Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Smart Summary

Factual and Procedural Background

This appeal under Section 39 of the Arbitration Act challenges the decision of the learned Subordinate Judge of Bhubaneswar who made an award Rule of the Court under Section 17 of the Act. Respondent No. 1, a firm of contractors, undertook the construction of the School of Mining Engineering at Keonjhar pursuant to a contract dated 22-8-1962, with the work order given on 30th June 1981. Construction of the ground floor was completed by 31-12-1961 and the first floor by 30th June 1962. The claimant-contractor sought appointment of an arbitrator under Section 8 of the Arbitration Act, and the Additional Chief Engineer appointed Respondent No. 2 as arbitrator. When the contractor’s application for revocation of the arbitrator's authority was rejected, the contractor moved the Court in Civil Revision No. 489 of 1978. A learned single Judge, by judgment dated 15-5-1979 (reported in 48 Cut VT 138 : AIR 1980 NOC 31 (Ori) Consolidated Construction Co. v. State of Orissa), allowed the application and appointed Sri Abhimanyu Misra, a retired Judge, as arbitrator. Both parties expressed no objection to his appointment. The arbitrator gave the award on 9-7-1980. Objections by the State of Orissa were overruled by the Subordinate Judge who made the award a Rule of the Court.

Legal Issues Presented

  1. Whether the claim leading to arbitration was barred by limitation and thus not tenable in law.
  2. Whether the State Government's counter-claim was properly considered and justified by the arbitrator.
  3. Whether the contractor’s claims were considered in a manner that could result in double payment under the same head.
  4. Whether the enhancement of the claim during the proceedings was justified.
  5. Whether the arbitrator had jurisdiction to award interest from the alleged date of dues, including pendente lite interest.
  6. Whether the arbitrator had jurisdiction to arbitrate in the absence of a joint reference.

Arguments of the Parties

Appellant's Arguments (State of Orissa)

  • The claim was barred by limitation at the time the dispute was raised and should have been rejected by the arbitrator.
  • The counter-claim advanced by the State was not properly discussed or justified by the arbitrator.
  • The manner of considering claims allowed the contractor to be paid more than once for the same head of claim.
  • The claim was unjustifiably enhanced during the proceedings beyond the contractual rate.
  • The arbitrator lacked jurisdiction to grant interest prior to the date of the claim and to award pendente lite interest without statutory or contractual basis.
  • The arbitrator had no jurisdiction to arbitrate as the award was not a result of a joint reference.

Respondent's Arguments (Contractor)

  • The final bill for the work was drawn up on 19-4-1980, during the pendency of arbitration, negating the limitation plea.
  • The arbitrator duly considered and rejected the counter-claim with adequate reasoning.
  • No evidence supports the allegation of double payment for the same claims.
  • The enhancement of the claim during proceedings is not verifiable due to the unreasoned award, and no mistake is apparent on the face of the award.
  • The arbitrator had jurisdiction to award interest, including pendente lite interest, supported by Supreme Court precedents such as Ashok Construction Company v. Union of India.
  • Both parties participated in arbitration proceedings without objection to jurisdiction, estopping the State from raising jurisdictional objections at this stage.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Consolidated Construction Co. v. State of Orissa, 48 Cut VT 138 : AIR 1980 NOC 31 (Ori) Appointment of an arbitrator with integrity and judicial experience to avoid objections. Used to justify appointment of retired Judge Abhimanyu Misra as arbitrator without objection from parties.
Wazir Chand v. Union of India, AIR 1967 SC 990 Arbitrator’s authority to decide limitation issues once dispute is referred to arbitration. Applied to hold that limitation did not bar the claim as final bill was drawn during arbitration.
Firm Madanlal Roshanlal Mahajan v. Hukumchand Mills Ltd., AIR 1967 SC 1030 Arbitrator’s jurisdiction to award interest including pendente lite interest if claim referred to arbitration. Supported the validity of awarding interest from date of dues and pendente lite interest.
Union of India v. Bungo Steel Furniture Pvt. Ltd., AIR 1967 SC 1032 Implied jurisdiction of arbitrator to grant interest on awarded amounts when disputes including interest are referred. Confirmed arbitrator’s power to grant interest post-award as an implied term of reference.
State of Madhya Pradesh v. Saith and Skelton (P) Ltd., AIR 1972 SC 1507 Arbitrator’s power to award pendente lite interest when all disputes are referred. Applied to uphold arbitrator’s award of interest for the period during arbitration proceedings.
Ashok Construction Company v. Union of India, (1970) SCD 530 Arbitrator’s jurisdiction to entertain claim for interest under arbitration agreement unless expressly excluded. Relied upon to hold that arbitrator’s award of interest was valid and not excluded by arbitration terms.
Thawardas Pherumal v. Union of India, AIR 1955 SC 468 Requirement of joint assent for arbitration reference; arbitrator’s jurisdiction depends on existence of dispute. Used to reject belated jurisdictional objection as parties had acquiesced and participated in arbitration.
Madhubala Pvt. Ltd. v. Naaz Cinema, AIR 1972 Delhi 263 Assent to terms of reference confers jurisdiction on arbitrator. Applied to affirm that parties’ conduct amounted to assent to arbitration jurisdiction.
Dilip Construction Company v. Hindustan Steel Ltd., AIR 1973 Madh Pra 261 Existence of dispute essential for arbitrator’s jurisdiction; failure to pay alone does not create dispute. Supported holding that jurisdiction existed as dispute was established and parties participated.
Khardah Company Ltd. v. Raymon & Co. (India) Pvt. Ltd., AIR 1962 SC 1810 Arbitrator’s jurisdiction depends on arbitration agreement; absence of agreement results in want of jurisdiction. Referenced to emphasize that jurisdiction cannot be cured by acquiescence but parties here had agreed.
Union of India v. Radhanath Nanda, AIR 1961 Ori 143 Estoppel against raising jurisdictional objections after participation in arbitration. Applied to hold appellants estopped from challenging arbitrator’s jurisdiction at this stage.
Bokaro and Ramgur Ltd. v. Dr. Prasun Kumar, AIR 1968 Pat 150 (FB) Estoppel against challenging jurisdiction after acquiescence and participation. Supported holding that State could not raise jurisdictional objection after full participation.

Court's Reasoning and Analysis

The Court first examined the limitation issue, relying on Section 37(1) of the Arbitration Act and the Supreme Court decision in Wazir Chand v. Union of India to hold that limitation applies to arbitration similarly as in court proceedings. Since the final bill was drawn during the pendency of arbitration proceedings, the limitation plea was rejected. The Court then considered the counter-claim, finding that the arbitrator adequately dealt with and rejected it with reasoning, particularly in relation to excess departmental materials. The allegation of double payment was dismissed due to lack of evidential foundation. The contention regarding enhancement of the claim was unverifiable given the unreasoned award and was not accepted. The Court gave significant weight to Supreme Court precedents establishing the arbitrator’s jurisdiction to award interest, including pendente lite interest, where the claim is referred to arbitration, notably relying on Ashok Construction Company and related cases. Finally, the Court addressed the jurisdictional objection, holding that since both parties had participated fully in the arbitration and had not objected earlier, the State was estopped from raising the issue. The Court applied established principles that jurisdiction depends on the existence of a dispute and assent to arbitration, and that lack of joint reference can be cured by court order or acquiescence. Consequently, all objections were overruled.

Holding and Implications

DISMISSED WITH COSTS

The appeal was dismissed with costs assessed at rupees two hundred. The Court upheld the award made by the arbitrator and confirmed the rule of the court made by the Subordinate Judge. The decision directly affects the parties by affirming the validity of the arbitration award and rejecting all objections raised by the State of Orissa. No new precedent was established beyond applying existing principles and prior case law.

    State Of Orissa And Another v. M/S. Consolidated Construction Company (Engineers & Contractors) And Anther

    1. This appeal under Section 39 of the Arbitration Act calls in question the decision of the learned Subordinate Judge of Bhubaneswar by which he has made an award Rule of the Court under Section 17 of the Act. Respondent No. 1—a firm of contractors—undertook construction of the School of Mining Engineering at Keonjhar by entering into a contract in the standard F-2 Form on 22-8-1962. Work order had, however, been given on 30th of June, 1981, and the construction of the ground floor was over by 31-12-1961, and of the first floor by 30th of June, 1962. The claimant-contractor have notice under Section 8 of the Arbitration Act for appointment of an arbitrator. The Additional Chief Engineer appointed respondent No. 2 as the arbitrator. When the contractor's application for revocation of the authority of the appointed arbitrator was rejected, the contractor had moved this Court in Civil Revision No. 489 of 1978 and a learned single Judge by his Judgment on 15-5-1979 reported in 48 Cut VT 138 : (AIR 1980 NOC 31 (Ori) Consolidated Construction Co. v. State of Orissa allowed the application and appointed Sri Abhimanyu Misra, a retired Judge of this Court, as arbitrator. From, paragraph 7 of the reported decision, it appears:—

    “………In course of the hearing of this case, I wanted, to know from both the parties if they had any objection to the appointment of retired justice Shri Abhimanyu Misra as the arbitrator in this case. None of the parties expressed any objection against him…………”

    The learned single Judge further observed:—

    “………To avoid further delay and to allay all apprehensions in the mind of the petitioner. I deem it just and proper to directly appoint an arbitrator of integrity, personality and judicial experience so that there would be or could be no scope for any objection on that score by any of the parties…………..”

    The new arbitrator after hearing parties cave his award on 9-7-1980. On behalf of the State of Orissa, objection was raised to the award. After hearing both parties, the learned Subordinate Judge overruled the objections and made the award a rule of the court.

    2. Five objections in the main have been raised in this appeal by leaned Additional Government Advocate:—

    (i) The claim which led to reference to arbitration was barred by limitation by the time the dispute was raised and, therefore, the arbitrator should have held that the claim was not tenable in law:

    (ii) The State Government had advanced a counter-claim which has not been properly discussed and the arbitrator has rejected the claim without indicating any ground for in

    (iii) The manner in which the different claims have been considered dearly indicates that the contractor will ultimately be paid mere than once under the sane head of claim which should not have been permitted;

    (iv) The claim has been allowed to be enhanced in the midst of the proceeding which was not justified:

    (v) The claim of interest from the alleged date of dues could not have been granted by the arbitrator, inasmuch as, there was no power in the arbitrator to grant interest prior to the date of claim in any event and the pendente lite interest also could not be granted in the present ease, as it was not covered by any of the principles indicated by the Supreme Court.

    3. Admittedly, the arbitrator has not Riven any reasoning for the award. In the operative part thereof, the arbitrator has stated:—

    “The parties addressed elaborate arguments in support of their respective contentions and referred to the documents and other material in respect of different items of claim, and counterclaim. Having Riven my full and careful consideration to the claims of the petitioner and counter-claim made be the opposite parties, their contentions, contained in the written statements, the documents referred to and relied upon and arguments advanced in detail in respect of each item of the claims and counter-claim. I proceed to record my conclusions and findings as detailed below:…………”

    As against all the thirtyfour items excepting item No. 26, the arbitrator has only indicated the amount in case he has allowed the whole or a part of the claim. As against item No. 25, the claim and counter-claim have been dealt with at some length.

    Section 37(1) of the Arbitration Act provides that all the provisions of the Indian Limitation Act of 1908 would apply to arbitration as they apply to proceedings in court. The Supreme Court pointed out in the case of Wazir Chand v. Union of India, AIR 1967 SC 990: (at p. 993)

    “There is no doubt that Cl. (1) of Section 37 of the Arbitration Act deals only with the authority of the arbitrator to deal with and decide any dispute referred to him: it has no concern with an application made to the Court to file an arbitration agreement and to refer a dispute to the arbitrator. After an agreement is filed in Court and the matter is referred to the arbitrator, it is for the arbitrator to decide by the application of the law contained in the Limitation Act, whether the claim is barfed.…………

    This view has received support from subsequent decisions. The question of limitation has not been specifically dealt with in the award, but as it appears the final bill for the work done in the sixties was finalised on 19-4-1980 and the arbitrator's records support this stand of Mr. Palit for the contractor. In view of the fact that the final bill is dated 19-4-1980, when the arbitration proceeding itself was pending, the question of limitation loses importance. Confronted with this situation, learned Additional Government Advocate instead of Dressing the question of limitation, contended that the dispute itself seemed to be premature if the final bill had not been drawn up till April, 1980. Such a contention had never been raised when the arbitrator was appointed or when this Court directed the new arbitrator to give his award expeditiously. The State of Orissa participated in the proceedings placed records, concurred in the extension of time and did not raise the plea of the proceedings being premature. While the question of limitation does not arise in view of the fact that the final bill was drawn up in April, 1980. I do not think, in the facts and circumstances of the case, it would be at all appropriate to hold that the dispute was premature and therefore, the reference to arbitration was not tenable.

    4. Admittedly, there was a counterclaim. The arbitrator did refer to the counter-claim and while dealing with the item No. 25, stated:—

    “Item No. 25 in the claim petition and items 1 and 2 of counter claim made by the respondents are taken up together. Item No. 25 of the claim petition is in substance a defence to and denial of the counter claims made by the respondents towards the value of the excess departmental materials alleged to have been supplied to the claimants and not consumed in the work nor returned after completion of the work. In the counter claim item No. 1 enumerates 14 different items of departmental materials which are alleged to have remained in excess with the contractor and not returned by him. The value of the said materials is estimated at Rs. 82,330.76 and as per stipulation in the agreement, together with penalty of 5 times, the total amount claimed is Rs. 4,11,570/-. Counter claim No. 2 is for interest on the aforesaid amount. In item No. 25 of the claim petition these alleged excesses in the departmental material issued has been denied and it is asserted that departmental materials issued have been fully consumed in the work. Though in the counter claim 14 items were mentioned, during the course of the proceeding, the respondents modified and reduced their claim to cement. M.S Rods, coal paint and asphalt, turpentine, D.B Oil and empty cement bags. They also modified and reduced the quantities originally alleged. After considering the material placed before me and perusal of the documents sought to be relied upon by the respondents I reject the counter claim of any excess material having been left with claimant petitioner. It follows that respondents are not entitled to recover any amount towards such excess material as made out in their counter claim and much less any interest on the value of the same.”

    In view of what has been stated above, the criticism of learned Additional Government Advocate that the arbitrator rejected the counter claim without any discussion is uncharitable. The arbitrator is entitled to give reasons, but there is no obligation for him to support his conclusion in favour of or against a party by giving reason. I must, therefore, hold that the tenanbility of the counter claim had been duly dealt with by the arbitrator and he has found that the counter claim has no justification. Keeping the nature of the award in view. I do not think it is open to the State to raise any further challenge to the finding.

    5. According to learned Additional Government Advocate, this is a case where same payment had been made to the contractor. It is maintained that the contractor laid claim in respect of certain items for which he had once been paid. The manner in which the claim has been treated, according to learned Additional Government Advocate, yields room for the same claim to have been taken into account more than once and, therefore, it cannot be ruled out that the claimant has not received payment on more than one occasion for the same head. I suggested to learned Additional Government Advocate to demonstrate with reference to actual record whether there is any foundation for the allegation. There is nothing on record which yields scope for the foundation of the argument. I therefore, do not think, there is any merit in the contention even if such a contention was maintainable.

    6. It was the next contention of learned Additional Government Advocate that there has been enhancement of the claim in the midst of the proceeding. According to him the rate at which the claim has been allowed is higher than the contractual rate. Since this is an unreasoned award, the contention of learned Additional Government Advocate is not verifiable from the record and I do not find there is any mistake on the face of the award on that score.

    7. The last contention is in regard to payment of interest. According to learned Additional Government Advocate, the Arbitrator has no jurisdiction to award interest for the period prior to the raising of the dispute and he has also no jurisdiction to award interest for the pendente lite period unless there be provision in the agreement, claim for interest is covered by statute such as the Interest Act, or the question of payment of interest has been specifically referred to for decision of the arbitrator. He has placed reliance on three decisions of the Supreme Court being Firm Madanlal Roshanlal Mahajan v. Hukumchand Mills Ltd. Indore, AIR 1967 SC 1030; Union of India v. Bungo Steel Furniture Pvt. Ltd., AIR 1967 SC 1032: and The State of Madhva Pradesh v. Saith and Skelton (P) Ltd., AIR 1972 SC 1507. In Firm Madanlal Roshanlal Mahajan's case (AIR 1967 SC 1030), the Court explained the earlier decision in Seth Thawardas Pherumal v. Union Of India, AIR 1955 SC 468, by saying:— (At p. 1032)

    “………But in later cases, this Court has pointed out that the observations in Thawardas's case (1955) 2 SCR 48 : (AIR 1955 SC 468), were not intended to lay down such a broad and unqualified proposition, see Nachiappa Chettiar v. Subramaniam Chettiar, (1960) 2 SCR 209 at p. 238 : (AIR 1960 SC 307 at p. 320), Satinder Singh v. Umrao Singh, (1961) 3 SCR 676 at p. 695 : (AIR 1961 SC 908, at p. 916). The relevant facts regarding the claim for interest in Thawardas's case (1955) 2 SCR 48 : (AIR 1955 SC 468), will be found (at Pp. 477 to 478 of AIR) and in Paras 2, 17 and 24 of the judgment of the Patna High Court reported in Union of India v. Premchand Satram Das, AIR 1951 Pat 201 at Pp. 204-205. The arbitrator awarded interest on unliquidated damages for a period before the reference to arbitration and also for a period subsequent to the reference. The High Court set aside the award regarding interest on the ground that the claim for interest was not referred to arbitration and the arbitrator had no Jurisdiction to entertain the claim. In this Court, counsel for the claimant contended that the arbitrator had statutory power under the Interest Act of 1839 to award the interest and in any event, he had power to award interest during the pendency of the arbitration proceedings under Section 34 of the Code of Civil Procedure, 1908, Bose, J. rejected this contention. It will be noticed that the judgment of this Court in Thawardas's case, (1955) 2 SCR 48 : (AIR 1955 SC 468), is silent on the question whether the arbitrator can award interest during the pendency of arbitration proceedings if the claim regarding interest is referred to arbitration. In the present case, all the disputes in the suit were referred to the arbitrator for his decision. One of the disputes in the suit was whether the respondent was entitled to pendente lite interest. The arbitrator could decide the dispute and he could award pendente lite interest just as a court could do so under Section 34 of the Code of Civil Procedure. Though, in terms. Section 34 of the Code of Civil Procedure does not apply to arbitrations, it was an implied term of the reference in the suit that the arbitrator would decide the dispute according to law and would give such relief with regard to pendente lite interest as the Court could give if it decided the dispute. This power of the arbitrator was not fettered either by the arbitration agreement or by the Arbitration Act, 1940…………”

    In Union of India v. Bungo Steel Furniture Private Ltd., AIR 1965 SC 1032, the Court referred to the same decision in AIR 1995 SC 466 and observed:— (at p. 1035)

    “……..but it should be noticed that the judgment of this Court in Thawardas's case (1955) 2 SCR 48 : (AIR 1955 SC 468), does not deal with the question whether the arbitrator can award interest subsequent to the passing of the ward if the claim regarding interest was referred to arbitration. In the present case, all the disputes in the suit, including the question of interest, were referred to the arbitrator for his decision. In our opinion, the arbitrator had jurisdiction, in the present case, to grant interest on the amount of the award from the date of the award from the date of the decree granted by Mallick, J. The reason is that it is an implied term of the reference that the arbitrator will decide the dispute according to existing law and give such relief with regard to interest as a Court could give if it decided the dispute. Though in terms, Section 34 of the Code of Civil Procedure does not apply to arbitration proceedings, the principle of that section will be applied by the arbitrator for awarding interest in cases where a Court of law in a suit having jurisdiction of the subject-matter covered by Section 34 could grant a decree for interest……”

    In the case of State of Madhya Pradesh v. Saith and Skelton (P) Ltd. (AIR 1972 SC 1507), the Supreme Court observed (at page 1614):—

    “From the decision in (1969) 1 SCR 105 : (AIR 1967 SC 1030) it is clear that if all the deputes are referred for arbitration, the arbitrator has power to award interest pendente lite, i.e during the pendency of the arbitration proceedings.

    In the case before us there is no controversy that all the disputes including a claim for payment of the amount with interest was referred to the arbitrator. The arbitrator, as pointed out earlier, found that the firm was entitled to the payment as price in the sum of Rs. 1,79,653.18 p. The arbitrator has further found that this amount became payable as balance price for the goods supplied by the firm on June 7, 1958, on which date the final inspection took place. It that is so Section 61 of the Sale of Goods Act 1930 squarely applies and it saves the right of the seller (in this case the firm) to recover interest where by law interest is recoverable………”

    Relying on these decisions, learned Additional Government Advocate contended that in the absence of clear proof that the claim of interest had also been referred to arbitration, the arbitrator could not have awarded interest. On the other hand, Mr. Palit for the claimant-respondent has relied upon a decision of the Supreme Court in the case of Ashok Construction Company v. Union Of India, (1970) SCD 530, where Shah, J. as the learned Judge then was, spoke for a Bench of three learned Judges thus:—

    “……In the view of the Deputy Commissioner under Clause 25 of the arbitration agreement, the arbitrator was not empowered to be into the questions of loss of goodwill, or damages by way of interest, and that the arbitrator could not award interest, by way of damages for detention of money and that is really what the claim for damages amounts to. The appellants made a claim for interest on the amount withheld after the due date and the arbitrator was competent to decide that claim. The arbitration agreement by clause 25 provides:—

    ‘Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions hereinbefore mentioned and as to the duality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing, whatsoever, in any way arising out of or relating to the contract designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whatever, arising during the progress of the work or after the completion or abendonment thereof shall be referred to the sole arbitration of the Superintending Engineer……’

    The terms of the arbitration agreement dad not exclude the jurisdiction of the arbitrator to entertain a claim for interest, on the amount due under the contract. The award of the arbitrator cannot be said to be invalid.”

    Relying on these observations of the Supreme Court in Ashok Construction Company's case, there have been a series of decisions in this Court that unless there be clear exclusion, the arbitrator would have jurisdiction to entertain a claim for interest. I am inclined to think that on the basis of this clear decision, the award of interest for the period from the date of detention of the money up to the raising of the claim as also for the period the arbitrator was in seisin of the proceeding was tenable and the award was not vitiated on that account.

    8. Learned Additional Government Advocate thereafter sought leave to raise a further, contention which had not been raised in the court below, namely that the arbitrator had no jurisdiction at all to arbitrate and the award made was illegal, inasmuch as it was not a Joint reference to him. In support of this proposition reliance has been placed on the observations of the Supreme Court in Thawardas's case (AIR 1955 SC 468) and a Bench decision of the Delhi High Court in Madhubala Pvt. Ltd. v. Naaz Cinema, AIR 1972 Delhi 263 as also a Bench decision of the Madhya Pradesh High Court in the case of Dilip Construction Company… v. Hindustan Steel Ltd.…., AIR 1973 Madh Pra 261. The Supreme Court observed in Thawardas's case (AIR 1955 SC 468) (at pages 469-70):—

    “A reference requires the assent of both sides. If one side is not prepared to submit a given matter to arbitration when there is an agreement between them that it should be referred, then recourse must be had to the Court under Section 20 of the Act and the recalcitrant party can then be compelled to submit the matter under sub-section (4).

    In the absence of either, agreement by both sides about the terms of reference, or an order of the Court under Section 20(4) compelling a reference, the arbitrator is not vested with the necessary exclusive jurisdiction.

    Therefore, when a question of law is the point at issue, unless both sides specifically agree to refer it and agree to be bound by the arbitrator's decision, the jurisdiction of the Courts to set an arbitration right when the error is apparent on the face of the award is not ousted. The mere fact that both parties submit incidental arguments about a point of law in the course of the proceedings is not enough……”

    Relying on these observations of the Supreme Court, the Delhi High Court in Madhubala's case (AIR 1972 Delhi 263) took the view that the appellant before it had assented to the terms of reference. In The Madhya Pradesh case (AIR 1973 Madh Pra 361) the Court held (at p. 265):—

    “(i) The existence of a difference or dispute is an essential condition for the arbitrator's jurisdiction to act under an arbitration clause in an agreement:

    (ii) The jurisdiction of an arbitrator depends not upon the existence of a claim or the accrual of a cause of action, but upon the existence of a dispute. A dispute implies an assertion of a right by one party and repudiation thereof by another

    (iii) A failure to pay is not a difference, and the mere fact that a party could not or would not pay does not in itself amount to a dispute unless the party who chooses not to pay raises a point of controversy regarding, for instance, the basis of payment or the time or manner of payment.”

    The Court referred to a later decision of the Supreme Court in the case of Khardah Company Ltd. v. Raymon & Co. (India) Private Ltd. , AIR 1962 SC 1810, where it was observed fat pages 1815-16):—

    “……But what confers jurisdiction on the arbitrators to hear and decide a dispute is an arbitration agreement as defined in Section 2(a) of the Arbitration Act and where there is no such agreement, there is an initial want of jurisdiction which cannot be cured by acquiescence. It may also be mentioned that the decision in (1860) 30 LJ Bcy 10 has been understood as an authority for the position that when one of the parties to the submission is under a disability that will not be a ground on which the other party can dispute the award if he was aware of it. Vide Russel on Arbitration 16th Edition, 320……”

    After quoting from the Supreme Court, the Madhya Pradesh High Court proceeded to say (at p. 267):—

    “When the respondent was not willing to join in the submission, the remedy of the appellant lay by way of an application under Section 20 of the Arbitration Act……”

    and support for this observation was drawn from Thawardas's case.

    In the instant case, there was an arbitration clause. An arbitrator was appointed to handle the dispute. Both parties were before, this Court on an earlier occasion when the arbitrator was substituted. Before the arbitrator both parties participated in the deliberations. They jointly applied for extension of time, as the award was not ready within four months from the date of reference. A counter claim was raised by the State requiring the arbitrator to go into that Question. No objection at all was raised until the appeal was heard in this Court about want of jurisdiction of the arbitrator. In these circumstances I do not think, it would at all be appropriate to entertain the contention of learned Additional Government Advocate of want of arbitrator's jurisdiction. On the other hand the single Judge decision of this Court in the case of Union of India v. Radhanath Nanda, AIR 1961 Ori 143 and the Full Bench decision of the Patna High Court in the case of Bokaro and Ramgur Ltd. v. Dr. Prasun Kumar, AIR 1968 Pat 150 (FB) should be applied and the appellants should be held estopped from raising such a contention.

    9. All the objections raised against the award having been overruled, this appeal is bound to fail and the same is accordingly dismissed with costs. Hearing, fee is assessed at rupees two hundred.

    Appeal dismissed.

    Use AI to get other relevant cases.

    Comments

    State Of Orissa And ... v. M/S. Consolidated Co...
    (Apr 28, 1981)