Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 33 of the Arbitration Act
  • Section 41(b) read with the Second Schedule of the Act
  • Section 41(b), Second Schedule of the Arbitration Act
  • Order 39 Rule 1 Code of Civil Procedure, 1908
  • The Code of Civil Procedure, 1908
  • clause (b) of Section 41 of the Arbitration Act
  • Section 41(b) of the Arbitration Act and the Second Schedule to the Arbitration Act, 1940
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 33 of the Arbitration Act
  • Section 41(b) read with the Second Schedule of the Act
  • Section 41(b), Second Schedule of the Arbitration Act
  • Order 39 Rule 1 Code of Civil Procedure, 1908
  • The Code of Civil Procedure, 1908
  • clause (b) of Section 41 of the Arbitration Act
  • Section 41(b) of the Arbitration Act and the Second Schedule to the Arbitration Act, 1940
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

The appellant entered into a contract with the State of Rajasthan for widening the Gagar Diversion Bridge at Bikaner in the Sri Ganganagar section. When disputes arose, the parties, by mutual agreement, referred the matter to arbitration before Shri K. L. Sethia. During the pendency of the arbitral reference the State sought to adjust sums allegedly payable to the appellant against amounts due under another contract. The appellant therefore moved the District Court under Order 39 Rule 1 of the Code of Civil Procedure, 1908, read with Section 41(b) and the Second Schedule of the Arbitration Act, 1940, seeking an ad-interim injunction to restrain the State from making such adjustments.

The District Judge held that the application was not maintainable because no arbitration proceedings were then pending “through the intervention of the court,” and consequently Section 41(b) and the Second Schedule were inapplicable. A Civil Revision Petition to the Rajasthan High Court was dismissed. The present appeal to the Supreme Court was filed by special leave challenging those concurrent orders.

Legal Issues Presented

  1. Whether a civil court can entertain an application for interim injunction under Section 41(b) read with the Second Schedule of the Arbitration Act, 1940, when no arbitration proceedings are pending before the court.
  2. Whether an injunction restraining the respondent-State from adjusting amounts due under a different contract is permissible, particularly when clause 50 of the contract expressly authorises such adjustments.

Arguments of the Parties

Appellant's Arguments

  • The availability of interim relief under Section 41(b) does not depend on arbitration proceedings being before the court; the provision applies so long as an arbitration is substantively pending between the parties.
  • Permitting the State to adjust amounts from another contract would nullify the arbitration proceedings by effectively allowing a unilateral set-off of the claim under arbitration.
  • Reliance was placed on Union of India v. Raman Iron Foundry (1974) 2 SCC 231 to support the position that courts may grant such injunctive relief.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. Raman Iron Foundry, (1974) 2 SCC 231 Earlier view suggesting courts could restrain withholding/adjustment of amounts even when arbitration was not before the court. Cited by the appellant; the Supreme Court did not follow it, noting that the later three-Judge Bench decision had limited its applicability.
H.M. Kamaluddin Ansari & Co. v. Union of India, (1983) 4 SCC 417 Clarified that the court’s powers under Section 41(b) are exercisable only “for the purpose of, and in relation to” arbitration proceedings before the court, and an injunction cannot in substance compel payment. Treated as binding authority; relied upon to hold that the District Court lacked jurisdiction and that the requested injunction was beyond the scope of Section 41(b).

Court's Reasoning and Analysis

The Supreme Court reiterated that, under Section 41(b) and the Second Schedule, the civil court’s power to grant interim measures exists only when some proceedings concerning the arbitration are already seized of the court. The initiation or pendency of such proceedings is a pre-condition for invoking those powers.

The Court further observed that granting an injunction restraining the State from adjusting amounts due under other contracts would “virtually amount to a direction to pay” the contractor, which falls outside the permissible ambit of Section 41(b). The Court drew direct support from the ratio in Kamaluddin Ansari, which had expressly overruled contrary reasoning of certain High Court decisions and qualified the earlier view in Raman Iron Foundry.

On the contractual merits, clause 50 expressly authorised the respondent to adjust sums due under other contracts. This contractual stipulation independently barred the relief sought. Consequently, the orders of the District Judge and the High Court were found to be correct in law and on facts.

Holding and Implications

Appeal Dismissed. No order as to costs.

The decision affirms that interim injunctions under Section 41(b) of the Arbitration Act, 1940, are unavailable unless arbitration proceedings are already before the court, and that courts cannot issue interim orders which, in substance, compel payment or prevent contractually permitted set-offs. The ruling reinforces the authority of Kamaluddin Ansari without creating a new legal precedent.

To access the original judgment, please Sign In or Subscribe.

    Sant Ram & Co. v. State Of Rajasthan And Others

    Order

    1. This appeal by special leave arises from the order of the Single Judge of the Rajasthan High Court made in Civil Revision Petition No. 293 of 1990, dated 7-8-1990.

    2. The admitted position is that the appellant had entered into a contract with the respondent-State for execution of the works of widening of Gagar Diversion Bridge at Bikaner in Sri Ganganagar section. Pursuant to a dispute which arose between the parties, in terms of the contract, the matter by mutual agreement, was referred to the arbitrator by name Shri K.L Sethia. Pending arbitration, the respondent sought to adjust the amounts due to the appellant in another contract. Thereon the appellant filed an application in the District Court under Order 39 Rule 1 Code of Civil Procedure, 1908 read with Section 41(b) of the Arbitration Act and the Second Schedule to the Arbitration Act, 1940 for ad interim injunction restraining the respondent from adjusting the same. The District Judge by his order held that such an application is not maintainable without the intervention of the court; therefore, Section 41(b) and the Second Schedule have no application. The same came to be upheld by the learned Chief Justice in the impugned order. Thus this appeal by special leave.

    3. Shri A.B Rohtagi, learned Senior Counsel for the appellant, contends that for entertaining an application under Section 41(b) read with the Second Schedule, it is not a condition that the arbitration proceedings should be pending through the intervention of the court. Independently thereof, when arbitration proceedings were pending between the parties in respect of the claim or counter-claim and when the respondent sought to adjust the same with the amounts due from other contracts, the court would, in the circumstances, intervene and restrain the respondents from adjusting the same as a counter-claim. Otherwise, the arbitration proceedings would be nullified. He placed strong reliance on the judgment of a two-Judge Bench of this Court in Union of India v. Raman Iron Foundry (1974) 2 SCC 231, (1974) 3 SCR 556. The question is no longer res integra. A Bench of three Judges of this Court in H.M Kamaluddin Ansari & Co. v. Union of India (1983) 4 SCC 417, (1983) 3 SCR 607 has considered the scope of Section 41(b) and the Second Schedule and had held thus:

    “The first question that falls for consideration in this appeal is about the exact scope and ambit of Section 41 in order to appreciate the contention raised on behalf of the appellant:
    ‘41. Procedure and powers of court.—Subject to the provisions of this Act and of rules made thereunder—
    (a) the provisions of the Code of Civil Procedure, 1908 shall apply to all proceedings before the court, and to all appeals, under this Act, and
    (b) the court shall have, for the purpose of, and in relation to, arbitration proceedings, the same power of making orders in respect of any of the matters set out in the Second Schedule as it has for the purpose of, and in relation to, any proceedings before the court:
    Provided that nothing in clause (b) shall be taken to prejudice any power which may be vested in an arbitrator or umpire for making orders with respect to any of such matters.’
    In view of clause (b) of Section 41 the court has been given power of passing orders in respect of any of the matters set out in the Second Schedule for the purpose of and in relation to any proceedings before the court. The Second Schedule of the Arbitration Act inter alia includes ‘interim injunction’ and the ‘appointment of receiver’.”

    4. In that case, an application under Section 33 of the Arbitration Act had come to be filed and then an application for ad interim injunction was filed. It will, therefore, be clear that to avail of the remedy under the provisions of the Code of Civil Procedure, when an application for injunction under Section 41(b) read with the Second Schedule is filed, the court shall have, pending proceedings for the purpose of and in relation to the arbitration proceedings availed of through the process of the court, the same power of making orders in respect of any matters set out in the Second Schedule as it has for the purpose of and in relation to any proceedings before the court. The initiation of pendency of any proceedings in the court in relation to the arbitration proceedings would, therefore, be a precondition for the exercise of the power by the civil court under the Second Schedule of the Act.

    5. On merits, this Court had held in similar circumstances that such an injunction cannot be granted as it amounts to granting a relief which is not warranted under Section 41(b) read with the Schedule of the Act. This Court had recorded a finding as under:

    “We are clearly of the view that an injunction order restraining respondents from withholding the amount due under other pending bills to the contractor virtually amounts to a direction to pay amount to the contractor-appellants. Such an order was clearly beyond the purview of clause (b) of Section 41 of the Arbitration Act. The Union of India has no objection to the grant of an injunction restraining it from recovering or appropriating the amount lying with it in respect of other claims of the contractor towards its claim for damages. But certainly clause 18 of the standard contract confers ample power upon the Union of India to withhold the amount and no injunction order could be passed restraining the Union of India from withholding the amount.”

    6. The Division Bench decision on which reliance was placed, has reiterated that principle, namely, that “such an injunction can only be for the purpose of and in relation to the arbitration proceedings. The court could not make an injunction order which, though ostensibly in the form of an order of interim injunction, in substance, amounted to a direction to the appellant to pay the amounts due to the respondent under other contracts”. In fact, the ratio therein which the learned counsel tried to propound, was not approved and the said decision was expressly overruled in Kamaluddin case (1983) 4 SCC 417, (1983) 3 SCR 607.

    7. It is seen that under clause (50) of the contract, the appellant has expressly agreed for adjustment of the amount pending with the respondent in respect of the claim under the dispute or any other contract with the Department. Under these circumstances, neither on merits nor on principle of law, we find any illegality in the order passed by the High Court warranting interference.

    8. The appeal is accordingly dismissed. No costs.

    Use AI to get other relevant cases.

    Comments

    Sant Ram & Co. v. State Of Rajasthan And Others
    (Nov 20, 1996)