AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 69 of the Indian Partnership Act.
  • Sec. 69 of the Partnership Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 69 of the Indian Partnership Act.
  • Sec. 69 of the Partnership Act
Smart Summary

Factual and Procedural Background

The Food Corporation of India (the Corporation) invited offers in 1976 for constructing godowns on their land to be rented at reasonable rates. Susheela, Managing Partner of Anupama Warehousing Establishment, showed interest and formed a partnership firm to raise funds for construction. An agreement was executed on 4-6-1977 between the plaintiff and the defendant for constructing a godown of 5000 M.T capacity at Pilicode, to be leased for five years at a specified rent with a completion timeline of four months.

Construction began before the agreement was signed, with site approval and loan advances facilitated by the defendant. Due to material shortages and modifications requested by the defendant, the completion was delayed and the contract time was extended multiple times, up to 31-7-1979. However, the defendant later declared the proposal not alive by letter dated 15-12-1979 and refused to occupy the completed godown.

The plaintiff filed suit claiming the cost of construction, interest on bank advances, rent receivable, and damages for mental agony totaling Rs. 38.8 lakhs. The defendant contested the suit citing Section 69 of the Indian Partnership Act and non-performance within the stipulated time, asserting time was essence of the contract. The trial court rejected the defendant's maintainability objection, held that time was not the essence of the contract, and awarded damages only for loss of rent, denying cost of construction and mental agony damages. Both parties filed appeals against parts of the decree.

Legal Issues Presented

  1. Whether the suit is maintainable under Section 69 of the Indian Partnership Act.
  2. Whether time was the essence of the contract between the parties.
  3. Whether the defendant validly terminated the contract due to delay in completion.
  4. Whether the plaintiff is entitled to damages including cost of construction, interest, rent, and mental agony.

Arguments of the Parties

Defendant's Arguments

  • The suit is barred by Section 69 of the Indian Partnership Act.
  • The plaintiff failed to complete construction within the stipulated time, making time the essence of the contract.
  • The defendant was not bound to take the godown on rent due to plaintiff's delay.
  • The defendant admitted recommending bank loans and supervising construction but maintained the plaintiff did not perform their contractual obligations timely.

Plaintiff's Arguments

  • Time was not the essence of the contract as the defendant extended the completion period multiple times.
  • The delay was caused by unavoidable shortages of materials and defendant’s suggestions for alterations.
  • The defendant’s termination of the contract was illegal and unjustifiable.
  • The plaintiff claimed damages for construction costs, interest on bank advances, rent, and mental agony totaling Rs. 38.8 lakhs.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Pollock & Mulla, Indian Contract and Specific Relief Acts, Tenth Edition, p. 445 Even if time is not the essence of the contract, performance must be within a reasonable time; a party can terminate the contract after unreasonable delay. The court relied on this principle to conclude that the Corporation was entitled to terminate the contract after inordinate delay despite previously granting extensions.

Court's Reasoning and Analysis

The court analyzed the contractual terms and the conduct of the parties regarding time for completion. It noted that although time was not originally considered the essence of the contract and extensions were granted repeatedly, the contract still required performance within a reasonable time. The court emphasized that indefinite delay is not permissible, especially when the warehouses were needed for a specific purpose by the Corporation.

Applying the principle from Pollock & Mulla, the court held that the Corporation’s termination of the contract after the extended deadline was lawful. The plaintiff’s delay in completing the construction until well after the final extension frustrated the purpose of the contract. Consequently, the plaintiff’s claim for damages, including construction costs and mental agony, was rejected as the termination was justified.

Holding and Implications

The appeals were disposed of by allowing A.S No. 12 of 1991 (filed by the defendant) and dismissing R.F.A No. 125 of 2003 (filed by the plaintiff).

The court held that the defendant-Corporation validly terminated the contract due to unreasonable delay in performance despite extensions. As a result, the plaintiff's claim for damages was denied. This decision directly affects the parties by setting aside the trial court's partial award in favor of the plaintiff, but it does not establish a new precedent beyond affirming that time, while not initially essential, must be treated as such if performance is unreasonably delayed to the detriment of the other party.

    The Food Corporation Of India v. Anupama Warehousing Establishment .

    S. Sankarasubban, J.:— A.S No. 12 of 1991 is filed by the defendant against the judgment and decree in O.S No. 126 of 1987 of the Sub Court, Tellicherry, while R.F.A No. 125 of 2003 is filed against the judgment and decree by the plaintiff in the suit. The facts of the case are as follows:

    2. In 1976, the Food Corporation of India (hereinafter called as ‘Corporation’) invited offers from the parties interested in constructing godowns in their land and rent it to the Corporation on reasonable rates. In response to the invitation, Susheela, Managing Partner of Anupama Warehousing Establishment, expressed her willingness to consider the offer. Thereafter, the District Manager of the defendant informed her to approach a Nationalised Bank for getting sufficient advance for the construction of godowns for the Corporation. It is also informed that the defendant would recommend the application if routed through them. On 20-10-1976 Susheela wrote a letter to the District Manager stating that she was interested in the proposal and that she intended to form a Partnership for the purpose of raising funds to construct the godown. Thereafter, through plaintiff Partnership Firm was constituted with Susheela as the Managing Partner. On 21-5-1977, an agreement was entered into between the plaintiff and the defendant. It was later cancelled and a new agreement was executed on 4-6-1977. As per the terms of the agreement, the plaintiff had to construct one godown of 5000 M.T's capacity at Pilicode, for the use of the defendant. It was agreed that after the construction, the plaintiff would lease the godown for a period of five years at the rate of 36 paise per sq. foot per month. There was a provision that the godown should be made ready for occupation within four months of the execution of the agreement.

    3. The construction had started even before the execution of the agreement. The property was purchased after the site approval of the officer of the defendant-Corporation. Under the terms of the agreement, it was made clear that the construction would be completed only by the grant of loan from Banks and that the defendant would be willing to recommend such applications to the Banks concerned. As per the terms of the agreement, the building had to be constructed under the supervision of the Corporation and the building was meant only for their use. Several difficulties cropped up during the progress of the construction. The cement was a material essential for the progress of the work. Though originally a time was fixed for the completion of the construction, it was never considered to be the essence of the contract. The Authorities were fully aware that time factor was inconsequential. As a matter of fact, the time was extended from time to time at least on 8 occasions. All the building materials were in short supply. So, the plaintiff cannot be in any way held responsible for the delay. Alternations, additions and modifications suggested by the defendant also have contributed for the delay. The period under the contract was extended by the defendant from time to time up to 31-7-1979. But in the meanwhile, the defendant wrote a letter dated 15-12-1979 by which the defendant informed the plaintiff that the proposal is not alive. The stand taken by the defendant is illegal and unjustifiable.

    4-5. After the completion of the building, the plaintiff informed the defendant to occupy the godown, but they refused to do so. The defendant had also suggested that they would consider the hiring of the godown on a month to month basis on a reduced rate. From this suggestion of the defendant, it is clear that they only wanted a reduction of the rent and that they never considered the time as the essence of the contract. This gigantic and massive building was constructed spending Rs. 17 lakhs, out of this Rs. 7.6 lakhs was advanced by Canara Bank on the recommendation of the defendant. The Bank has advanced at the interest rate of 15%. The liability to the Bank as on the date of the plaint is Rs. 14 lakhs. So, the suit was filed claiming the actual cost of construction of Rs. 17 lakhs with interest on Bank advance of Rs. 12.5 lakhs, rent receivable and also for damages for mental agony. A total amount of Rs. 38.8 lakhs is claimed as damages.

    6. In the written statement filed by the defendant, they contended that the suit is hit by Section 69 of the Indian Partnership Act. They also contended that the plaintiff has not performed her part of the contract. They contended that the building was not constructed within the time stipulated and under the contract, the time was an important factor and that the plaintiff was expected to complete the building within the time stipulated in the agreement. They admitted having extended the time fixed by the original contract. The defendant took up a stand that they were to bound to take up the building on rent as the plaintiff did not complete the construction within the time stipulated. They admitted that they have recommended for financial aid from the Bank. They also admitted that the building was constructed under their supervision, strictly in accordance with this specification stipulated by them.

    7. The Court below framed the necessary issues. The plaintiff produced Exts. A1 to A101 and the defendant produced Exts. B1 to B58. There was no oral evidence on either side. On a detailed consideration of the documentary evidence, the Court below came to the conclusion that the objection taken up by the defendant that the suit is not maintainable under Sec. 69 of the Partnership Act was rejected. On issue No. 4, on the question whether time is the essence of the contract, the Court below came to the conclusion that there is ample evidence to show that the parties did not intend to make the time an important condition of the contract and so it cannot be held that the time is the essence of the contract. On issue No. 2, the Court below found that the plaintiff is entitled to bring in the suit. On issue No. 5, the Court below came to the conclusion that the breach of the contract was made by the defendant. Regarding the question of damages, the Court below took the view that the plaintiff is not entitled to the cost of construction. The Court below granted a decree only on the basis of the loss of rent. The cost of the building was not granted. Damages for mental agony was not granted. The Corporation filed this appeal against the granting of the damages, while the plaintiff has filed the appeal against that part of the decree, which did not grant damages as prayed for. It is against that these two appeals have been filed.

    8. We heard learned Counsel for the appellant and learned Counsel for the respondents.

    9. While learned Counsel for the appellant argued that the termination of the contract was valid and that the appellant was not liable to pay any damages, learned Counsel for the respondent reiterated the contentions urged by him in the Court below. So far as the question whether time is the essence of the contract is concerned, there can be no rigid rule. It depends upon the facts and circumstances of each case. It cannot be argued that merely because time is proved to be not the essence of the contract, the contract could be performed at any time. Performance of a contract by the promisee at a very late stage cannot be accepted, if it does not achieve the purpose for which the contract was entered into. In the present case, we find that the requirement of the appellant-Corporation was the requirement to have warehouses for storing the foodgrains. Because of large stock of foodgrains, the Corporation wanted warehouses. In the present case, we find that the agreement was entered into on 4-6-1977 between the plaintiff and the defendant. By this agreement, it was stipulated that the building should be constructed within four months. It is seen that the plaintiff could not perform the contract within four months. It applied for extension. Extensions were granted by the Corporation and it is pertinent to say that at all time, permission was granted at the request of the plaintiff. The terms of the contract show that there was no obligation on the part of the Corporation to perform any act for the completion of the work. The entire construction of the building was left with the plaintiff, who had to find out the raw materials and other things for the construction of the building. It is found that the Corporation has been giving sufficient extensions to the plaintiff. Ext. B54 is the order by which last extension was granted. By this, time was extended up to 31-7-1979. When construction was not completed by 31-7-1979, the Corporation by Ext. B56 dated 15-12-1979 informed the plaintiff that the contract was terminated. It is 10 months after this that the building has been completed and notice was issued by the plaintiff to the Corporation. The mere fact that on previous occasion time was not extended does not prevent the party from stipulating a time for the completion of the construction. A construction, which was agreed to be completed within four months from 4-6-1977 could be executed only by 1980. According to us, the mere fact that previously time was granted cannot lead us to come to the conclusion that one party has to wait unendingly. It is not the law. It has been clearly stated by the defendant that warehouses were required for a particular purpose and that purpose could not be achieved by the construction of the warehouses at a later stage.

    10. In Pollock & Mulla, Indian Contract and Specific Relief Acts, Tenth Edition at page 445, it is stated thus:

    “Either party's general right to have the contract performed within a reasonable time according to the circumstances is, of course, unaffected by the fact of time not being of the essence; and in case of unnecessary delay by one party the other may give him notice fixing a reasonable time after the expiration of which he will treat the contract as at an end; the party who serves such a notice will himself be bound by it. Where there has been inordinate delay on both sides, it may be inferred that the contract has been abandoned, although no such notice has been given. Also parties may bind themselves to use special diligence in completion, without naming any particular date…..”

    It shows that even if time is not the essence of the contract, the contract has to be performed within a reasonable time. If it is not performed within a reasonable time, the party affected by this, is entitled to put an end of the same.

    11. In the above view of the matter, we are of the view that the termination of the contract by the appellant-Corporation is legal. Hence, the claim for damages claimed by the plaintiff will not stand. Hence, we set aside the judgment and decree of the Court below. A.S No. 12 of 1991 is allowed and so far as R.F.A No. 125 of 2003 is concerned, it is dismissed.

    Order accordingly.