AMICUS AI
Citation Codes
Neutral Citations
2007 INSC 27
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 11 of the Arbitration Act
  • Section 37(1)(b) of the Arbitration and Conciliation Act, 1996
  • Section 37(1)(b) of the Arbitration Act
  • Section 16 of the Arbitration Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2007 INSC 27
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 11 of the Arbitration Act
  • Section 37(1)(b) of the Arbitration and Conciliation Act, 1996
  • Section 37(1)(b) of the Arbitration Act
  • Section 16 of the Arbitration Act
Smart Summary

Factual and Procedural Background

An agreement dated 27-11-1993 between Krishna Bhagya Jala Nigam Ltd. (“Jala Nigam”) and the respondent-contractor covered construction of the Mulawad Lift Irrigation Scheme, initially scheduled for completion by 26-11-1996. Two supplementary agreements (11-6-1996 and 7-11-1998) extended the work, and the completion date was ultimately pushed to 31-12-2003.

Disputes arose and, relying on clause 29 of the contract, the contractor asked the Chief Engineer to arbitrate (23-3-1998). The Chief Engineer refused, claiming the contract lacked an arbitration clause. The contractor petitioned the High Court under Section 11 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”), which on 10-9-1999 appointed the Chief Engineer as arbitrator. After both sides filed statements and evidence, an award dated 25-6-2000 (published 14-11-2000) granted the contractor several monetary claims.

Jala Nigam challenged the award under Section 34 before the Principal Civil Judge, Bijapur (Arbitration Case 1/2001); the challenge was dismissed on 15-12-2001. Its further appeal under Section 37(1)(b) (MFA 1785/2002) was dismissed by the Karnataka High Court on 28-1-2005. Jala Nigam then filed the present civil appeal to the Supreme Court.

Legal Issues Presented

  1. Whether, in the circumstances, Jala Nigam could contend that clause 29 of the contract was not an arbitration clause, rendering the arbitral award a nullity for lack of jurisdiction.
  2. Whether the arbitral award required interference on the merits of the contractor’s various monetary claims, particularly interest rates and idling charges for machinery.

Arguments of the Parties

Appellant (Jala Nigam)

  • Clause 29 is not an arbitration clause; therefore, the arbitral tribunal lacked jurisdiction and its award is a nullity.
  • Lack of jurisdiction cannot be cured by consent or participation; appearance before the arbitrator does not confer jurisdiction.
  • The plea of “no arbitration clause” had been raised earlier in the Section 11 proceedings (CMP 26/1999) and thus was not waived.
  • Proceedings should be stayed until a Constitution Bench decides on the interpretation of clause 29 (reference in P. Dasaratharama Reddy Complex v. State of Karnataka).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
P. Dasaratharama Reddy Complex v. Government of Karnataka (order of referral, 26-7-2005) Pending Constitution Bench reference on whether clause 29 of similar contracts constitutes an arbitration clause. The Court declined to await the outcome of the reference, holding that the parties’ conduct and the delay in the present matter made postponement unnecessary.

Court's Reasoning and Analysis

On the jurisdiction issue, the Supreme Court noted that Jala Nigam never objected to arbitration before the arbitrator, in the Section 34 proceedings, or when the High Court appointed the Chief Engineer. Instead, it actively participated—filing counter-statements, submitting evidence, and presenting written arguments—thereby accepting the existence of an arbitration agreement. Because Section 16 was not invoked to question the tribunal’s competence, and both parties consistently proceeded on the footing that clause 29 was an arbitration clause, Jala Nigam was estopped from alleging the contrary at this late stage.

Regarding the reference pending before a Constitution Bench, the Court held that the factual matrix and long-standing nature of this dispute made further delay unjustified; the appeal would therefore be decided on its own facts without awaiting the larger bench’s ruling.

On the merits of the award, the Court found the arbitrator’s item-wise analysis “meticulous.” It intervened only on two counts:

  • Interest: In view of changed economic conditions, the uniform 18 % interest (pre-reference, pendente lite, and future) was excessive; it was reduced to 9 % across all periods.
  • Idling Charges: Although the contractor claimed Rs 1.47 crore for machinery lying idle, the Court—after reviewing the arbitrator’s exclusions and considering delays caused by Jala Nigam—suggested, and the contractor accepted, a reduction to Rs 1 crore.

No other aspect of the award warranted interference.

Holding and Implications

Civil appeal partly allowed. The Supreme Court upheld the arbitration award except for: (a) reducing all interest rates from 18 % to 9 %, and (b) reducing idling-charge compensation from Rs 1.47 crore to Rs 1 crore. No order as to costs.

Implications: The decision reinforces the principle that a party who participates in arbitration without timely jurisdictional objection cannot later challenge the existence of an arbitration agreement. Substantively, it signals judicial willingness to recalibrate high interest awards in light of contemporary economic conditions, but otherwise respects arbitral fact-finding.

To access the original judgment, please Sign In or Subscribe.

    Krishna Bhagya Jala Nigam Ltd. v. G. Harischandra Reddy And Another

    S.H Kapadia, J.— Leave granted.

    2. Two issues arise for determination in this civil appeal filed by Krishna Bhagya Jala Nigam Ltd. (for short “Jala Nigam”) against the decision of the Division Bench of the Karnataka High Court dated 28-1-2005 in Miscellaneous First Appeal No. 1785 of 2002 dismissing the said appeal preferred by Jala Nigam under Section 37(1)(b) of the Arbitration and Conciliation Act, 1996 (for short “the Arbitration Act”).

    3. The first issue is: whether Jala Nigam could be allowed to raise the contention, on the facts and circumstances of this case, that clause 29 of the contract (agreement) is not an arbitration clause and due to want of jurisdiction of the Arbitral Tribunal to adjudicate upon the claims made by the contractor (Respondent 1), award dated 25-6-2000 published on 14-11-2000 was a nullity.

    4. The second issue is regarding the merits of the claims made by the contractor.

    5. The facts giving rise to the above civil appeal are as follows:

    On 27-11-1993 agreement bearing No. 41/93 was entered into between Jala Nigam and the claimant (Respondent 1) concerning construction of Mulawad Lift Irrigation Scheme. The contract was for 36 months. It was to be completed by 26-11-1996. In the course of execution of the contract, Jala Nigam entrusted to the contractor, certain extra work vide two supplementary agreements dated 11-6-1996 and 7-11-1998. The contract was extended up to 31-12-2003. The claimant (contractor) raised disputes, said to have arisen out of the works entrusted under the contract. By letter dated 23-3-1998 the contractor called upon the Chief Engineer to act as an arbitrator under clause 29 of the contract which is reproduced hereinbelow:

    “Clause 29(a) If any dispute or difference of any kind whatsoever were to arise between the Executive Engineer/Superintending Engineer and the contractor regarding the following matters namely:
    (i) the meaning of the specifications, designs, drawings and instructions hereinbefore mentioned,
    (ii) the quality of workmanship or materials used on the work, and
    (iii) any other question, claim, right, matter, thing whatsoever, in any way arising out of or relating to the contract, designs, or those conditions or failure to execute the same whether arising during the progress of the work or after the completion, termination or abandonment thereof the dispute shall, in the first place, be referred to the Chief Engineer who has jurisdiction over the work specified in the contract. The Chief Engineer shall within a period of ninety days from the date of being requested by the contractor to do so, give written notice of his decision to the contractor.
    (b) Subject to other form of settlement hereafter provided, the Chief Engineer's decision in respect of every dispute or difference so referred shall be final and binding upon the contractor. The said decision shall forthwith be given effect to and the contractor shall proceed with the execution of the work with all due diligence.
    (c) In case the decision of the Chief Engineer is not acceptable to the contractor, he may approach the law courts at ….(*) for settlement of dispute after giving due written notice in this regard to the Chief Engineer within a period of ninety days from the date of receipt of this written notice of the decision of the Chief Engineer.
    (d) If the Chief Engineer has given written notice of his decision to the contractor and no written notice to approach the law court has been communicated to him by the contractor within a period of ninety days from receipt of such notice, the decision shall be final and binding upon the contractor.”

    6. By letter dated 26-3-1998 the Chief Engineer refused to act as an arbitrator on the ground that the contract did not provide for arbitration. This led the contractor to file CMP No. 26 of 1999 under Section 11 of the Arbitration Act. By order dated 10-9-1999 the High Court directed the Chief Engineer to act as an arbitrator. By the said order the High Court directed both the parties to file their respective claims and counterclaims before the arbitrator. By letter dated 12-11-1999 the arbitrator entered upon the reference. He fixed the date of appearance of the parties. The arbitrator gave necessary directions to both sides to file statements and counter-statements. The contractor placed before the arbitrator, 11 claims in all. Jala Nigam filed its counter-statement. Ultimately, on the basis of the evidence produced by the parties, the arbitrator gave his award on 25-6-2000 and the same was published on 14-11-2000.

    7. Aggrieved by the award, Jala Nigam filed a petition under Section 34(2)(v) of the Arbitration Act before the Principal Civil Judge (Senior Division), Bijapur vide Arbitration Case No. 1 of 2001. The award was confirmed by the said civil court vide judgment dated 15-12-2001. Aggrieved by the said decision, Jala Nigam carried the matter in first appeal filed under Section 37(1)(b) of the Arbitration Act to the High Court. Vide impugned judgment dated 28-1-2005 the appeal stood dismissed. Hence this civil appeal.

    8. Mr C.S Vaidyanathan, learned Senior Counsel for Jala Nigam, contended that the abovequoted clause 29 of the contract was not an arbitration clause and, therefore, the proceedings before the arbitrator stood vitiated for lack of jurisdiction. He contended that the proceedings before the arbitrator were without jurisdiction for want of arbitration agreement which cannot be cured by appearance of the parties, even if there was no protest or even if there was a consent of Jala Nigam, since consent cannot confer jurisdiction and, therefore, the impugned award was null and void. Learned counsel submitted that though the plea of “no arbitration clause” was not raised in the counter-statement before the arbitrator, such a plea was taken by Jala Nigam in CMP No. 26 of 1999 filed by the contractor and, therefore, Jala Nigam was entitled to raise the plea of “no arbitration clause”. Learned counsel submitted that under the circumstances the courts below had erred in holding that Jala Nigam had waived its right to object to the award on the aforementioned grounds.

    9. We do not find any merit in the above arguments. The plea of “no arbitration clause” was not raised in the written statement filed by Jala Nigam before the arbitrator. The said plea was not advanced before the civil court in Arbitration Case No. 1 of 2001. On the contrary, both the courts below on facts have found that Jala Nigam had consented to the arbitration of the disputes by the Chief Engineer. Jala Nigam had participated in the arbitration proceedings. It submitted itself to the authority of the arbitrator. It gave consent to the appointment of the Chief Engineer as an arbitrator. It filed its written statements to the additional claims made by the contractor. The Executive Engineer who appeared on behalf of Jala Nigam did not invoke Section 16 of the Arbitration Act. He did not challenge the competence of the Arbitral Tribunal. He did not call upon the Arbitral Tribunal to rule on its jurisdiction. On the contrary, it submitted to the jurisdiction of the Arbitral Tribunal. It also filed written arguments. It did not challenge the order of the High Court dated 10-9-1999 passed in CMP No. 26 of 1999. Suffice it to say that both the parties accepted that there was an arbitration agreement, they proceeded on that basis and, therefore, Jala Nigam cannot be now be allowed to contend that clause 29 of the contract did not constitute an arbitration agreement.

    10. Before concluding on this issue, one clarification needs to be mentioned. On 26-7-2005 a three-Judge Bench of this Court has referred the question involving interpretation of clause 29 of the contract to the Constitution Bench in P. Dasaratharama Reddy Complex v. Govt. of Karnataka. Placing reliance on the said order, learned counsel for Jala Nigam submitted that the hearing of this civil appeal be postponed pending disposal of the above reference by the Constitution Bench. We do not find any merit in this argument. As stated above, the plea that clause 29 of the contract was not an arbitration clause, was raised in the present case for the first time only in Miscellaneous First Appeal No. 1785 of 2002 filed under Section 37(1)(b) of the Arbitration Act before the High Court. As stated above, Jala Nigam, on the contrary, had consented to the Chief Engineer, acting as an arbitrator. For the aforestated reasons and particularly in view of the fact that there has been considerable delay in the litigation no useful purpose would be served in keeping the matter pending in this Court awaiting the decision of the Constitution Bench. Therefore, on the facts and circumstances of this case and in view of the conduct of the parties, we hold that Jala Nigam cannot be allowed to urge that clause 29 of the contract is not an arbitration clause.

    11. On the merits of the claims made by the contractor we find from the impugned award dated 25-6-2000 that it contains several heads. The arbitrator has meticulously examined the claims of the contractor under each separate head. We do not see any reason to interfere except on the rates of interest and on the quantum awarded for letting machines of the contractor remaining idle for the periods mentioned in the award. Here also we may add that we do not wish to interfere with the award except to say that after economic reforms in our country the interest regime has changed and the rates have substantially reduced and, therefore, we are of the view that the interest awarded by the arbitrator at 18% for the pre-arbitration period, for the pendente lite period and future interest be reduced to 9%.

    12. As far as idling charges are concerned, the arbitrator has awarded Rs 42,000 per day for the period 1-2-1994 to 17-12-1994 and from 1-6-1995 to 31-12-1995 excluding the period 18-12-1994 to 31-5-1995 and from 1-1-1996 to 12-11-1996. On this basis the idling charges awarded by the arbitrator was arrived at Rs 1.47 crores. It is contended that the contractor has not led any evidence to show the existence of the machinery at site and, therefore, he was not entitled to idling charges. We are of the view that the award of the arbitrator is fair and equitable. He has excluded certain periods from calculations, as indicated above. We have examined the records. The delay took place on account of non-supply of drawings and designs and in the meantime the establishment of the contractor stood standstill. We suggested to the learned counsel for the respondent (contractor) for reduction of the awarded amount under this head from Rs 1.47 crores to Rs 1 crore. Learned counsel for the respondent fairly accepted our suggestion. We suggested the aforestated figure keeping in mind the long-standing dispute between the parties. Therefore, the amount awarded under this head shall stand reduced from Rs 1.47 crores to Rs 1 crore.

    13. Accordingly, the civil appeal stands allowed to the extent indicated above with no order as to costs.