash Gupta v. Digvijendra Singh . 1982 8 ALR 242 SC.. In view of the decision of Supreme Court in Om Prakash Gupta's case (supra), the submission made by learned counsel for the petitioner, to the contrary, cannot be accepted. Further, even if we count the date of completion of construction from the date as was mentioned in paragraph 3 of the plaint of the earlier suit, which reads as follows:—
“3. That the portion in occupation of the defendant was constructed in 1978 and as such the same is beyond the purview of U.P Act No. 13 of 1972.”
the result would remain the same. In the said paragraph, the exact date of construction disclosed, only the year, i.e, 1978 was disclosed. The Suit No. 14 of 1988 was filed by the respondent, according to his own case on 14.01.1988, which was well within 10 years from the date/year given in paragraph 3 of the plaint. In view of the aforesaid facts. No case for interference under Article 226 of the Constitution of India is made out.
11. Lastly, learned counsel for the petitioner prayed that some reasonable time, to vacate the building in question may be granted to the petitioner. Learned counsel appearing for the contesting respondent has got no objection if six months' time is granted to the petitioner to vacate the building in question subject to the condition the petitioner furnishes an undertaking in writing before the Prescribed Authority within 15 days from today that immediately on expiry of the aforesaid time or before that he will vacate the building in question and hand over possession to the landlord, respondent No. 3.
12. In view of the aforesaid fact, it is hereby directed that for a period of six months from today the petitioner shall not be evicted from the building in question subject to the condition, the petitioner furnishes an undertaking in writing before the Prescribed Authority within a period of fifteen days from today to the effect that on the expiry of the aforesaid time or before that, he shall hand over vacant possession of the building in question to the landlord and shall also pay the rent for the building in question for the period he remains in occupation of the same. It is ordered accordingly.
13. Subject to what has been stated above, the writ petition fails and is hereby dismissed.
Petition Dismissed.