  • Article 181 of the former [Limitation Act, 1908]
  • Article 137 of the Limitation Act, 1963
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Arbitration and Conciliation Act, 1996 (Section 16(1)(b))
  • Section 20 of the Act of 1963
  • Section 28 of the Contract Act
  • The Arbitration Act, 1940
  • Section 8 of the Arbitration Act, 1940
  • Section 8 of the Act
  • Section 2(a) of the Act
  • Uncitral Model Law on International Commercial Arbitration (Article 16(1))
  • Section 37 of the Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
008 INSC 1482
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Article 181 of the former [Limitation Act, 1908]
  • Article 137 of the Limitation Act, 1963
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Arbitration and Conciliation Act, 1996 (Section 16(1)(b))
  • Section 20 of the Act of 1963
  • Section 28 of the Contract Act
  • The Arbitration Act, 1940
  • Section 8 of the Arbitration Act, 1940
  • Section 8 of the Act
  • Section 2(a) of the Act
  • Uncitral Model Law on International Commercial Arbitration (Article 16(1))
  • Section 37 of the Act
Smart Summary

Factual and Procedural Background

The respondent (Irrigation Department) awarded the appellant (contractor) a tendered contract on 9-2-1988 for canal excavation at an agreed price of Rs 21,10,233. The work was to finish by 8-1-1989 but was successively extended to 30-9-1990, when it was completed. Measurements were recorded on 26-11-1990 and the final bill, paid on 4-12-1990, was accepted by the appellant without objection.

On 27-2-1991, claiming to have executed extra items of work, the appellant demanded additional payment. After further correspondence (10-6-1991, 26-9-1991) the Executive Engineer rejected the claims on 5-10-1991, stating they were time-barred because they were raised beyond 30 days after the defect-liability period (which expired on 31-5-1991). The Superintending Engineer, by minutes dated 30-12-1991, likewise rejected the request for arbitration.

The Chief Engineer, by letter dated 26-2-1992, also refused to appoint an arbitrator. The appellant then applied under Section 8 of the Arbitration Act, 1940 before the Civil Judge (Senior Division), Ahmednagar, who on 9-12-1997 appointed a sole arbitrator. The High Court, in Civil Revision Application No. 201/1998, set aside that order on 13-4-2004; review was refused. The present appeal is against the High Court’s decision. Leave to appeal was granted by the Supreme Court.

Legal Issues Presented

  1. Whether Clauses 54 and 55 of the contract permitted the contractor to invoke arbitration after completion of the contract and acceptance of the final bill.
  2. Whether the contractor’s demand for arbitration was barred because it was not made within 30 days after expiry of the defect-liability period.
  3. Whether the civil court, exercising power under Section 8 of the Arbitration Act, 1940, could appoint an arbitrator when the contractual pre-conditions for arbitration were allegedly unmet.

Arguments of the Parties

Appellant's Arguments

  • The contractual time-limit in Clause 54 does not apply in the present circumstances; therefore the request for arbitration was timely.
  • Because the appellate authority finally rejected the claims only on 26-2-1992, the 30-day period should run from that date.
  • Under Section 8 of the Act the court need decide only whether a triable issue exists, not the merits of the claim.
  • Once a triable issue is found, courts must refer the matter to arbitration without examining the substantive validity of the claims.

Respondent's Arguments

  • Clause 54 must be invoked during the currency of the contract; after completion and acceptance of the final bill the arbitration agreement expires.
  • By accepting the final bill without protest the contract—and with it the arbitration clause—stood extinguished.
  • The appellant neither invoked Section 37(4) of the Act nor showed sufficient cause for extension, so even a court could not enlarge time for arbitration.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Vulcan Insurance Co. Ltd. v. Maharaj Singh (1976) 1 SCC 943 Validity of contractual time-limits and their coexistence with Article 137 Limitation Act. Used to affirm that contractual limitation clauses are not invalid under Section 28 of the Contract Act.
Scott v. Avery (1843-60) All ER Rep 1 Effect of clauses that stipulate arbitration as a condition precedent to suit. Cited to distinguish situations where a dispute is outside the arbitration clause.
Baroda Spg. & Wvg. Co. Ltd. v. Satyanarayen Marine & Fire Insurance Co. Ltd. (ILR 38 Bom 344) Contractual time-limit clauses not hit by Section 28 of Contract Act. Relied upon in the discussion of Vulcan Insurance.
Dawood Tar Mahomed Bros. v. Queensland Insurance Co. Ltd. AIR 1949 Cal 390 Same principle as above. Referenced along with Vulcan Insurance.
Ruby General Insurance Co. Ltd. v. Bharat Bank Ltd. AIR 1950 EP 352 Same principle as above. Referenced along with Vulcan Insurance.
A.B.C Laminart (P) Ltd. v. A.P Agencies (1989) 2 SCC 163 Enforceability of contractual limitation clauses. “See also” reference supporting the same line of reasoning.
Damodar Valley Corporation v. K.K. Kar (1974) 1 SCC 141 Accord and satisfaction does not necessarily extinguish arbitration clause. Quoted but distinguished from present case.
Heyman v. Darwins Ltd. (1942 AC 356) Relationship between termination of contract and survival of arbitration clause. Referenced within discussion of Damodar Valley.
S.C. Konda Reddy v. Union of India AIR 1982 Kant 50 Accord and satisfaction and arbitration. Cited as additional authority; not central to ratio.
BHEL v. Amar Nath Bhan Prakash (1982) 1 SCC 625 Whether discharge by accord is itself arbitrable. Court held it not applicable because present issue concerns time-bar, not accord.
Bharat Coking Coal Ltd. v. Annapurna Construction (2003) 8 SCC 154 Arbitrator’s jurisdiction confined to contract terms. Used to interpret effect of earlier cases and limit arbitrator’s power.
NTPC Ltd. v. Reshmi Constructions (2004) 2 SCC 663 Need only show triable issues at Section 8 stage. Cited but distinguished; court noted different fact situation.
Union of India v. Kishorilal Gupta & Bros. AIR 1959 SC 1362 Doctrine of separability of arbitration agreement. Referred to in discussing survival of arbitration clauses.
Naihati Jute Mills Ltd. v. Khyaliram Jagannath AIR 1968 SC 522 Same as above. Cited within NTPC discussion.
Buckeye Check Cashing Inc. v. Cardegna, 546 US 460 (2005) Separability rule in U.S. arbitration law. Illustrative comparison to modern approach; distinguished on facts.
Prima Paint Corp. v. Flood & Conklin, 388 US 395 (1966) Origin of separability doctrine. Cited in same context as Buckeye.
Southland Corp. v. Keating, 465 US 1 (1984) Federal substantive arbitration law and separability. Cited in same context as Buckeye.
Wild Life Institute of India v. Vijay Kumar Garg (1997) 10 SCC 528 Clause that extinguishes liability if claim not made within 90 days after final bill. Relied on to support view that such clauses operate as extinguishing, not mere limitation clauses.
P.K. Ramaiah & Co. v. NTPC (1994 Supp (3) SCC 126) Earlier precedent on similar contractual clauses. Distinguished; effect re-examined in Bharat Coking Coal case.

Court's Reasoning and Analysis

The Court first examined Clauses 37, 54 and 55 of the contract and found that the arbitration clause is of limited scope: it can be invoked only if the contractor raises a contemporaneous dispute during execution of the work and follows the sequential procedure (Executive Engineer → Appellate Authority → arbitration request within 30 days).

The appellant raised no claim until after completion, final measurements and payment. Clause 54, on its plain wording, “does not envisage raising of a claim … after the completion of contract.” Because the defect-liability period ended on 31-5-1991, the latest date for invoking arbitration was 30-6-1991; notices sent thereafter were time-barred.

While Article 137 of the Limitation Act applies to court applications, the contractual 30-day stipulation is a valid substantive bar under Section 28 of the Contract Act. Precedents such as Vulcan Insurance and Wild Life Institute were cited to affirm the validity of extinguishing clauses.

The doctrine of separability was acknowledged, but the Court clarified that separability cannot revive an arbitration clause when the contract itself makes timely invocation a condition precedent. Accord-and-satisfaction cases (Damodar Valley, NTPC Ltd.) were inapposite because the dispute here concerns expiration of the contractual right, not settlement of the claim.

Consequently, the civil court’s order appointing an arbitrator was beyond jurisdiction; the High Court correctly set it aside. Section 37(4) of the Act could not salvage the claim because the appellant neither invoked it nor showed cause for extension.

Holding and Implications

APPEAL DISMISSED – High Court judgment affirmed.

Immediate Effect: No arbitrator will be appointed; the contractor cannot pursue these claims through the contractual arbitration mechanism.
Broader Implications: The decision reinforces the enforceability of contractual clauses that require disputes to be raised and arbitration invoked within strictly defined periods, and clarifies that separability of an arbitration clause does not override explicit temporal conditions agreed by the parties.

To access the original judgment, please Sign In or Subscribe.

    P. Manohar Reddy & Bros. v. Maharashtra Krishna Valley Development Corporation And Others

    S.B Sinha, J.— Leave granted.

    2. The respondent herein invited tenders for the work of excavation in canal, K.M No. 126, Kukadi Left Bank Canal, Shrigonda in the district of Ahmednagar at an estimated cost of Rs 23,26,424 pursuant whereto the appellant herein submitted its offer for a sum of Rs 21,10,233. The said offer being the lowest was accepted.

    3. The parties hereto thereafter entered into a contract on 9-2-1988, Clauses 37, 54 and 55 whereof read as under:

    “37. After completion of work and prior to that payment, the contractor shall furnish to the Executive Engineer, a release of claims against the Government arising out of the contract, other than claims specifically identified, evaluated and expected from the operation of the release by the contractor.
    54. Settlement of dispute (for works costing less than Rs 50 lakhs).—If the contractor considers any work demanded of him to be outside the requirements of the contract, or considers any drawings, record or ruling of the Executive Engineer, KIP, Division No. VII, Shrigonda on any matter in connection with or arising out of the contract or the carrying out of work to be outside the terms of contract and hence unacceptable, he shall promptly ask the Executive Engineer, in writing, for written instructions or decision. Thereupon the Executive Engineer, shall give his written instructions or decision within a period of 30 days of such request.
    Upon receipt of the written instructions or decision the contractor shall promptly proceed without delay to comply with such instructions or decision.
    If the Executive Engineer fails to give his decision in writing within a period of 30 days after being requested, or if the contractor is dissatisfied with the instructions or decision of the Executive Engineer, the contractor may within 30 days after receiving the instructions or decision, appeal to the upward authority who shall afford an opportunity to the contractor to be heard and to offer evidence in support of his appeal.
    If the contractor is dissatisfied with this decision, the contractor within a period of thirty days from receipt of the decision shall indicate his intention to refer the dispute to arbitration as per Clause 55 failing which the said decision shall be final and conclusive.
    55. Arbitration (for works costing less than Rs 50 lakhs).—All the disputes or differences in respect of which the decision has not been final and conclusive as per Clause 54 above shall be referred for arbitration to a sole arbitrator appointed as follows:
    Within 30 days of receipt of notice from the contractor or his intention to refer the dispute to arbitration the Chief Engineer (SP, Irrigation Department), Pune shall send to the contractor a list of three officers of the rank of Superintending Engineers or higher, who have not been connected with the work under this contract. The contractor shall within 15 days of receipt of this list select and communicate to the Chief Engineer, the name of one officer from the list who shall then be appointed as the sole arbitrator. In case the contractor fails to communicate this selection of name within the stipulated period, the Chief Engineer shall without delay select one officer from the list and appoint him as the sole arbitrator. If the Chief Engineer fails to send such a list within 30 days as stipulated, the contractor shall send a similar list to the Chief Engineer within 15 days. The Chief Engineer shall then select one officer from the list and appoint him as the sole arbitrator within 15 days. If the Chief Engineer fails to do so, the contractor shall communicate to the Chief Engineer the name of one officer from the list who shall then be the sole arbitrator.
    The arbitration shall be conducted in accordance with the provisions of the Arbitration Act, 1940 or any statutory modification thereof. The arbitrator shall determine the amount of costs to be awarded to either parties.
    Performance under the contract shall continue during the arbitration proceedings and payments due to the contractor shall not be withheld unless they are subject-matter of the arbitration proceedings.
    All awards shall be in writing and in case of award amounting to rupees one lakh and above, such awards shall state the reasons for the amount awarded. Neither party is entitled to bring a claim to the arbitrator if the arbitrator has not been appointed before the expiration of 30 days after defects liability period.”

    A work order was issued on the same day. The said contract was to be completed by 8-1-1989 i.e within a period of about 11 months. The appellant failed to complete the work within the stipulated time. He applied for extension which was granted first up to 9-7-1989 and thereafter up to 30-9-1990. Within the said period the work was completed. The measurements of the work undertaken by the appellant were recorded on 26-11-1990. Final bill prepared and paid by the respondent was accepted by the appellant without any demur.

    4. Inter alia, on the premise that the appellant was asked to do extra items of work, it raised its claims by a letter dated 27-2-1991, which were rejected. Details of the purported extra work done by the appellant, however, were not mentioned in the said letter dated 27-2-1991. It submitted another claim giving details thereof by a letter dated 10-6-1991.

    5. The appellant by a letter dated 26-9-1991 purporting to invoke Clause 54 of the general conditions of the contract, issued notice to the Executive Engineer of the respondent, stating:

    “Whereas a number of claims were referred to you from time to time and in respect of many of them you have failed to give the decision. And whereas the work under contract was kept in progress by us in good faith and with a belief that on completion of the work you will reconsider our total case and settle our accounts with all the claims.
    And whereas the work has been duly completed by us, we are now in a petition (sic position) of finally working out in full the sum of money due and payable to us by the Department including all the claims.
    Now therefore, we hereby call upon you and give you notice finally under Clause 54 of the general conditions of the contract with a request to settle our accounts and give your decisions in respect of our following claims and disputes within a period of thirty days from the date of receipt of this notice by reconsidering your earlier decision in respect of claim on which you had indicated your decision earlier.”

    He specified 16 claims thereunder.

    6. The respondent rejected the said claims by its letter dated 5-10-1991 alleging that the stipulated period therefor expired in May 1991. The Executive Engineer of the respondent by his letter dated 29-10-1991 opined that the matter cannot be considered for arbitration, stating:

    “Please refer your letter under reference which was received by this office in the 1st week of October, 1991. The claims raised were already denied by this office vide Letter No. 448 dated 29-4-1991. As you have referred the matter under the provisions of Clause 54 of LCB No. 18 for 87, 88, the decisions of this office are again sent herewith. It is further clarified that the matter is brought for arbitration process after expiry of 30 days from the end of defect liability period. The work was completed in November 1990 and the defect liability period of six months is over in May 1991, hence the matter cannot be considered for arbitration.”

    However, its earlier decision of rejecting the claim was repeated.

    7. Treating the same to be an order rejecting his claim, the appellant herein preferred an appeal thereagainst before the Superintending Engineer in terms of its letter dated 26-11-1991, pursuant whereto a meeting was held between the representatives of the parties, the minutes whereof read as under:

    “Since the contractors have not submitted their claims under Clause 54 of the general conditions of the contract along with documentary evidences within the stipulated period i.e before the expiry of 30 days after defect liability period and as per Clause 55 which states ‘Neither party is entitled to bring a claim to the arbitrator if the arbitrator has not been appointed before the expiration of 30 days after defect liability period’.
    Defect liability period of this contract expired on 31-5-1991 and the stipulated period of 30 days expired on 30-6-1991.
    Hence the contractor's appeal for arbitration is hereby rejected.”

    A copy of the said minutes of the meeting was sent by the Superintending Engineer along with his letter dated 30-12-1991.

    8. A notice, on the premise that disputes and differences arose between the parties within the meaning of Clause 55 of the general conditions of the contract, was served upon the Chief Engineer asking him to furnish the names of its three officers for appointment of sole arbitrator within 30 days from the receipt thereof. The said request was rejected by the Chief Engineer in terms of his letter dated 26-2-1992, stating:

    “You have given notice under Clause 54 on 26-11-1991 to refer the dispute to arbitration. Thus the notice under Clause 54 is given after the expiry of 30 days of defect liability period.
    Thus you have not submitted the claims within the stipulated time and followed the procedure as per Clause 54 of general conditions for settlement of dispute. This has already been informed to you by the Superintending Engineer, Kukadi Canal Circle, Pune 6 under his Letter No. KCC/PB-1.KM 126.Claims/4129 dated 30-12-1991.
    Hence the question of appointing the arbitrator by this office does not arise.”

    9. The appellant thereafter sent a list of arbitrators on 9-3-1992 followed by a notice through a lawyer. Indisputably, the said request for referring the disputes to an arbitrator was rejected by respondent.

    10. The appellant filed an application under Section 8 of the Arbitration Act, 1940 (for short “the Act”) in the Court of Civil Judge (Senior Division), Ahmednagar at Ahmednagar for appointment of arbitrator. By reason of a judgment and order dated 9-12-1997, the Civil Judge (Senior Division), Ahmednagar opining that the said application having been filed within the period as specified in Article 137 of the Limitation Act, 1963 and the cause of action therefor having arisen on 29-10-1991 on which date the appellant's claim was rejected, appointed one Shri V.M Bedse, a retired Chief Engineer as arbitrator with regard to the additional and extra works allegedly carried out by the appellant. The learned Judge held:

    “The petitioner along with Ext. 19 has produced various documents and correspondence ensued with the respondents. It is crystal clear from this correspondence that the petitioner had demanded release of claim on 27-2-1991 under Clause 37 of the contract agreement. This claim letter was received by the respondents and further query in respect of proof of claim was called for by the respondents by their letter dated 29-4-1991. Accordingly, the proof was submitted by letter dated 10-6-1991 and details of claim were given on 26-9-1991. The petitioner also apprised about ‘settlement of dispute’ as contemplated in Clause 54 of the contract agreement. Therefore, practically there is compliance by the petitioner as contemplated under Clause 54 of the contract agreement. The record also reveals that the respondents on 5-10-1991 i.e after a lapse of three months replied to the notice of the petitioner dated 10-6-1991 and for the first time it was agitated that the petitioner has not taken steps under Clause 55 under defect liability and before expiration of 30 days. Clause 19(a) of the contract agreement is in respect of material and workmanship and it defines the defect liability in respect of workmanship and materials and so also the defect liability period is to be counted from the certified date of completion certificate. Under Clause 26 of the contract agreement, it is the respondents who are required to issue such certificate to the petitioner. The notices were issued by the petitioner under Clauses 54 and 55 of the contract but it appears from the record that the respondents did not take any steps to choose their arbitrator. On the contrary, on 9-3-1992 the list of three officers was demanded and out of them sole arbitrator was chosen but the respondents have not replied to the same. In this manner, the petitioner and the respondents could not concur for appointment of arbitrator and the petitioner had therefore no alternative but to resort to provisions of Section 8 of the Arbitration Act. The correspondence produced on record in support of claim under Section 8 of the Arbitration Act by the petitioner is sufficient to come to the conclusion that there was dispute between the petitioner and the respondents in respect of additional work and no such steps have been taken by the respondents as provided under the contract.”

    Civil Revision Application No. 201 of 1998 was preferred thereagainst by the respondent before the High Court, which by reason of the impugned judgment and order dated 13-4-2004 has been allowed. A review petition filed by the appellant thereagainst has been dismissed.

    11. Mr Sundaravardan, learned Senior Counsel appearing on behalf of the appellant raised the following contentions in support of the appeal:

    (i) The High Court committed a serious error of law in passing the impugned judgment insofar as it failed to take into consideration that limitation for raising a claim as envisaged under Clause 54 is not applicable in the instant case.
    (ii) In view of the fact that the claim was rejected only on 26-2-1992 by the appellate authority, the period of 30 days should be counted therefrom.
    (iii) While exercising its jurisdiction under Section 8 of the Act, the Court was concerned only with the question as to whether there was a triable issue.
    (iv) Once a triable issue is found to have been raised, which was required to be referred to the arbitration, the merit of the claim cannot be gone into.

    12. Ms Aprajita Singh, learned counsel appearing on behalf of the respondent, on the other hand, would urge:

    (i) Clause 54 of the general conditions of the contract must be invoked by the contractor during the tenure thereof and not after completion of the contract and acceptance of the final bill.
    (ii) The final bill having been accepted without any demur, the contract came to an end, wherewith the arbitration agreement which was a part thereof also perished.
    (iii) The appellant having not sought for extension of time in terms of sub-section (4) of Section 37 of the Act and in any event no sufficient cause having been made out therefor, even no extension of time could be granted.

    13. Indisputably, the parties are governed by the Act. “Arbitration agreement” has been defined in Section 2(a) of the Act to mean a written agreement to submit present or future differences to arbitration, whether an arbitrator is named therein or not. An arbitration is a private dispute resolution mechanism agreed upon by the parties. The arbitration agreement is contained in a commercial document; it must be interpreted having regard to the language used in it.

    14. A bare perusal of Clauses 37, 54 and 55 of the general conditions of contract clearly shows that the arbitration agreement entered into by and between the parties is not of wide amplitude. In a case where arbitration clause is of wide amplitude, the same may cover also the claims arising during the tenure of the contract or thereafter, provided the arbitration clause subsists.

    15. Clause 37 imposes an obligation upon the contractor to furnish to the Executive Engineer a release of claims against the Government arising out of the contract other than the claims specifically identified, evaluated and expected from the operation of the release by the contractor only after completion of the work and prior to payment thereof. There is nothing on record to show that any claim in relation to extra or additional work had been raised by the contractor prior to 27-2-1991 although final measurement had been recorded on 26-11-1990 and the bill has been paid in full and final satisfaction on 4-12-1990. Clauses 54 and 55 of the arbitration agreement must be read together.

    16. Indisputably, the contract has been entered into for works costing less than Rs 50 lakhs and, thus, Clause 54 would be attracted in the instant case. In terms of the said provision, the contractor has to raise a demand with the Executive Engineer if any work is demanded from him, which he considers to be outside the requirements of the contract. The word “consider” is of some significance, it means “to think over; to regard as or deem to be”. (See Advanced Law Lexicon, 3rd Edn., 2005.)

    17. If a work has to be carried out outside the terms of the contract and is unacceptable, the contractor is required to promptly approach the Executive Engineer in writing for obtaining his written instruction or decision in that behalf. The Executive Engineer is obligated to give his written instructions or decision within a period of 30 days of making such request. Once such instruction or decision is received, the contractor is required to comply therewith. Only in a case where the Executive Engineer fails and/or neglects to give a decision or issue instruction, the contractor may within a period of 30 days thereafter prefer an appeal to the appellate authority. The appellate authority is required to provide an opportunity of hearing to the contractor. It is only when the contractor is dissatisfied with the decision of the appellate authority, he may indicate his intention to refer the dispute to arbitration in terms of Clause 55 within a period of 30 days from the date of receipt of the said decision, failing which, the same would be final.

    18. The arbitration clause, thus, could be invoked only in a case where the decision has not become final and conclusive as per Clause 54.

    19. A plain reading of the aforementioned provisions clearly shows that Clause 54 does not envisage raising of a claim in respect of extra or additional work after the completion of contract. The jurisdiction of the civil court under Section 8 of the Act or under Section 20 thereof can be invoked if the disputes and differences arising between the parties was the one to which the arbitration agreement applied.

    20. The contractual clause provides for a limitation for the purpose of raising a claim having regard to the provisions of Section 28 of the Contract Act. It is no doubt true that the period of limitation as prescribed under Article 137 of the Limitation Act would be applicable, but it is well settled that a clause providing for limitation so as to enable a party to lodge his claim with the other side is not invalid.

    21. In Vulcan Insurance Co. Ltd. v. Maharaj Singh (1976) 1 SCC 943, AIR 1976 SC 287 the arbitration clause read as under:

    “9. …18. If any difference arises as to the amount of any loss or damage such difference shall independently of all other questions be referred to the decision of an arbitrator, to be appointed in writing by the parties in difference, or, if they cannot agree upon a single arbitrator to the decision of two disinterested persons as arbitrators….
    And it is hereby expressly stipulated and declared that it shall be a condition precedent to any right of action or suit upon this policy that the award by such arbitrator, arbitrators or umpire of the amount of the loss or damage if disputed shall be first obtained.
    19. In no case whatever shall the company be liable for any loss or damage after the expiration of twelve months from the happening of the loss or damage unless the claim is the subject of pending action or arbitration.”

    22. Referring to the well-known decision of Scott v. Avery (1843-60) All ER Rep 1, (1856) 25 LJ Ex 308, and noticing different views expressed by different courts, it was held: (Maharaj Singh case (1976) 1 SCC 943, AIR 1976 SC 287)

    “22. The two lines of cases clearly bear out the two distinct situations in law. A clause like the one in Scott v. Avery (1843-60) All ER Rep 1, (1856) 25 LJ Ex 308 bars any action or suit if commenced for determination of a dispute covered by the arbitration clause. But if on the other hand a dispute cropped up at the very outset which cannot be referred to arbitration as being not covered by the clause, then the Scott v. Avery (1843-60) All ER Rep 1, (1856) 25 LJ Ex 308 clause is rendered inoperative and cannot be pleaded as a bar to the maintainability of the legal action or suit for determination of the dispute which was outside the arbitration clause.”

    Whether such a clause comes within the purview of the arbitration clause vis-à-vis Article 137 of the Limitation Act, it was held: (Maharaj Singh case (1976) 1 SCC 943, AIR 1976 SC 287)

    “23. … It has been repeatedly held that such a clause is not hit by Section 28 of the Contract Act and is valid; vide Baroda Spg. and Wvg. Co. Ltd. v. Satyanarayen Marine and Fire Insurance Co. Ltd. ILR (1914) 38 Bom 344, AIR 1914 Bom 225 (2), Dawood Tar Mahomed Bros. v. Queensland Insurance Co. Ltd. AIR 1949 Cal 390 and Ruby General Insurance Co. Ltd. v. Bharat Bank Ltd. AIR 1950 East Punj 352 Clause 19 has not prescribed a period of 12 months for the filing of an application under Section 20 of the Act. There was no limitation prescribed for the filing of such an application under the Limitation Act, 1908 or the Limitation Act, 1963. Article 181 of the former did not govern such an application. The period of three years prescribed in Article 137 of the Act of 1963 may be applicable to an application under Section 20.”

    23. Whether the difference which arose between the parties was the one to which the arbitration clause applied and whether the application under Section 20 of the Act could be dismissed, this Court opined: (Maharaj Singh case (1976) 1 SCC 943, AIR 1976 SC 287)

    “24. But in this case on a careful consideration of the matter we have come to the definite conclusion that the difference which arose between the parties on the company's repudiation of the claim made by Respondent 1 was not one to which the arbitration clause applied and hence the arbitration agreement could not be filed and no arbitrator could be appointed under Section 20 of the Act. Respondent 1 was ill-advised to commence an action under Section 20 instead of instituting a suit within three months of the date of repudiation to establish the company's liability.”

    [See also A.B.C Laminart (P) Ltd. v. A.P Agencies (1989) 2 SCC 163, AIR 1989 SC 1239.]

    24. It is not a case where an application under Section 8 could not (sic) be filed within a period of 3 years. It is a case where a determination was necessary as regards invocation of the dispute settlement processes. For resolution of the dispute, a claim must be made in terms of the provisions of the contract for the purpose of giving effect to the arbitration clause, the application thereof being limited in nature.

    25. Mr Sundaravardan has taken us through a large number of decisions to contend that the purported “accord and satisfaction” on the part of the contractor might not itself be a sufficient ground to reject a prayer for making a reference under the Arbitration Act. Such a question came up for consideration before this Court in Damodar Valley Corpn. v. K.K Kar (1974) 1 SCC 141, wherein this Court noticing the decision of Heyman v. Darwins Ltd. 1942 AC 356, (1942) 1 All ER 337 (HL) stated the law thus: (Damodar Valley case (1974) 1 SCC 141)

    “9. … ‘… Again, an admittedly binding contract containing a general arbitration clause may stipulate that in certain events the contract shall come to an end. If a question arises whether the contract has for any such reason come to an end I can see no reason why the arbitrator should not decide that question. It is clear, too, that the parties to a contract may agree to bring it to an end to all intents and purposes and to treat it as if it had never existed. In such a case, if there be an arbitration clause in the contract, it perishes with the contract. If the parties substitute a new contract for the contract which they have abrogated the arbitration clause in the abrogated contract cannot be invoked for the determination of questions under the new agreement. All this is more or less elementary.’ ”

    It was furthermore held: (Damodar Valley case (1974) 1 SCC 141)

    “13. … Similarly the question whether there has been a settlement of all the claims arising in connection with the contract also postulates the existence of the contract. The principle laid down by Sarkar, J., in Kishorilal Gupta & Bros. case AIR 1959 SC 1362, (1960) 1 SCR 493 that accord and satisfaction does not put an end to the arbitration clause was not dissented to by the majority. On the other hand Proposition 6 seems to lend weight to the views of Sarkar, J. In these circumstances, the question whether the termination was valid or not and whether damages are recoverable for such wrongful termination does not affect the arbitration clause, or the right of the respondent to invoke it for appointment of an arbitrator.”

    (See also S.C Konda Reddy v. Union of India AIR 1982 Kant 50.)

    26. We are, however, in this case faced with a different situation. The contention of the respondent is not that there has been a breach of contract and the contract still subsists. Its contention is that in terms of the contract the claim for extra work or additional work should have been raised during the tenure of the contract itself and not after it came to an end and payment received in full and final satisfaction.

    27. An arbitration clause, as is well known, is a part of the contract. It being a collateral term need not, in all situations, perish with coming to an end of the contract. It may survive. This concept of separability of the arbitration clause is now widely accepted. In line with this thinking, the Uncitral Model Law on International Commercial Arbitration incorporates the doctrine of separability in Article 16(1). The Indian law — the Arbitration and Conciliation Act, 1996, which is based on the Uncitral Model Law, also explicitly adopts this approach in Section 16(1)(b), which reads as under:

    “16. Competence of Arbitral Tribunal to rule on its jurisdiction.—(1) The Arbitral Tribunal may rule on its own jurisdiction, including ruling on any objections with respect to the existence or validity of the arbitration agreement, and for that purpose,—
    (a) an arbitration clause which forms part of a contract shall be treated as an agreement independent of the other terms of the contract; and
    (b) a decision by the Arbitral Tribunal that the contract is null and void shall not entail ipso jure the invalidity of the arbitration clause.”
    (emphasis supplied)

    Modern laws on arbitration confirm the concept.

    28. The United States Supreme Court in a recent judgment in Buckeye Check Cashing Inc. v. Cardegna 546 US 460 (2005) acknowledged that the separability rule permits a court “to enforce an arbitration agreement in a contract that the arbitrator later finds to be void”. The Court, referring to its earlier judgments in Prima Paint Corpn. v. Flood & Conklin Mfg. Co. 18 L Ed 2d 1270, 388 US 395 (1966) and Southland Corpn. v. Keating 465 US 1 (1984), inter alia, held:

    “Prima Paint and Southland answer the question presented here by establishing three propositions. First, as a matter of substantive federal arbitration law, an arbitration provision is severable from the remainder of the contract.”

    But this must be distinguished from the situation where the claim itself was to be raised during the subsistence of a contract so as to invoke the arbitration agreement would not apply.

    29. BHEL v. Amar Nath Bhan Prakash (1982) 1 SCC 625, whereupon reliance has been placed by Mr Sundaravardan is not applicable as it was held therein that the question whether there was discharge of the contract by accord and satisfaction or not, is itself arbitrable. The said question need not detain us having been considered by this Court in Bharat Coking Coal Ltd. v. Annapurna Construction (2003) 8 SCC 154 holding: (Bharat Coking Coal Ltd. case (2003) 8 SCC 154)

    “14. The question as to whether the claim of the contractor is dehors the rules or not was a matter which fell for consideration before the arbitrator. He was bound to consider the same. The jurisdiction of the arbitrator in such a matter must be held to be confined to the four corners of the contract. He could not have ignored an important clause in the agreement; although it may be open to the arbitrator to arrive at a finding on the materials on record that the claimant's claim for additional work was otherwise justified.”

    30. In NTPC Ltd. v. Reshmi Constructions, Builders & Contractors (2004) 2 SCC 663 this Court held:

    “18. Normally, an accord and satisfaction by itself would not affect the arbitration clause but if the dispute is that the contract itself does not subsist, the question of invoking the arbitration clause may not arise. But in the event it be held that the contract survives, recourse to the arbitration clause may be taken. (See Union of India v. Kishorilal Gupta AIR 1959 SC 1362, (1960) 1 SCR 493 and Naihati Jute Mills Ltd. v. Khyaliram Jagannath AIR 1968 SC 522.)”

    It was furthermore opined: (NTPC Ltd. case (2004) 2 SCC 663)

    “28. Further, necessitas non habet legem is an age-old maxim which means necessity knows no law. A person may sometimes have to succumb to the pressure of the other party to the bargain who is in a stronger position.
    29. We may, however, hasten to add that such a case has to be made out and proved before the arbitrator for obtaining an award.
    30. At this stage, the court, however, will only be concerned with the question whether triable issues have been raised which are required to be determined by the arbitrators.”

    31. We, however, as noticed hereinbefore, are concerned with a different fact situation. As arbitration clause could not be invoked having regard to the limited application of Clauses 37, 54 and 55 of the general conditions of the contract, we are of the opinion that the trial court was not correct in directing appointment of an arbitrator.

    32. We may notice that in Wild Life Institute of India v. Vijay Kumar Garg (1997) 10 SCC 528 a Division Bench of this Court held as under:

    “6. It is also necessary to refer to the arbitration clause under the contract which clearly provides that if the contractor does not make any demand for arbitration in respect of any claim in writing within 90 days of receiving the intimation from the appellants that the bill is ready for payment, the claim of the contractor will be deemed to have been waived and absolutely barred and the appellants shall be discharged and released of all liabilities under the contract in respect of these claims. The liability, therefore, of the appellants ceases if no claim of the contractor is received within 90 days of receipt by the contractor of an intimation that the bill is ready for payment. This clause operates to discharge the liability of the appellants on expiry of 90 days as set out therein and is not merely a clause providing a period of limitation. In the present case, the contractor has not made any claim within 90 days of even receipt of the amount under the final bill. The dispute has been raised for the first time by the contractor 10 months after the receipt of the amount under the final bill.”
    (emphasis in original)

    33. The High Court has relied upon a decision of this Court in P.K Ramaiah and Co. v. NTPC 1994 Supp (3) SCC 126. We need not deal therewith in detail as the effect thereof has been considered by us in Bharat Coking Coal Ltd. v. Annapurna Construction (2003) 8 SCC 154.

    34. It is also not a case where sub-section (4) of Section 37 of the Act could be invoked. The appellant did not invoke Section 37(4) of the Act. No reason has been assigned as to why the said discretion of the court should be invoked particularly when the claim has been raised only after completion of the work.

    35. For the reasons aforementioned, we, albeit for different reasons, affirm the judgment of the High Court. The appeals are, accordingly, dismissed. In the facts and circumstances of the case there shall be no order as to costs.

    36. We may clarify that nothing stated herein shall affect the merit of the appellant's claim to invoke the jurisdiction before any other forum for enforcing the same.

    Use AI to get other relevant cases.

    Comments

    P. Manohar Reddy & Bros. v. Maharashtra Krishna Valley Development Corporation And Others
    (Dec 18, 2008)