Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Clause (b) or Clause (c) of Section 15 of the Indian Arbitration Act.
  • Section 15 of the Indian Arbitration Act. Section 15
  • Section 15 of the Indian Arbitration Act
  • INDIAN LIMITATION ACT
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Clause (b) or Clause (c) of Section 15 of the Indian Arbitration Act.
  • Section 15 of the Indian Arbitration Act. Section 15
  • Section 15 of the Indian Arbitration Act
  • INDIAN LIMITATION ACT
Smart Summary

Factual and Procedural Background

The dispute arose from a contract dated 14 March 1951 between Himatsingka Timber Ltd. (the contractor) and the Government (representing Indian Railways) for the supply of first-class Sal sleepers. The contractor alleged that the sleepers were not supplied in accordance with certain data in the agreement and that it was paid at a rate lower than that provided for in the contract. The contractor claimed additional payment; that claim was disputed and referred to arbitration pursuant to the contract's arbitration clause.

The arbitrator, Mr. A. K. Gupta (Government Inspector of Railways), delivered a brief award dated 26 December 1961 directing the President of India (through the Sleeper Control Officer, S.E. Railway, Calcutta) to pay the claimant Rs. 3,024 towards the claim and Rs. 260 as costs (aggregate Rs. 3,284). The Government challenged the award by filing the present application to set it aside.

Legal Issues Presented

  1. Whether the arbitrator's award was of a time-barred claim and, if so, whether that constituted misconduct or an error warranting setting aside the award.
  2. Whether the arbitrator had jurisdiction to decide the dispute in view of an exception in the arbitration clause excluding matters in respect of which the Sleeper Control Officer or similar officials had "sole power, discretion, liberty, decision or jurisdiction".
  3. Whether an award directing the President of India to make payment is valid, and if not, whether the Court has power under Section 15 of the Indian Arbitration Act to correct an award that mistakenly names the President instead of the Union of India.

Arguments of the Parties

Government's Arguments

  • The award should be set aside because the arbitrator awarded a time-barred claim: final payment, according to the Government, was made in 1953 and the reference and award were made many years later (claim asserted to be beyond the statutory limitation period).
  • The arbitrator misconducted himself by making an award on a time-barred claim.
  • The arbitrator lacked jurisdiction because the arbitration clause expressly excluded matters where the Sleeper Control Officer (or related officers) had sole discretion — specifically, the contract permitted the Sleeper Control Officer to grant or refuse extensions of time and to make a final decision on extension issues; if a reduction of 2½% per month had been applied pursuant to a contractual provision for delay, that decision was within the sole discretion of the Sleeper Control Officer and not referable to arbitration.
  • The award is a nullity insofar as it directs the President of India to pay, because the President has immunity from being made personally liable under Articles 299(2), 300(1) and 361(4) of the Constitution; the phrase “may sue or be sued” in Article 300(1) should not be read to permit a decree or award to be made against the President personally.

Contractor / Respondent's Arguments (as disclosed in the opinion)

  • The contractor asserted that, following the earlier payment at the lower rate, there was extensive correspondence between the parties that included acknowledgments of liability; such acknowledgments would, the contractor contended, take the claim out of the statute of limitation.
  • The contractor's position (on the issue of reduction for delay) was that a 2½% reduction per month was permissible only if no extension of time had been granted; the contractor maintained that an extension had in fact been granted and therefore no reduction was permissible — making the question whether time had been extended the core dispute between the parties.
  • The contractor and its counsel pointed out that, although the award nominally directed payment by the President of India, the arbitrator’s direction of payment “through the Sleeper Control Officer, South Eastern Railway” indicated the arbitrator intended to make the Union of India (i.e., the Government) liable, and that the use of the President's name was a clerical or form mistake.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Award Case No. 252 of 1962: Union of India v. Salween Timber and Construction Co. Ltd., AIR 1963 Cal 307 Observation that an arbitrator's decision, right or wrong, is not liable to be set aside unless an error of law is apparent on the face of the award; and the Court's power under Section 15 to correct awards in certain circumstances was exercised in that case. The judge relied on this earlier decision to refuse to set aside an award on the ground that the claim was time-barred when the alleged legal error was not apparent on the face of the award; the judge also stated that in that earlier case he had corrected an award under Section 15 and he follows that view here.
Award Case No. 463 of 1962 (Cal) — Ray, J.'s decision between the same parties The contrary view (as recorded) that the Court has no power to correct such an award and that an award which, on its face, makes the President liable is a nullity which cannot be corrected. The court noted this contrary authority and observed that an appeal from that decision was pending. After consideration, the judge reaffirmed his earlier view (as in Award Case No. 252) that Section 15 permits correction in the circumstances of the present case.

Court's Reasoning and Analysis

The Court addressed the issues in sequence and applied the following reasoning (as set out in the opinion):

  1. Time-barred claim: The Government alleged the claim was statute-barred because final payment had been made years earlier. The contractor claimed that subsequent correspondence contained acknowledgments of liability, which could extend limitation. The arbitrator had considered the matter and held that the claim was alive. The Court observed that an error of law cannot properly be relied on unless it is apparent on the face of the award; there was no reasoning or material in the award that demonstrated such an apparent error. The Court declined to "ransack the whole record" to test documents afresh and therefore refused to set aside the award on the ground that the arbitrator had allowed a time-barred claim.
  2. Jurisdiction under the arbitration clause: The Government argued that the arbitration clause excluded disputes which concerned matters in respect of which certain officials (e.g., the Sleeper Control Officer) had sole discretion, and that decisions such as whether to grant an extension (and consequent reduction in rates) were non-arbitrable. The Court analysed the contract provision and the specific dispute: whether an extension had been granted (which would preclude reduction) or not (which would permit reduction). The Court concluded that this factual and legal dispute over whether an extension was granted was covered by the arbitration clause and hence was a matter for arbitration; the arbitrator therefore had jurisdiction to decide it.
  3. Award against the President and competence to correct: The Court accepted the Government's proposition that a decree or order directly against the President of India would be impermissible in law (citing Articles 299(2), 300(1) and 361(4) of the Constitution). The award, however, nominally made the President liable and directed payment "through the Sleeper Control Officer." The Court found on the available materials that the arbitrator plainly intended to make the Union of India (i.e., the Government) liable rather than the President personally. That misnaming was characterised as either an "obvious error" or a "clerical mistake or error arising from an accidental slip or omission."
  4. Power to correct under Section 15: The Court relied on Section 15 of the Indian Arbitration Act (which empowers the Court to modify or correct an award where it is imperfect in form or contains an obvious error or a clerical mistake) to hold that the award could be corrected to substitute the Union of India for the President. The judge explicitly relied on his earlier view in Award Case No. 252 of 1962 where he had corrected such an award, and after considering the contrary view expressed by Ray, J. in Award Case No. 463 of 1962 (Cal), elected to adhere to his prior position that the Court had the corrective power under Section 15 in such circumstances.
  5. Procedural disposition: The judge noted the existence of conflicting appellate outcomes on the precise point and the pendency of appeals, but declined to defer judgment pending an authoritative appellate decision. After "anxious consideration," the judge reaffirmed his earlier approach and proceeded to correct the award and enforce it against the Union of India.

Holding and Implications

Holding: The application to set aside the arbitrator's award is dismissed, and the award is enforced as corrected.

The Court's direct orders and immediate consequences for the parties (as stated in the opinion) are:

  • The application challenging the award fails and is dismissed (para 11).
  • The award is treated as containing an error in form (naming the President instead of the Union of India) and is corrected under Section 15 of the Indian Arbitration Act so that the Union of India is made liable.
  • The Court passes judgment in terms of the award as corrected and orders interest on the judgment debt at the rate of 3% per annum (para 12).
  • The Government is given three months for payment; no execution is to be levied before the expiry of that period (para 13).
  • On costs, the opinion contains both the statement "There will be no order for costs" (para 11) and the statement that judgment is passed "with the usual costs" (para 12). The opinion records both lines as they appear in the judgment text.

Broader implications: The Court explicitly recognised a conflict of judicial views on the availability of the Court's power to correct an award that nominally makes the President liable, and noted that appeals on related points were pending. The judgment adheres to the view that Section 15 permits correction in such circumstances, but the opinion records that this question is contested and subject to further appellate determination. The Court did not purport to pronounce an authoritative rule conclusively beyond the specific correction ordered in this case.

    Union Of India And Another v. Himatsingka Timber Ltd. .

    1. This is an application to set aside an award. The dispute is between the contractor and the Government. The contractor entered into a contract with the Government on March 14, 1951, for the sale of certain sleepers. The sleepers were supplied not within the data provided in the agreement: The contractor was paid for the goods at a rate lower than what is provided in the contract. The contractor claimed that it was entitled to more. This was disputed. The dispute was referred to arbitration under the arbitration clause in the contract. The arbitrator in the instant case Mr. A.K Gupta, Government Inspector of Railways give his award on December 26, 1961. The award is very short and is set out below in extenso:

    AWARD.

    “Whereas a dispute in connection with the supply of first class Sal sleepers to the Sleeper Control Officer. S.E Rly., under agreement No. 14.MSM/51 has been referred to my arbitration And Whereas I have heard the representatives of the parties, considered the statements and documents filed and/or produced before me and having taken everything into consideration carefully, I hereby award that the respondent, the President of India (through the Sleeper Control Officer, S.E Rly., Calcutta) do forthwith pay to the claimant, Himatsingka Timber ltd., the sum of Rs. 3024.00 and Rs. 260.00 being the amounts of their claim and costs therein respectively, aggregating to Rs. 3284.00

    Dated, Calcutta, this 26th day of December, 1961.

    Sd. Illegible.

    Government Inspector of Railways, Calcutta

    Now Known As

    Additional Commissioner of Railway Safety, Calcutta,

    Arbitrator.”

    This Award is being challenged by the Government.

    2. Mr. Debi De, learned counsel appearing for the Government, contended first that this award ought to be set aside because the arbitrator has made an award of a time-barred claim. It is alleged in the petition that final payment was received by the contractor as far back as 1953 and that more than seven years after the receipt of such payment and eight years after the supply of the sleepers this reference was made upon which an award in favour of the contractor was given. In the affidavit in opposition it is contended that subsequent to the payment of the sum at the rate of Rs. 56/- per sleeper there has been a large number of correspondence between the parties. According to the contractor, in the course of the correspondence there has been acknowledgment of liability so as to extend the period of limitation. The point was debated before the arbitrator who held that the claim was alive and not time-barred. No point is made that this error of law is apparent on the face of the award. No reason is given either in the award or in any connected paper so that the error of law if any may be apparent on the face of the award. Mr. Debi Dey therefore did not challenge the award on that ground. Mr. De contended that the arbitrator misconducted in the proceeding in making an award of a time-barred claim. In order to sustain this argument Mr. De has to establish first that the claim is time-barred. In the Award Case No. 252 of 1962 Union of India v. Salween Timber and Construction Co. Ltd., AIR 1963 Cal 307, I made the following observation:

    “The decision of the arbitrator right or wrong is not liable to De set aside, unless the error of law is apparent on the face of the award. As stated before, the error of law, if any, is not apparent on the face of the award. In my judgment, it is not for the Court to ransack the whole record for the purpose of finding out whether in fact there is or is not an acknowledgment in the documents filed before the arbitrator. The letters were placed before him and he might well have construed the document or any one of them to amount to are acknowledgment so as to take the claim out of the Statute of Limitation. It cannot therefore be contended that the arbitrator must have made the award of a time-barred claim contrary to the provisions of the Indian Limitation Act. The award is not liable to be set aside on this ground.”

    On the same ground I reject Mr. Dey's contention the instant case.

    3. It is next contended by Mr. De that the arbitrator had no jurisdiction to decide the dispute. The arbitration clause even though couched in the widest possible language, contains exceptions, and takes certain disputes out of the arbitration clause. It is provided in the agreement as under:

    “The reference to arbitration shall not however embrace or be referable to any matter in respect of which the sole power, discretion, liberty, decision or jurisdiction lies with the Sleeper Passing Officer, the Sleeper Control Officer, or President, Eastern Group, of any one of them under the agreement, terms of contract or specification hereof.”

    The contract provides that if the contractor delayed in the? supply of the materials so as to necessitate an extension of the time provided in the Schedule, he shall apply in writing to the Sleeper Control Officer, Eastern Group, who, if reasonable grounds be shown to his satisfaction, shalt grant such extension in writing as he in his absolute discretion may think fit, and for this purpose his decision in writing shall be considered final, and if any such extension shall be granted the dates for delivery specified in the schedule or such of them as shall be affected by such extension shall be postponed accordingly. If is further provided that a reduction of 2½ per cent in rates will be made on supplies made and accepted for each month of delay after the stipulated date provided no extension of time is granted.

    4. Mr. De contended that in terms of the clause above referred to, a reduction of 2½ per cent in rates has been made from the contractor's original bill. That being so, the discretion exercised by the Sleeper Contract Officer cannot be the subject-matter of arbitration. The contention of the contractor is that the reduction of 2½ per cent for each month's delay would be permissible only if no extension of time was granted. In the instant case there has been an extension of time and, therefore, no reduction was permissible. The dispute, therefore, is whether there was an extension of time granted by the Sleeper Control Officer. If in fact, an extension of time was granted, no reduction of 2½ per cent per month from the original date of delivery would be permissible. If, on the other hand, time was not extended, such a reduction would be permissible. That was the dispute and, in my judgment, such dispute is covered by the arbitration clause. It cannot, therefore, be said that the dispute between the parties is taken out of the arbitration agreement by reason of the exception clause set out above, in the facts and circumstances of his case, in that view of the matter, the second point taken by Mr. De also cannot be sustained. The next point taken by Mr. De is that no award can be made against the President and an award made against the President of India is a nullity. This indeed is Mr. De's main ground for challenging the award,.under Article 299(2) of the Constitution of made the President is not personally liable in respect of any contract entered into by him on behalf of the Union. Article 300(1) provides that the Government of India may sue or be sued in the name of the Union of India. And Article 361(4) provides, that no civil proceedings in which relief is claimed against the President, shall be instituted during the term of office in any Court. It is, therefore, submitted by Mr. De that there, is absolute immunity granted to the President both in respect of his official acts and in respect of his personal acts and he is not liable to be sued in any court so long as he occupies the office of President Mr. De submitted that the words “may sue or be sued” In Article 300(1) should be given an extended meaning and should not be restricted to suits for or against the Government. I am in complete agreement with Mr. De that no suit can be instituted against the President, and no decree can be passed against the President, directing him to make any payment whatsoever. I also agree that the award of the arbitrator directing the President of India to make payment of the amount due to the contractor cannot be made in law. It is I not necessary for me to decide in this application whether Article 300(1) was intended to cover only cases which come before the Court, that is, whether it covers only suits and applications pending in Court or whether it is wide enough to cover proceedings before the arbitrator as well. It is not necessary for me to decide that question in this application having regard to my finding that the award made against the President is a bad award and cannot be made in law. Mr. De contended that in that view of the matter I have no other option than to set aside the award. The reason why I am net doing it will appear from what is stated hereunder.

    5. There is no question in this case that the subject-matter of the arbitration is a contract between the Union of India on the one band and the contractor on the other. The contract, however, has been entered into in the name of the President of India as provided in the Constitution, it appears that because of this, the contractor was foolish enough to give the cause title in his State of Facts as under.

    “In the matter of Indian Arbitration Act — The President of India v. Ourselves.”

    In the counter State of Facts filed on behalf of the Government, however, the mistake has been corrected and it has very rightly been pointed out that the disputes subsisting between the parties is between Messrs Himatsingka Timber Ltd., Claimant on the one hand and the Union of India the respondent on the other. There was no manner of doubt that the claim was being made by 3 the contractor against the Union of India as representing the Indian Railways and there is no manner of doubt either that the arbitrator by his award made the Government of India liable. He, however, in his award directed the President of India through the Sleeper Control Officer, South Eastern Railway, to pay the claimant's dues amounting to Rs. 3024.00 and Rs. 260.00 on account of costs.

    6. I am satisfied, in my mind, that the arbitrator intended to make the award as against the Union of India representing the Indian Railways and the form of the award is clearly a mistake. Now, the question is, whether such an award which on the face of it is bad, can be corrected by the Court. The power of the Court to correct an award is given in Section 15 of the Indian Arbitration Act. Section 15 provides:

    ‘The Court may by order modify or correct an award ……………..

    (a) x x x x x x x x x x x

    (b) Where the award is imperfect in form or contains an obvious error which can be amended without affecting such decision, or

    (c) Where the award contains a clerical mistake or error arising from an accidental slip or omission.”

    7. In the instant case I have not the least doubt that the intention of we arbitrator was to mane we Union of India liable. The arbitrator was not called upon by either party to decide whether the Union Government or the President of India would be liable. That question was never before the arbitrator. Nobody had even dreamed of making a claim against the President and no such claim was ever made even though through error the cause title was stated as stated above. In my judgment while making the award the arbitrator did not intend to impose a liability or obligation on the President but he intended to impose a liability on the Union of India. Mrs. Khastgir the learned junior counsel appearing for the respondent with Mr. Bhabra has drawn my attention to the fact that the President through the Sleeper Control Officer, South Eastern Railway has been directed to pay. This is an Indication of the fact that the arbitrator did not intend to make the President of India liable. In my judgment the mistake in the award can be corrected either under Clause (b) or Clause (c) of Section 15 of the Indian Arbitration Act. The form of the award is wrong. The arbitrator while intending to make the Union of India liable has through mistake made the President of India liable and has thereby committed an obvious error. Alternately, I hold that it is a clear case of an accidental slip on the part of the arbitrator in not making the Union of India liable. On this ground. I am apt to think that the Court has got power to correct the award. This very point was raised by Mr. Debt De before me in another case of Salween Timber noted above, AIR 1963 Cal 307. In that case I took the view that the Court had power under Section 15 of the Indian Arbitration Act to correct such award and I did correct the award accordingly. I am told that an appeal has been taken against the decision and it is still pending.

    8. Subsequent to my decision the point came up for consideration before Ray, J. in a case between the same parties in Award Case No. 463 of 1962 (Cal). My learned brother Ray, J. has taken the view that the Court had no such power. The view expressed by Ray, J. is that the award is a nullity and cannot be corrected. I am told by Mr. Debi De that this decision of Ray, J. also is appealed against and the appeal is pending.

    9. At first I was inclined to defer delivering judgment till the authoritative decision on the point is given by the Appeal Court. There are objections to such procedure and I was pressed to deliver judgment now.

    10. Having regard to the contrary opinion expressed by Ray J., I gave my anxious consideration to the question. Even after such anxious consideration I do not find any reason to revise the opinion already expressed by me.

    11. In the result the application fails and is dismissed. There will be no order for costs.

    12. I pass judgment in terms of the award as corrected with the usual costs. Interest on judgment debt at the rate of 3 per cent per annum.

    13. The Government will get three months for payment before the expiry of which no execution is to be levied.

    KG/D.H.Z

    14. Petition dismissed.