Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 23 of the Act, Section 4 (1)
  • Section 4 of the Land Acquisition Act
  • Section 18 of the Act
  • Section 54 of the Land Acquisition Act, 1894
  • Section 23(1) of the Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 24 of the Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 23 of the Act, Section 4 (1)
  • Section 4 of the Land Acquisition Act
  • Section 18 of the Act
  • Section 54 of the Land Acquisition Act, 1894
  • Section 23(1) of the Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 24 of the Act
Smart Summary

Factual and Procedural Background

The State Government of Maharashtra acquired land bearing Gat No. 85 measuring six acres in Village Mhasekot, Aurangabad District, in 1982 for the Hivra Medium Project. The Special Land Acquisition Officer (SLAO) passed an award on 1-9-1986 fixing total compensation at Rs 36,00,385.50 under various heads, including the value of land, trees, wells, structures, solatium and statutory additions.

Dissatisfied, the landowners (appellants) sought a reference under Section 18 of the Land Acquisition Act, 1894, claiming a market value of Rs 150 per sq. m. and higher compensation for their khandsari sugar factory’s structure, machinery and consequential loss of earnings. After trial, the Reference Court on 24-4-1996 enhanced compensation by:

  • Fixing land value at Rs 6 per sq. ft.
  • Awarding Rs 3,86,867 for demolition and dismantling of installations.
  • Awarding Rs 5,00,000 for loss of earnings (1981-1986).
  • Awarding additional sums for damages and transportation.

The State and beneficiary authorities (respondents) appealed under Section 54 to the Bombay High Court. The Division Bench partly allowed the appeal, restored the SLAO’s land valuation, disallowed most additional heads, and limited loss‐of‐earnings compensation to Rs 1,00,000.

The landowners filed the present civil appeal before the Supreme Court challenging the High Court’s reduction.

Legal Issues Presented

  1. Whether the High Court erred in rejecting the Reference Court’s determination of market value based on comparable sale instances and expert evidence.
  2. Whether the High Court correctly disallowed compensation for demolition, dismantling, damages, transportation and adequately compensated loss of business arising from closure of the khandsari factory.
  3. Whether the High Court’s approach conformed to principles laid down by the Supreme Court governing assessment of market value, escalation, and development deductions under the Land Acquisition Act, 1894.

Arguments of the Parties

Appellants' Arguments

  • The acquired land had non-agricultural potential and was already partially used for a khandsari factory; therefore the market value should be Rs 150 per sq. m. (≈ Rs 14 per sq. ft.).
  • Comparable sale deeds (Exhs. 23 & 35) supported a higher rate; the Reference Court’s Rs 6 per sq. ft. was reasonable and ought not to be disturbed.
  • They incurred substantial loss due to compulsory closure of the factory and were entitled to compensation for loss of earnings, demolition, dismantling, damages to civil structures, machinery and transportation.

Respondents' Arguments

  • The SLAO’s original award correctly reflected agricultural value; the Reference Court’s enhancement was excessive and based on incomparable sales.
  • No statutory basis existed for granting the large sums awarded for factory-related heads and for prolonged loss of business.
  • The High Court rightly restored the SLAO’s valuation and curtailed additional amounts.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Thakarsibhai Devjibhai v. Executive Engineer (2001) 9 SCC 584 Distance between exemplar land and acquired land is not decisive if quality and potentiality are similar; burden on State to show dissimilarity. Used to criticise the High Court’s summary rejection of sale deeds solely on ground of distance.
Viluben Jhalejar Contractor v. State of Gujarat (2005) 4 SCC 789 Comprehensive guidelines for determining market value: willing buyer–seller test, comparable sales, positive/negative adjustment factors, development deductions (20–50%). Cited as governing law that the High Court failed to apply while reassessing compensation.
Atma Singh v. State of Haryana (2008) 2 SCC 568 Definition of “market value”; objective assessment ignoring vendor’s reluctance or purchaser’s urgency; hypothetical willing buyer–seller framework. Referenced to emphasise correct methodology for valuation which the High Court overlooked.
Subh Ram v. State of Haryana (2010) 1 SCC 444 Recent pronouncement reiterating principles of escalation and development deductions. Cited illustratively; Court directed High Court to apply these principles on remand.
A.P. Housing Board v. K. Manohar Reddy (2010) 12 SCC 707 Further elucidation of market-value assessment, escalation and deductions. Cited illustratively; to be considered by High Court on fresh hearing.

Court's Reasoning and Analysis

The Supreme Court examined the pleadings, evidence and competing awards and found multiple errors in the High Court’s approach:

  • Improper rejection of comparable sales: The High Court dismissed sale deeds (Exhs. 23 & 35) by stating the properties were “at a considerable distance” without analysing their qualitative comparability, contrary to the rule in Thakarsibhai Devjibhai.
  • Failure to evaluate evidence: The High Court undertook no detailed scrutiny of oral testimony (especially PW-2, an approved valuer) or documentary proof regarding non-agricultural use, factory location, and market potential of the land.
  • Disregard of established principles: It neglected the Supreme Court’s recent jurisprudence (Viluben Jhalejar, Atma Singh, Subh Ram, A.P. Housing Board) on market-value determination, escalation for time gap between notification and award, and deductions for development, resulting in a decision “contrary to law”.
  • Inadequate reasons for reducing special damages: The Court criticised the High Court for cutting compensation for demolition, dismantling, transportation and loss of business without cogent reasoning, despite uncontroverted expert evidence and the State’s failure to rebut it.
  • Lack of State evidence: The respondents produced no substantive material to sustain the SLAO’s lower valuation, and DW-1’s testimony was deemed irrelevant by the Reference Court; the High Court ignored this evidentiary void.

Given these deficiencies, the Supreme Court concluded that a fresh appraisal by the High Court, guided by settled law, was necessary.

Holding and Implications

Holding: The appeal is ALLOWED; the Bombay High Court’s judgment is set aside and the matter is remitted to the High Court for de novo consideration of the State’s appeal in accordance with the principles laid down by the Supreme Court.

Implications: The decision restores the Reference Court’s award only temporarily; final compensation awaits the High Court’s fresh determination. While no new legal rule is announced, the Supreme Court reinforces that appellate courts must (i) conduct a thorough evaluation of evidence, (ii) apply the established guidelines on comparable sales, escalation and development deductions, and (iii) furnish cogent reasons when varying compensation under the Land Acquisition Act.

To access the original judgment, please Sign In or Subscribe.

    Gajanan And Others v. State Of Maharashtra And Another

    Judgment

    1. This appeal is directed against the judgment of the Bombay High Court whereby the appeal preferred by the respondents under Section 54 of the Land Acquisition Act, 1894 (for short “the Act”) was partly allowed and the amount of compensation determined by the Civil Judge, Senior Division, Aurangabad (hereinafter described as “the Reference Court”) was substantially reduced.

    2. The appellants' land comprised in Gat No. 85 measuring 6 acres situated in Mhasekot Village, Aurangabad District was acquired by the State Government in 1982 for Hivra Medium Project. By an award dated 1-9-1986, the Special Land Acquisition Officer directed the respondents to pay compensation amounting to Rs 36,00,385.50 to the appellants under the following heads:

    1. True area of the land acquisition 133.42 H.R 2. The compensation of dry land Rs 13,36,440.00 3. Valuation of trees Rs 83,071.25 4. Valuation of wells Rs 2,00,811.00 5. (a) Agricultural lands of S. No. 85 @ Rs 9500 H.R 1-60 (b) NA land of S. No. 85 O-80 @ Rs 20,000 (c) Building valuation (d) Damages and shifting charges Rs Rs Rs Rs 15,200.00 16,000.00 3,67,100.00 2,11,000.00 6. Total compensation Rs 1,65,522.25 7. 30% Solatium Rs 5,95,456.70 8. 12% enhancement of compensation on market value w.e.f notification under Section 4 Rs 8,75,306.50 9. Total amount of compensation Rs 36,00,385.50

    3. Feeling dissatisfied with the quantum of compensation, the appellants filed an application under Section 18 of the Act and claimed that the market value of the acquired land is Rs 150 per square metre. They also claimed higher compensation for the civil structure, machinery, electrical and mechanical installations of the khandsari factory which they had established on a portion of the land. The respondents filed reply to contest the appellants' claim for higher compensation and pleaded that the award made by the Special Land Acquisition Officer was legally correct and justified.

    4. On the pleadings of the parties, the Reference Court framed the following issues:

    “1. Whether the claimant proves that the valuation made by LAO is improper, inadequate and not as per the market value?
    2. Whether the claim petition is in limitation?
    3. Whether the claimant proves that he accepted the compensation amount under protest? If not, what is its effect?
    4. Whether the claimant is entitled to additional amount of compensation claimed?
    5. What order?”

    5. After considering the pleadings of the parties and evidence produced by them, the Reference Court passed an order dated 24-4-1996 and determined the amount of compensation as under:

    (i) Market value of the acquired land (total measuring) at the rate of Rs 6 per square foot.
    (ii) Rs 3,86,867 towards demolition and dismantling of electrical, mechanical and other installations.
    (iii) Rs 5,00,000 towards loss of earning for the period from 1981 to 1986.
    (iv) Rs 91,000 towards damages and dismantling charges.
    (v) Rs 15,000 towards transportation charges.

    The Reference Court also declared that the appellants are entitled to solatium, interest, etc.

    6. The Division Bench of the High Court partly allowed the appeal preferred by the respondents, set aside the determination of market value made by the Reference Court and restored the one made by the Special Land Acquisition Collector. The High Court also quashed the compensation awarded by the Reference Court towards demolition and dismantling charges, damages to the structure and machinery of the factory and transportation charges. As regards the loss of earning, the High Court held that the appellants are entitled to Rs 1,00,000 for the loss of earning for one year instead of Rs 5,00,000.

    7. We have heard the learned counsel for the parties and carefully perused the record. It is borne out from the record that out of the total acquired land, the appellants had utilised 0.80 ha in 1976 for establishing khandsari factory. As a sequel to initiation of the acquisition proceedings, the appellants had to close the factory. The Reference Court referred to the statement of PW 2, Mukund Dharashivkar, a consulting engineer-cum-approved valuer and held that while the appellants had been able to prove that as a result of the acquisition of land, they had to close the khandsari factory and suffered huge financial loss, the State did not adduce any evidence on the issue of loss of business and damage to the structure, machinery and electric and mechanical installation and that the statement made by DW 1, Nilkanth Tukaram Bhosale was not at all relevant. The discussion on this issue is contained in paras 19 to 41 of the order of the Reference Court.

    8. The Reference Court then referred to the sale instance, Ext. 23 by which land measuring 30 × 32 ft was sold in 1976 for a sum of Rs 3000 and another sale instance, Ext. 35 by which 5023 sq ft land was sold in 1982 for a sum of Rs 35,000 and observed:

    “46. The certified copy of the sale instance produced at Ext. 23 is in respect of Mauza Gondegaon which is of the year 1976 and does have evidentiary value which was in respect of land admeasuring 32′ × 30′ for a consideration of Rs 3000. It is contended that the price of Gat No. 85 is decided on the basis of agricultural land in respect of 80 R which was used for construction of khandsari sugar mill in respect of which the petitioner obtained non-agricultural permission from the authority concerned. The remaining portion of 1 ha 60 R was also used as non-agricultural land. As per valuation of PW 2 Dharashivkar, 5 to 6 acres of land is required for khandsari sugar mill in order to store fuels, sugarcane and other allied purposes. This fact also has been admitted on behalf of the State, hence, there is no manner of doubt that 1 ha 60 R of land would also have fetched more value at the rate of NA assessment. But the learned SLAO has given the price on the basis of agricultural land in respect of sale in view of the fact that no actual permission was obtained by the petitioner, in respect of 1 ha 60 R of land which as per the learned counsel for the petitioner should have been considered non-agricultural land because of its long use and not taking of crops on the said field.
    47. The petitioner in order to prove the price of non-agricultural open plot, placed reliance on the sale deed, Ext. 35 in which 5023 sq ft of land was sold at Rs 35,000 in the year 1982 in respect of land situated at Jargaon which is at a distance of 2 km from Mhasekote. However nothing was said by the petitioner in his cross-examination regarding the non-consideration of this land for the purpose of determining the valuation or compensation. Thus, the entire Gat No. 85 having been used by the petitioner for the production of sugar and its allied purposes, the entire land was utilised for non-agricultural purpose.
    48. There is nothing on the record to show that the rest of the land of 1 ha 60 R was used for agricultural purpose. This fact appears to have been not considered by the SLAO. Moreover, the factory was situated on State highway going from Pachora to Sillod and railway station of Pachora is at a distance of just 11 km from the factory. Hence looking into its use and situation of the factory in the suit along with other vital factors, the SLAO was duty-bound to consider the value of the suit land in respect of its non-agricultural use.
    51. Thus, if Gat No. 85 admeasuring 2 ha 40 R i.e 6 acres, if converted into guntas, it comes to 240 guntas. One gunta comes to 1089 sq ft. If this 1089 sq ft is multiplied by 240 guntas, then it comes to 2,61,360 sq ft and by deducting 10% of the land from the above area, it comes to 2,35,224 sq ft. Thus, the value at the rate of Rs 6 per square foot for 2,35,224 sq ft comes to Rs 14,11,344.
    52. In the instant case, the notification appears to be of the year 1981 and the award came to be passed in the year 1986. Thus, after six years from the passing of the notification, the award was passed. The land of 960 sq ft of Village Gondegaon as per Ext. 23 was sold at Rs 3000. Thus, the rate was nearly between Rs 3 to 4 per square foot. Taking this rate into consideration from Rs 3 per square foot, the rate of Rs 6 per square foot in the instant case would not be exorbitant in light of the submissions made in that behalf accompanied by the report of the valuer, Ext. 21 as laid down in 1993 BCJ p. 27 even though no formal permission for NA purpose was granted by the authority concerned.”

    9. On the issue of valuation of the structure of the factory, plant and machinery and loss of business, the Reference Court observed:

    “55. During the course of cross-examination of Mr Gulwe, it was admitted by him that the valuation which has been shown to him in respect of electrical and mechanical establishments were taken into consideration by him in the valuation report given by the petitioner himself to the government approved valuer. It is further admitted by him that dismantling charges were granted by him on the valuation report of Mr Dharashivkar. It is further admitted by him that the Executive Engineer had come along with him on the site for inspection. The entire report was based on the valuation given by the petitioner but he had not specifically given the valuation of the machinery on the premises of the factory. It is further admitted by him that the valuation of the machinery cannot be given by the State but the valuation of dismantling charges is sustainable. It is further admitted by him that he had only given the valuation in respect of civil and no valuation in respect of electrical and mechanical establishments was done.
    56. The valuation certificate given by PW 2 Dharashivkar is placed at Ext. 21. Thus, it appears from the record that as per the project report that was initially prepared in the year 1976 the cost of factory installation was given at Rs 6,98,677 and as per the award it has been given Rs 5,78,100. The petitioner-plaintiff has claimed Rs 91,000 towards dismantling costs and damages and Rs 15,000 towards transportation and loading and unloading. Even though the costs of Rs 6,98,677 was initially claimed in the project report, the project report is dated 1974-1975. Thus, by the time the award was pronounced, there would have been depreciation of 10% in the valuation of the machineries. Thus, the value recorded by the SLAO regarding these machineries to the tune of Rs 5,78,100 which has also been admitted by the Executive Engineer needs to be accepted as there was no vital dispute on this point. As a matter of fact, whatever entire claim made by the petitioner on the basis of purchase made by him does not sustain in law, the same was properly assessed by the State as per the project report but it only mentions about the building valuation and damages and shifting charges, but does not mention about the demolition and dismantling charges in respect of electrical, mechanical and machinery installation which comes to Rs 1,29,267, 1,25,300 and 1,32,300 respectively. Thus, cumulatively, the petitioner is entitled to get Rs 3,86,867.
    57. As regards the loss in business sustained by the petitioner due to acquisition by the respondent, it has been requisitioned at Rs 2 lakhs per year as net income for a period of 20 to 25 years. As per the expert, who is a government approved valuer, PW 2 Dharashivkar whose evidence has not been completely shattered on the point of valuation of the factory, and so also as regards the valuation of structure and machinery, so also the valuation of Executive Engineer, DW 3 Gulwe to some extent admitted the report given by Dharashivkar. Hence in order to support the factum that the evidence given by the assessor and valuer as per Ext. 21 needs to be taken into consideration.”

    10. The Division Bench of the High Court did not make an in-depth evaluation of the pleadings and evidence produced by the parties and rejected the two sale instances by making a cryptic observation that the lands were situated at a considerable distance. While doing so, the High Court ignored the law laid down by this Court in Thakarsibhai Devjibhai v. Executive Engineer (2001) 9 SCC 584 the relevant portions of which are extracted below:

    “12. … So far as the other question of distance between the two classes of lands is concerned, that by itself cannot derogate the claim of the claimant unless there are some such other materials to show that quality and potentiality of such land is inferior. However, distance between the land under Ext. 16 and the present land, even if they are 5 km apart, would not be relevant, the relevancy could be, their distances from Viramgam Town. We find, as per the map produced by the State, the present acquired land is about 3 km away from it, while the land under Ext. 16 is about 2 km away from it. This difference is not such as to lead to reduce the rate of compensation, specially on the facts of this case. In the present case, as we have recorded above, it has been found that the quality including potentiality of land between Ext. 16 and the present one are similar. No evidence has been led on behalf of the State to find any difference between the two. In view of this, the inference drawn by the High Court for reducing the compensation by Rs 10 per square metre cannot be sustained.”

    Indeed, the respondents had not adduced any other evidence which could be relied upon by the Reference Court for approving the determination of market value made by the Special Land Acquisition Officer.

    11. We are further of the view that the judgment of the High Court runs contrary to the law laid down by this Court in recent judgments including Viluben Jhalejar Contractor v. State of Gujarat (2005) 4 SCC 789, Atma Singh v. State of Haryana (2008) 2 SCC 568, Subh Ram v. State of Haryana (2010) 1 SCC 444 and A.P Housing Board v. K. Manohar Reddy (2010) 12 SCC 707. In Viluben Jhalejar Contractor v. State of Gujarat (2005) 4 SCC 789, this Court laid down the following principles for the determination of the market value of the acquired land:

    “17. Section 23 of the Act specifies the matters required to be considered in determining the compensation; the principal among which is the determination of the market value of the land on the date of the publication of the notification under sub-section (1) of Section 4.
    18. One of the principles for determination of the amount of compensation for acquisition of land would be the willingness of an informed buyer to offer the price therefor. It is beyond any cavil that the price of the land which a willing and informed buyer would offer would be different in the cases where the owner is in possession and enjoyment of the property and in the cases where he is not.
    19. Market value is ordinarily the price the property may fetch in the open market if sold by a willing seller unaffected by the special needs of a particular purchase. Where definite material is not forthcoming either in the shape of sales of similar lands in the neighbourhood at or about the date of notification under Section 4(1) or otherwise, other sale instances as well as other evidences have to be considered.
    20. The amount of compensation cannot be ascertained with mathematical accuracy. A comparable instance has to be identified having regard to the proximity from time angle as well as proximity from situation angle. For determining the market value of the land under acquisition, suitable adjustment has to be made having regard to various positive and negative factors vis-à-vis the land under acquisition by placing the two in juxtaposition. The positive and negative factors are as under:

    Positive factors Negative factors (i) smallness of size (i) largeness of area (ii) proximity to a road (ii) situation in the interior at a distance from the road (iii) frontage on a road (iii) narrow strip of land with very small frontage compared to depth (iv) nearness to developed area (iv) lower level requiring the depressed portion to be filled up (v) regular shape (v) remoteness from developed locality (vi) level vis-à-vis land under acquisition (vi) some special disadvant-ageous factors which would deter a purchaser (vii) special value for an owner of an adjoining property to whom it may have some very special advantage

    21. Whereas a smaller plot may be within the reach of many, a large block of land will have to be developed preparing a layout plan, carving out roads, leaving open spaces, plotting out smaller plots, waiting for purchasers and the hazards of an entrepreneur. Such development charges may range between 20% and 50% of the total price.”

    12. In Atma Singh v. State of Haryana (2008) 2 SCC 568, the Court held:

    “4. In order to determine the compensation which the tenure-holders are entitled to get for their land which has been acquired, the main question to be considered is what is the market value of the land. Section 23(1) of the Act lays down what the court has to take into consideration while Section 24 lays down what the court shall not take into consideration and have to be neglected. The main object of the enquiry before the court is to determine the market value of the land acquired. The expression ‘market value’ has been the subject-matter of consideration by this Court in several cases. The market value is the price that a willing purchaser would pay to a willing seller for the property having due regard to its existing condition with all its existing advantages and its potential possibilities when led out in most advantageous manner excluding any advantage due to carrying out of the scheme for which the property is compulsorily acquired. In considering market value disinclination of the vendor to part with his land and the urgent necessity of the purchaser to buy should be disregarded. The guiding star would be the conduct of hypothetical willing vendor who would offer the land and a purchaser in normal human conduct would be willing to buy as a prudent man in normal market conditions but not an anxious dealing at arm's length nor facade of sale nor fictitious sale brought about in quick succession or otherwise to inflate the market value. The determination of market value is the prediction of an economic event viz. a price outcome of hypothetical sale expressed in terms of probabilities.”

    13. Another error committed by the High Court is that while reducing the amount of compensation, it did not keep in view the rules evolved by this Court for giving the benefit of escalation in land prices to the landowners and making appropriate deduction towards development cost whenever it is pleaded by the acquiring authority or the beneficiary that it will have to spend substantial amount for making the land useful for the purpose for which it is acquired. Yet another error committed by the High Court is that it did not assign any cogent reasons for reducing the amount of compensation in lieu of the loss of business and in lieu of the damage to structure, plant and machinery, etc.

    14. In the premise aforesaid, we feel that the ends of justice will be served by remitting the matter to the High Court for fresh disposal of the appeal filed by the respondents.

    15. In the result, the appeal is allowed. The impugned judgment is set aside and the matter is remitted to the High Court for fresh disposal of the appeal filed by the respondents. It is needless to say that while deciding the appeal afresh, the High Court will take into consideration the law laid down by this Court in recent judgments including those referred to hereinabove.