Structured Summary of the Opinion (Bharuka, J.)

Factual and Procedural Background

The appellant is a company engaged in manufacturing cement with a factory at Malkhed in Gulbarga District. Lands were acquired under the Karnataka Industrial Areas Development Act, 1966 (KIAD Act), and a final award was passed by the Deputy Commissioner, Gulbarga, on 28.6.1982. The land owners accepted the compensation awarded and, in a meeting between representatives of the appellant, the Deputy Commissioner and the land owners, it was agreed that the appellant would make additional ex-gratia payments to the land owners; an affidavit in respect of one land owner is placed at Annexure 'A'.

Subsequently, the Special Land Acquisition Officer of the Karnataka Industrial Areas Development Board (the Board) suo moto passed an order dated 17.2.1988 awarding additional sums (difference of solatium and difference in interest) and later presented a supplementary award dated 21.8.1991 (Annexure 'B') for approval. After approval, a demand (Annexure 'D') dated 30.12.1992/02.01.1993 was raised against the appellant for Rs. 9,74,039.99 with interest and service charges totaling Rs. 11,78,588.40.

The appellant challenged the action. The Single Judge in W.P. No. 8707/93 upheld the validity of the supplementary award by order dated 17.6.1998. This intra Court appeal challenges that order and the consequential demand.

Legal Issues Presented

  1. Whether the Special Land Acquisition Officer could, after the award had attained finality and after a lapse of several years, pass a supplementary award and raise a demand against the appellant for additional sums.
  2. Whether the supplementary demand was contrary to the statutory scheme — specifically Section 29(2) of the KIAD Act and Section 11(2) of the Land Acquisition Act, 1894 — where compensation had been determined by agreement and accepted by the persons interested.
  3. Whether, given acceptance of the award by the land owners and absence of any timely reference under Section 18 of the Land Acquisition Act, the supplementary award could be validly made.

Arguments of the Parties

Appellant's Arguments

  • The original award passed by the Deputy Commissioner was accepted by the land owners and ex-gratia payments were made pursuant to an agreement reached in a meeting; affidavits from land owners confirm acceptance (Annexure 'A').
  • No reference under Section 18 of the Land Acquisition Act was made within the prescribed time, so the award attained finality and could not be reopened.
  • The supplementary demand and award issued by the Special Land Acquisition Officer are contrary to Section 29(2) of the KIAD Act (where compensation determined by agreement shall be paid in accordance with such agreement) and Section 11(2) of the Acquisition Act (allowing an award where all interested persons have agreed in writing), and therefore impermissible and tainted with mala fides.

Respondents' Position (as reflected in the opinion)

  • The Special Land Acquisition Officer issued a supplementary award and the Board raised a demand which was upheld by the Single Judge. The opinion notes, however, that learned counsel for the respondents could not point to any statutory provision authorizing the supplementary award after a lapse of six years.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sushila Devi v. Ramanandan Prasad . 1976 1 SCC 361 Principle that "for a finality of litigation, a person should not be vexed twice for the same cause". The court relied on this principle to hold that once the land owners had accepted the award pursuant to agreement and it had attained finality, the Special Land Acquisition Officer could not pass the supplementary award reopening the matter.
Kothamasu Kanakarathamma v. State of Andra Pradesh . AIR 1965 SC 304 Authority for the proposition that a reference under Section 18 of the Acquisition Act is not maintainable after the prescribed period (i.e., limitations on challenging an award). The court cited this decision to support the conclusion that a challenge or reference under Section 18 was not available after the lapse of the prescribed period, reinforcing the finality of the original award.

Court's Reasoning and Analysis

The court proceeded through the following analytical steps, based strictly on the material in the opinion:

  1. The original acquisition proceeded and a final award was passed by the Deputy Commissioner on 28.6.1982; the land owners accepted the compensation and, by agreement reached in a meeting involving the appellant, the Deputy Commissioner and the land owners, the appellant made additional ex-gratia payments (evidence: Annexure 'A').
  2. Where an award is passed and no reference is sought under Section 18 of the Land Acquisition Act within the prescribed time, that award attains finality. In the present case no such reference was made by any interested person.
  3. The impugned supplementary award dated 17.2.1988 and the later supplementary award presented on 21.8.1991 (Annexure 'B') followed by a demand (Annexure 'D') were examined against the statutory scheme. Section 29(2) of the KIAD Act provides that where compensation has been determined by agreement between the State Government and the person to be compensated, it shall be paid in accordance with such agreement. Section 11(2) of the Land Acquisition Act permits the Deputy Commissioner to make an award according to the terms of a written agreement entered into by all interested persons.
  4. Given that the land owners had entered into and accepted an agreement fixing the quantum of compensation (including solatium) and had filed affidavits to that effect, the court concluded that the Special Land Acquisition Officer's unilateral supplementary demands were contrary to those statutory provisions and ex facie mala fide and impermissible.
  5. The court relied on the authority in Sushila Devi v. Ramanandan Prasad to reinforce the principle against relitigation and the concept that a person should not be vexed twice for the same cause. It also relied on Kothamasu Kanakarathamma to support the view that a reference under Section 18 is not maintainable after the prescribed period.
  6. The opinion records that the learned Single Judge had upheld the impugned supplementary award but that the statutory aspects relied upon by the appellant were not apparently brought to the Single Judge's attention, resulting in the impugned affirmance.
  7. On the basis of the statutory provisions, the acceptance by the land owners, the absence of any timely Section 18 reference, and the cited authorities, the court concluded that the supplementary award and demand could not stand.

Holding and Implications

Holding: The court allowed the intra Court appeal and set aside the Single Judge's order dated 17.6.1998 in W.P. No. 8707/93. It quashed the consequential demand dated 30.12.1992/02.01.1993 (Annexure 'D') raised by the Special Land Acquisition Officer and thus invalidated the supplementary award presented on 21.8.1991 (Annexure 'B').

Implications: The direct consequence is that the appellant is relieved of the supplementary demand of Rs. 11,78,588.40. The court characterized the supplementary action as contrary to the statutory scheme (Section 29(2) of the KIAD Act and Section 11(2) of the Acquisition Act) and tainted with mala fides. The opinion records that no statutory provision was shown to permit such a supplementary award after the lapse of six years, and that a reference under Section 18 would not have been maintainable after the prescribed period. The court ordered that parties shall bear their own costs.

The opinion does not purport to create or announce any broader new legal precedent beyond applying the cited authorities and the statutory provisions to the facts of this case.

    Rajashree Cement v. Karnataka Industrial Areas Development Board And Others

    Bharuka, J.:—

    This intra Court appeal is directed against the order dated 17.6.1998 passed by the learned Single Judge in W.P No. 8707/93 upholding the validity of the order dated 21.8.1991/17-2-1988 (Annexure ‘B’) passed by the Special Land Acquisition Officer, KIADB, Gulbarga, and the consequential demand dated 30.12.1992/02.01.1993 (Annexure ‘D’) raised against the appellant for a sum of Rs. 9,74,039.99 with interest at the rate of 21% along with service charges of the respondent Board amounting in all Rs. 11,78,588.40.

    2. The appellant is a company engaged in manufacture of cement. It has a factory at Malkhed in Gulbarga Dist.

    3. The 1st respondent Karnataka Industrial Areas Development Board (in Short the ‘Board’) is constituted under Section 5 of the Karnataka Industrial Areas Development Act, 1966 (in short the ‘KIAD Act’). The Act inter alia provides for securing the establishment of industrial areas in the State of Karnataka and to promote the establishment and orderly development of industries therein. For the purposes of the Act, lands were acquired and final award was passed by the Deputy Commissioner, Gulbarga, on 28.6.1982, which was not questioned by the land owners in any manner as required under Section 18 of the Land Acquisition Act, 1894 (in short the ‘Acquisition Act’), which, as per Section 30 of the KIAD Act, mutatis mutandis applies to the acquisitions made under thereunder.

    4. It is a matter of record that compensation as awarded by the Deputy Commissioner was duly accepted by the land owners. In the Writ Petition before this Court, it was clearly stated that in the meeting held between the representatives of the appellant company, the Deputy Commissioner, and the land owners, it was agreed for additional payment by the appellant company and accordingly ex-gratia payment was made to the land owners. Copy of the affidavit in respect of one of the land owners has been placed at Annexure ‘A’.

    5. It appears that subsequently the Special Land Acquisition Officer of the Board suo moto passed the order dated 17.2.1988 stating therein that.—

    “In the circumstances stated above, the difference of 30% of the solatium market value admissible 15% already awarded and difference of the interest @ 9% and 15% as admissible under the amendment Act and the interest actually paid is hereby awarded as worked out in the Statement Annexure-I”.

    6. Subsequently, by communication dated 21.8.1991 (Annexure ‘B’), the Special Land Acquisition Officer of the Board presented supplementary award to the Special Deputy Commissioner in a sum of Rs. 4,80,640.18 for his approval. It appears that after receiving the approval, demand was raised against the appellant requiring it to deposit a sum of Rs. 11,78,588.40 as noticed above.

    7. In our opinion, the demand raised against the appellant is contrary to the provisions of the KIAD Act and the Acquisition Act and even otherwise it is tainted with mala fides. Once an award is passed and if the person interested does not accept the same, then the only legal remedy which remains with him is to question the same by seeking reference under Section 18 of the Acquisition Act. In the present case, admittedly, no reference was sought by the interested person within the prescribed time. Thus, the award has attained its finality.

    8. Apart from the facts as noticed above, the impugned action of the respondent Special Land Acquisition Officer in raising the supplementary demand against the appellant company under Annexure ‘D’ for paying additional payments to the land owners is clearly hit by Section 29(2) of the KIAD Act, which reads thus.

    Section 29 Compensation.

    (1) XXXXXXXXX

    (2) Where the amount of compensation has been determined by agreement between the State Government and the person to be compensated, it shall be paid in accordance with such agreement.

    9. Similarly, Section 11(2) of the Acquisition Act also provides for entering into a written agreement by all the interested persons regarding quantum of award. This Section reads thus.

    11. Enquiry and award by collector.

    (1) XXXXXXXXX

    (2) Notwithstanding anything contained in sub-section (1), if at any stage of the proceedings, the Deputy Commissioner is satisfied that all the persons interested in the land who appeared before him have agreed in writing on the matters to be included in the award of the Deputy Commissioner in the form prescribed by rules made by the appropriate Government, he may, without making further enquiry, make an award according to the terms of such agreement.

    10. In terms of the above provisions, as stated in the Writ Petition, it was agreed between the parties that the land owners should be given ex gratia payment in addition to compensation granted by the Special Land Acquisition Officer. It is a matter of record that in terms of the above provisions, the land owners had entered into an agreement with the Government and the beneficiary in relation to quantum of compensation including solatium payable to them and had accepted the amounts so determined as full and final settlement of their claims. They had also filed affidavits to that extent as is evident from Annexure ‘A’ Despite these facts, the Special Land Acquisition officer of his own, had raised impugned supplementary demands, which ex-facie seems to be mala fide and impermissile.

    11. In the case Sushila Devi v. Ramanandan Prasad . 1976 1 SCC 361 it has been held that “for a finality of litigation, a person should not be vexed twice for the same cause”. We are of the considered opinion that in the present case, since the land owners had accepted the award passed pursuant to agreement between the parties and the same having attained finality, the respondent Special Land Acquisition Officer could not have passed the supplementary award.

    12. Learned Counsel for the respondents could not brought to our notice any statutory provisions under which the respondent could have made the supplementary award that too after a lapse of 6 years. More over, even a reference under Section 18 of the Acquisition Act is not maintainable after the lapse of prescribed period as held by the Supreme Court in the case of Kothamasu Kanakarathamma v. State of Andra Pradesh . AIR 1965 SC 304.

    13. It appears that the above legal aspects were not brought to the notice of the learned Single Judge, which has resulted in passing of the impugned order affirming the impugned supplementary award.

    14. Accordingly, for the reasons state above, we set aside the order dated 17.6.1998 passed by the learned Single Judge in W.P No. 8707/93 and quash the consequential demand dated 30.12.1992/02.01.1993 (Annexure ‘D’) passed by the Special Land Acquisition officer.

    15. In the result, the appeal is allowed. Parties to bear their own costs.