AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 9 of the Code of Civil Procedure
  • Section 1 of the particular Act
  • Sections 12, 19 and 52 of the Indian Electricity Act, 1910
  • The provisions of the Electricity (Supply) Act, 1948
  • Section 12 of the Electricity Act, 1910
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 9 of the Code of Civil Procedure
  • Section 1 of the particular Act
  • Sections 12, 19 and 52 of the Indian Electricity Act, 1910
  • The provisions of the Electricity (Supply) Act, 1948
  • Section 12 of the Electricity Act, 1910
Smart Summary

Factual and Procedural Background

The respondent owns land (Kh. No. 908/2, area 1.32 acres, Village Nandai) earmarked for industrial use. After the respondent had already commenced construction of a saw-mill, the appellant Electricity Board erected 33 KV high-tension transmission lines with poles over the property without obtaining the respondent’s consent. Alleging danger to its property and claiming loss, the respondent filed Civil Suit No. 9-A of 1967 seeking removal of the line and compensation.

The Civil Judge, Class-I, Rajnandgaon, decreed removal of the line, awarded past damages of Rs 1,770 and future damages at Rs 5 per day. The First Additional District Judge, Durg, dismissed the Board’s first appeal. In second appeal, the High Court of Madhya Pradesh removed the mandatory injunction (thereby allowing the line to remain) but sustained the damages. The Electricity Board appealed to the Supreme Court.

Legal Issues Presented

  1. Whether the civil suit was barred—expressly or impliedly—because the Indian Electricity Act, 1910 and the Electricity (Supply) Act, 1948 provide a special forum and remedies, thereby excluding civil-court jurisdiction under Section 9 of the Code of Civil Procedure.
  2. Whether, on the facts found, the respondent was entitled to damages for the unauthorised erection of the transmission line.

Arguments of the Parties

Appellant (Electricity Board)

  • Relied on Sections 12, 19 and 52 of the Indian Electricity Act, 1910 to contend that the Act furnishes complete remedies and a specialised forum; hence the civil court’s jurisdiction is impliedly excluded.
  • Argued that, because of the statutory bar, the respondent should have pursued remedies under the Act instead of filing a civil suit.
  • (Attempted, but was not allowed, to raise a limitation plea for the first time before the Supreme Court.)

Respondent (Plaintiff)

The opinion does not contain a detailed account of the respondent’s legal arguments; the court’s summary indicates reliance on common-law rights after finding that the Board did not comply with statutory prerequisites.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
South Madras Electric Supply Corpn. Ltd. v. T.L. Jagannatha Aiyar, AIR 1960 Mad 374; (1959) 2 MLJ 446 Civil court jurisdiction where electricity lines are laid without complying with statutory requirements. Supported the High Court’s view that, absent an approved scheme and consent, the plaintiff could sue in civil court for damages.
Amalgamated Electricity Co. Ltd. v. N.S. Bathena, AIR 1964 SC 1598; (1964) 7 SCR 503 Liability of electricity authorities for unauthorised acts causing damage. Cited to reinforce the availability of common-law remedies when statutory safeguards are breached.
Dhulabhai v. State of M.P., (1968) 3 SCR 662; AIR 1969 SC 78 Tests for exclusion of civil-court jurisdiction; particularly, that exclusion is not inferred if statutory provisions are not complied with. The Supreme Court applied the first proposition to hold that civil-court jurisdiction was not excluded because the Board had not acted under a sanctioned scheme or in conformity with the Act.

Court's Reasoning and Analysis

The Court reiterated the settled principle that exclusion of civil-court jurisdiction cannot be lightly inferred. Referring to the Dhulabhai test, it found:

  • The transmission line was laid without the respondent’s consent and without any sanctioned or approved scheme.
  • Because the Board did not comply with the statutory framework, it could not invoke the Act’s protective provisions or special forum.
  • Therefore, the civil court retained jurisdiction, and the respondent was entitled to common-law damages.
  • Given these concurrent factual findings by the lower courts, no ground existed to disturb the High Court’s decree.

Holding and Implications

APPEAL DISMISSED. The Supreme Court affirmed the High Court’s judgment: the mandatory injunction for removal of the line remains set aside, but the award of past and continuing damages in favour of the respondent is upheld. No order as to costs.

Implications: The decision underscores that electricity authorities cannot rely on statutory bars when they act outside the scope of the governing Acts. It reaffirms the Dhulabhai principles on civil-court jurisdiction and signals that unauthorised encroachments by utilities may incur continuing liability for damages, even where injunctive relief is withheld.

To access the original judgment, please Sign In or Subscribe.

    M.P Electricity Board, Jabalpur v. Vijaya Timber Co. .

    K. Venkataswami, J.— The appellant/defendant in Civil Suit No. 9-A of 1967 on the file of the Court of Civil Judge, Class-I, Rajnandgaon, has suffered a decree at the hands of the trial Judge, directing the removal of the electric line with poles situated in the land bearing Kh. No. 908/2 area 1.32 acres at Village Nandai. In addition to that, the appellant was also directed to pay a sum of Rs 1770 towards past damages and to pay future damages @ Rs 5 per day to the plaintiff (respondent herein) from the date of institution of suit till the removal of electric line.

    2. Aggrieved by the decree, an appeal was preferred to the First Additional District Judge, Durg, at Rajnandgaon. The appellate court dismissed the appeal by judgment and decree dated 5-2-1984. Still aggrieved, he preferred a second appeal in the High Court of Madhya Pradesh, Jabalpur. The High Court modified the decree by removing the mandatory injunction directing the defendant to remove the electric line with poles but sustained the decree for damages, past and future. The above appeal is directed against the judgment and decree of the High Court.

    3. Shri Pallav Shishodia, learned counsel appearing for the appellant, attempted to argue the appeal by raising a point which was neither raised in the pleadings nor argued in the courts below, namely, that the suit was barred by limitation. As this question of limitation on the facts of this case was not one of pure question of law but a mixed question of fact and law, we did not permit the learned counsel to raise this point for the first time before us.

    4. The learned counsel for the appellant, therefore, has to confine his argument as to the bar of the suit as raised before the High Court. By referring to Sections 12, 19 and 52 of the Indian Electricity Act, 1910, the learned counsel submitted that the suit, as filed in the present case was barred. In other words, according to the learned counsel, the civil court could not adjudicate the dispute raised in the suit for which remedies and forum are provided under the Act itself and the plaintiff/respondent ought to have pursued those remedies before the forum mentioned in the Act. The contention of the learned counsel for the appellant was that in view of the forum provided in the Act for resolving the dispute, the suit must be taken to have been barred impliedly under Section 9 of the Code of Civil Procedure.

    5. For appreciating the above contention, minimal facts may now be noted.

    6. The grievance of the plaintiff/respondent was that in the land belonging to him which has been set apart for industrial use, the appellant Board had taken 33 KV high tension transmission lines over the construction already started in the said land without its consent and as such the erection was unauthorised and liable to be removed. The defence was that there was no erection when the high tension transmission lines were taken through the land and the plaintiff/respondent never objected to taking those lines. However, the findings of all the three courts are to the effect that the transmission lines were laid without the plaintiff's consent after the plaintiff has already constructed a portion of its sawmill, that the overhead transmission lines are likely to endanger the property of the plaintiff, that there was no sanctioned scheme for the transmission lines and that the plaintiff suffered damages @ Rs 5 per day.

    7. In the light of the above concurrent findings of all the three courts, we do not think that there is any case for the appellant to sustain the defence it has taken in the written statement.

    8. The High Court has given a finding after referring to Section 12 of the Electricity Act, 1910 as well as the provisions of the Electricity (Supply) Act, 1948, that the provisions of the latter Act have no application to the facts of the case as admittedly, the transmission lines were not laid under any approved scheme. The High Court further held that the appellant Board having laid the transmission lines without taking the consent of the plaintiff, cannot be treated as having acted in accordance with the provisions of the Indian Electricity Act to take shelter under those provisions. Therefore, according to the High Court, the remedy of the plaintiff was not to take recourse under the provisions of the Act but to file a civil suit for compensation/damages under the common law. In support of this conclusion, the High Court has relied on a judgment of the Madras High Court in South Madras Electric Supply Corpn. Ltd. v. T.L Jagannatha Aiyar AIR 1960 Mad 374, (1959) 2 MLJ 446 and also another judgment of this Court in Amalgamated Electricity Co. Ltd. v. N.S Bathena AIR 1964 SC 1598, (1964) 7 SCR 503.

    9. It is well settled that the exclusion of jurisdiction of civil court cannot be readily inferred and the normal rule is that civil courts have jurisdiction to try all suits of a civil nature except those of which cognizance by them is either expressly or impliedly excluded. A Constitution Bench of this Court in Dhulabhai v. State of M.P (1968) 3 SCR 662, AIR 1969 SC 78, (1968) 22 STC 416 had laid down several propositions in this regard. The first proposition is apposite for the facts of this case. It reads as under:

    “(1) Where the statute gives a finality to the orders of the special tribunals the civil court's jurisdiction must be held to be excluded if there is adequate remedy to do what the civil courts would normally do in a suit. Such provision, however, does not exclude those cases where the provisions of the particular Act have not been complied with or the statutory tribunal has not acted in conformity with the fundamental principles of judicial procedure.”

    10. In the light of the findings of the courts below which we have extracted above, we do not think that the High Court has committed any error in holding that the suit was maintainable and also in granting the modified relief.

    11. Before parting with the case, we may observe that we gave an opportunity to the appellant to settle the matter outside the court but the learned counsel appearing for the appellant after getting instructions reported that the settlement was not possible. It is unfortunate. In the result the appeal is dismissed. However, there will be no order as to costs.