Against the judgment of the learned Single Judge dated 11th
February, 2009 passed in C.W.J.C. No. 16495 of 2008 and 16496 of 2008
------
1. THE EAST CENTRAL RAILWAY(ENGINEERING DEPARTMENT),
THROUGH ITS CHIEF ADMINISTRATIVE OFFICER
(CONSTRUCTION) SOUTH EAST CENTRAL RAILWAY,
MAHENDRUGHAT, PATNA.
2. THE CHIEF ENGINEER (CONSTRUCTION) NORTH II, EAST
CENTRAL RAILWAY, MAHENDRUGHAT, PATNA.
3. THE DEPUTY CHIEF ENGINEER (CONSTRUCTION) EAST
CENTRAL RAILWAY, MAHENDRUGHAT, PATNA.
4. EXECUTIVE ENGINEER (CONSTRUCTION)/WORKS, EAST
CENTRAL RAILWAY, MAHENDRUGHAT, PATNA.
5. EXECUTIVE ENGINEER, CONSTRUCTION INCHARGE, EAST
CENTRAL RAILWAY, HAJIPUR--------Appellants in both the appeals.
Versus
M/S INTERLINK COAL PVT.LTD., A COMPANY INCORPORATED
UNDER THE INDIAN COMPANIES ACT, 1956, HAVING ITS HEAD
OFFICE AT SHUKLA COLONY, HINOO, RANCHI, THROUGH ITS
MANAGING DIRECTOR SRI RASENDRA KUMAR SINGH SON OF
LATE RAJENDRA SINGH, RESIDENT OF JANKI NIWAS, SHUKLA
COLONY, HINOO, P.S. HINOO, DISTRICT RANCHI (JHARKHAND)
---------------------------RESPONDENTS IN BOTH THE APPEALS.
-------
For the Appellants : M/S. N. K. Agrawal, Sr. Advocate Railways &
Dr. Kumar Uday Pratap
For the Respondent : M/S. Anil Kumar Singh, Sr. Advocate &
Raj Kishore Prasad.
PRESENT
THE HON'BLE THE CHIEF JUSTICE
THE HON'BLE MR. JUSTICE DR. RAVI RANJAN
---------
Koshy, C.J: On 22.7.2007, the East Central Railway invited tenders for the
construction of several residential units, staff quarters and other
miscellaneous works at Sonepur/Hajipur. The estimated cost of the project
was Rs.106788840.20 paise. The tender stipulated price variation clause in
Chapter - 3. Clause 34 of the said terms and conditions provides for price
variation. Clause 34(A) is the general conditions for price variation. Clause
34(C) stipulates ceiling on price variation. As per Clause 34(C)(i), the
adjustment ie. reimbursements/recovery based on price indices, shall be
made only if to the extent the amount to be adjusted is in excess of 5% of
the amount payable to the contractor as per accepted rates. As per Clause
34(C)(ii), the total amount of adjustments ie. increase/decrease in the
payment to the contractor shall be limited to 10% ie. (15% - 5% (floor
price)) of the amount finally payable to the contractor as per accepted rates
for the contracts where the period of completion is between 1 to 2 years. As
per Clause 34(C)(iii), the total amount of adjustment ie. increase/decrease
in the payment to the contractor shall be limited to 20% ie. (25% - 5%
(floor price)) of the amount finally payable to the contractor as per accepted
rates for the contracts where the period of completion is more than two
years. That from perusal of the ceiling on price variation clause is evident
that the total amount of adjustment shall be limited to 10% of the amount
finally payable to the contractor where the period of completion is upto two
years and 20% adjustment is in the case of period of completion of more
than two years. In the present case, the period of completion of the work is
eighteen months and, therefore, the upper ceiling limit is only upto 10%.
Pursuant to the tender notification, several contractors, including the
petitioner, submitted tender papers, along with the earnest money deposits
in the form of fixed deposit. The tender was opened on 5.9.2007. The
offer of the petitioner, being the lowest, was accepted. The acceptance was
communicated to the petitioner in writing on 23/24.1.2008. The petitioner
started the work. A final agreement as contemplated under the terms and
conditions, After the acceptance of the quotation made by the petitioner, as
per Annexure - 1 dated 28.9.2007, there was a change in policy, whereby
the ceiling limit prescribed at 15-25% stood deleted. In the opening
sentence of the said circular, it is stated that the modified clause would
have prospective effect in all future work contracts. On 2.2.2008 and
5.5.2008, after starting the work, the petitioner requested the appellant for
deleting the price variation clause, in view of the amendment. On 8.7.2008,
the petitioner sent Annexure - 4 letter stating the difficulty in signing the
agreement unless price variation clause is deleted. Annexure - 4 reads
thus:
in clause 34(C) as per policy decision of the Ministry of Railway
(Railway Board) issued vide letter no. 2007/CEI/CT/18, New Delhi
dated 28.9.2007.
Dear sir,
With reference to the captioned subject, we would like
to submit that we have been allotted works contract vide Acceptance
No.ECR/CAO/Con/WT/474/450 dated 23.01.08 for the work of
„providing 38 units type III, 86 units type II and 36 units type I quarter
and other miscellaneous work at Konharaghat, Hajipur‟.
In terms of the agreement, we have been directed to
utilise Cement PPC confirming IS 1489 (Pt. I) and TMT steel basis
(Grade fe 415) conforming to IS: 1786 of any dia.meter from
Tata/Sail/RINL. Accordingly we quoted the basic rates of thesaid
quality of cement and steel as prevailing in the market at that point of
time.
However, the agreement consists of the Price
Variation Clause. In clause 34(c)(ii) & (iii) of the agreement, there is a
ceiling on price variation, which inter alia provides that the total
amount of adjustment shall be limited to 10% (15% - 5% (floor price))
in case of work to be completed within two years and 20% (25% - 5%
(floor price)) in case the period of completion is more than 2 years.
Before the agreement was signed by both the parties,
we could be able to know that the Govt. of India, Ministry of Railway
(Railway Board) has taken a policy decision to delete the clause
relating to Ceiling on price variation so far as it relates to upper limit.
The said policy decision was communicated to all F.A & CAOs of all
Indian Railways vide letter no. letter no.2007/CEI/CT/18, New Delhi
dated 28.9.2007 issued under the signature of Executive Director Civil
Engineering, Railway Board, New Delhi.
We, therefore, request you to kindly delete the clause
34(C)(ii) & (iii) in terms of the policy decision of the Govt. of India,
Ministry of Railway (Railway Board), else, we are unable to sign the
agreement in questioin, which consists of ceiling clause on price
variation. Thesaid clause is actually in the teeth of the policy decision
of the Govt. of India, Ministry of Railway (Railway Board).
Thanking you,
Yours faithfully,
For: M/s Interlink Coal (P) Ltd
Sd/-
Managing Director"
Despite the above letter, the appellant Railway took the stand that since the
policy decision was after the acceptance of the tender submitted by the
petitioner, no change can be effected. Finally, on 18.3.2008, a formal
agreement was entered into between the parties on the same terms and
conditions as stipulated in the tender form retaining the ceiling clause. On
12.11.2008, the writ petition was for incorporating the price variation
clause in the agreement, in view of the amendment to the policy dated
28.9.2007.
2. The learned single Judge found that
the petitioner seeks only a just
compensation for unanticipated abnormal rise in prices of its basic
ingredients required for fulfillment of the contract. On the other hand, if
compensation, accordingly, is not permitted, then Railway would certainly
be getting its work done at a cost less than legitimate due and would, thus,
be unjustly enriching itself because of factors beyond control of both the
contracting parties. That would be unjust and unfair.
The learned single
Judge held that the policy decision is violative of Article 14 of the
Constitution and the Railway cannot act unfairly. The writ petition was
allowed in the following manner:
Thus, in my view, the writ petition must succeed. Clause 34
of the GCC, as applicable to the petitioner in the facts and
circumstances noted above, would apply in the form modified by the
policy of the Railways, as contained in Annexure-1, and Railways
would be bound to give benefit thereof to the petitioner. In case
Railway itself has some reservation in that regard then it would be
duty bound to supply the goods by procuring them in their stocks but
Railways certainly cannot avoid both the situations to the detriment of
the petitioner. I order accordingly.
3. The appellant contended that the policy decision dated 28.9.2007 was
prospective and should apply only to those tenders which were floated after
the policy decision and not to apply to the contracts entered after the policy
decision, where the tenders were floated prior to policy. Therefore, the
petitioner is not entitled to get the benefit stipulated in the policy dated
28.9.2007.
4. It is true that the publication of the tender documents by the Railways
is not an offer. It is only an invitation or, in other words, „a chaffer to
offer‟. Various contractors made quotations (offers) in response to the
tender notification. The tender quotations were opened on 5.9.2007.
Earnest money was also deposited by the petitioner. Having found that the
petitioner fulfilled all the conditions, the Railway accepted the offer of the
petitioner, being the lowest tenderer. The acceptance of the tender was
communicated to the petitioner on 23/24.1.2008. The petitioner sent two
letters dated 2.2.2008 and 5.5.2008 requesting deletion of the price
variation clause, in view of the policy dated 28.9.2007. Even though the
petitioner informed the appellant Railways by letter dated 8.7.2008 that it
cannot sign the agreement with a clause incorporating ceiling on price
variation, the request having been refused, the petitioner on 18.3.2008
signed the formal agreement incorporating the tender condition
notwithstanding the subsequent policy decision of the Railways. Therefore,
it is contended, the petitioner is bound by the terms and conditions under
the agreement and the writ petition will not lie.
5. It is settled law that in contractual matters, the power of this Court for
interference is very limited. The award of a contract, whether it is by a
private party or by a public body or the State, it is essentially a commercial
transaction. In arriving at a commercial decision, considerations which are
of paramount importance are commercial considerations. Price may not
always be the sole criterion for awarding a contract. The Court cannot
substitute its own decision for the decision of an expert evaluation
committee. Award of contract is reached by process of negotiations at
several tiers and more often, such decisions are made qualitatively by
experts. Quashing decisions may impose heavy administrative burden on
the administration and lead to increased and unbudgeted expenditure (see
Tata Cellular v. Union Of India. - (1994) 6 SCC 651). A contract between
the parties is in the realm of private law. The contract in question is not a
statutory contract. The dispute relating to interpretation of the terms and
conditions of a contract could not have been agitated in a petition under
Article 226 of the Constitution of India. Of course, it is true, if the State or
its agencies act arbitrarily violating Article 14 of the Constitution of India
or as if there is procedural illegalities, a writ will lie even in contractual
matters, as held by the apex Court in Food Corporation of India and
another v. SEIL Ltd and others ((2008) 3 SCC 440), ABL International
Ltd v. Export Credit Guarantee Corporation of India Ltd ((2004) 3
SCC 553 and Karnataka State Forest Industries Corporation v. Indian Rocks (2009(1) SCC 150).
6. But, in this case, the question is whether any arbitrary or
discriminatory action was taken by the Railways so as to justify
interference in contractual matters. The tender notification was published
much prior to the policy decision. By open eyes, the petitioner made the
quotation. As a prudent and responsible contractor, he would have quoted
the price after consultation with technical and financial experts. The other
tenderers also quoted the amount considering the terms and conditions in
the tender notification, knowing fully well that there is a ceiling on price
escalation. The quotation made by the petitioner was the lowest. Since it
was the lowest quotation, the petitioner‟s quotation was accepted before
change in the policy decision. Further, if the price escalation limit was not
there, others also might have quoted lesser amounts. If the ceiling of price
escalation is taken away only with regard to the petitioner, who was the
lowest quoted tenderer, then it would have been violative of Article 14 of
the Constitution of India. It is for the petitioner to study the market
conditions and make quotations. Having found that the petitioner‟s
quotation was the lowest, he was awarded the contract and even letter of
acceptance was sent before the change in policy condition and there left
only the signing of the formal agreement by the parties. The petitioner had
sent two letters expressing his difficulty in signing the agreement unless the
ceiling clause is deleted. But the appellant did not agree for the same. The
agreement was also signed. Now the petitioner cannot go back from the
terms of the tender accepted by them. In fact, it was stated in that circular,
by which the change in policy was made, that it is prospective in nature.
Prudent contractors submitted their tenders and quoted the amount taking
into account that there would not be any price escalation. It cannot be
changed after the date fixed for submission of tenders and opening of the
tenders. Then only arbitrariness will come into surface. The agreement is in
the nature of a private contract, the tender quotation was made by the
petitioner with open eyes and the petitioner is bound by the general
conditions. The terms and conditions of the agreement cannot be modified
in a writ petition merely because one party to the contract is an
instrumentality of the State. The Railways also cannot say that since written
agreement was signed later, an agreement condition contrary to the tender
conditions should be incorporated in the written agreement thereby making
an additional burden on the contractor. We are of the view that the stand of
the Railways that the petitioner is bound by the tender conditions, on the
basis of which quotation was submitted and accepted. It cannot be altered
on the basis of a subsequent policy change made after the opening and
acceptance of the tender. It cannot be stated that there is any arbitrariness
on the part of the Railways so as to warrant interference by this Court in a
contractual matter. The petitioner-contractor was not able to convince us
that there is violation of Article 14 of the Constitution or discrimination
shown to him by the Railways. There is no patent illegality or procedural
violation. In such circumstances, this Court cannot re-write the contracts
between the parties. There is no scope for judicial review.
7. Therefore, we allow the Letters Patent Appeal and the impugned
judgment of the learned single Judge is set aside.
(J. B. Koshy, C.J.)
Dr. Ravi Ranjan, J., I agree.
(Dr. Ravi Ranjan, J.)
Patna High Court,
The 6th May, 2009.
AMIN/ (A.F.R.)