Smart Summary

Factual and Procedural Background

The Petitioners are ex-employees (described as persons whose names were on a "Badli list") of the Karnataka State Road Transport Corporation ("Corporation"). The Badli list was a list of persons available to be given day-to-day employment to cover for regular employees who were absent. Petitioners were given employment only on days when regular employees were absent. The Corporation deleted the petitioners' names from the Badli list on grounds of unsuitability and issued orders terminating their services. Prior to termination, none of the petitioners had worked 240 days in any year.

The petitioners challenged the legality of the termination orders on the ground that Section 25-F of the Industrial Disputes Act had not been complied with, arguing that they were in "continuous service" within the meaning of Section 25-B(1) (or alternatively Section 25-B(2)) of the Industrial Disputes Act. The Corporation contended that Badli workers are engaged only on a day-to-day basis, that no employer-employee relationship existed on days when they were not given work, and that the petitioners did not satisfy the 240-day requirement of Section 25-B(2).

Some petitions were also objected to on the ground of delay and laches, as they were filed more than three years after removal from the Badli list. The court ultimately dismissed the writ petitions and ordered no costs.

Legal Issues Presented

  1. Whether the termination orders removing petitioners from the Badli list (and thereby ending their day-to-day engagement) were illegal for non-compliance with Section 25-F of the Industrial Disputes Act.
  2. Whether petitioners who worked only on days when regular employees were absent qualify as being in "continuous service" under Section 25-B(1) of the Industrial Disputes Act.
  3. Whether petitioners qualify as being in "continuous service" under Section 25-B(2) by virtue of having worked 240 days in a year (and whether the 240 days must be within the twelve months immediately preceding the date of termination).
  4. Whether the delay (presentation of petitions after three years) constitutes a bar by laches or undue delay to the maintenance of the petitions.

Arguments of the Parties

Petitioners' Arguments

  • Because they worked on all days on which they were given work and were not given work on other days through no fault of theirs, they must be deemed to be in continuous service under Section 25-B(1) of the Industrial Disputes Act.
  • Section 25-B(1) is beneficial legislation and should be interpreted in a manner favorable to workers.
  • Alternatively, in some petitions petitioners asserted that they had worked 240 days in some year (counting from commencement of appointment), and therefore Section 25-B(2) and Section 25-F should apply.
  • Reliance was placed on the Supreme Court judgment in Mohanlal v. Management, Bharath Electronics Ltd. (AIR 1981 SC 1252) to support their interpretation of Section 25-B(1).

Corporation's Arguments

  • Inclusion of a name in the Badli list does not make the person an employee of the Corporation except for the specific day-to-day appointment; it is a mechanism to provide day-to-day work against leave vacancies as regulated by Regulation 16 of the K.S.R.T.C. Cadre and Recruitment Regulations, 1968.
  • The petitioners did not work 240 days in any year and therefore do not fall within Section 25-B(2).
  • Because the petitioners were not in the employment of the Corporation on days they were not given work, Section 25-B(1) is not attracted to them and consequently Section 25-F is not applicable.
  • Where an issue of fact exists as to whether a workman has worked 240 days in a year, the appropriate remedy is to raise an industrial dispute; the Corporation conceded cases in which a workman had actually worked 240 days in a year.
  • Some petitions are barred by delay and laches, having been filed more than three years after removal from the Badli list.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Huchaiah v. K.S.R.T.C. (1983 1 LLJ 30) Illustrates that to attract Section 25-B(2) the workman must have actually worked 240 days in a year; if the 240-day condition is satisfied, Section 25-B(2) applies regardless of nature of employment. The court referenced Huchaiah to state there is no dispute about the scope of Section 25-B(2): 240 days is the threshold for that clause.
K.S.R.T.C v. Boraiah (1984 1 SCC 244) Confirms the principle that satisfaction of the 240-day requirement brings a worker within Section 25-B(2) irrespective of employment nature. Used alongside Huchaiah to affirm the settled position about Section 25-B(2)'s scope.
Mohanlal v. Management, Bharath Electronics Ltd. (AIR 1981 SC 1252) Explains that Section 25-B(1) and (2) introduce deeming fictions; Section 25-B(1) ignores interruptions caused by specified hazards and Section 25-B(2) deems continuity where the worker has actually worked 240 days in the 12 months preceding the date relevant for calculation. The court quoted Mohanlal but held that Mohanlal did not support the petitioners' expansive construction of Section 25-B(1); Mohanlal was read as confirming that Section 25-B(1) requires the person to have been in service (not only occasional day-to-day work).
Lalappa v. Laxmi Vishnu Textile Mills (1981 2 SCC 238) Held that badli (substitute) employees are substitutes/spare men and are not covered by the substantive part of the definition of "continuous service" (in Payment of Gratuity Act), but fall within an explanation analogous to Section 25-B(2); they are not entitled to benefits for periods with no work allotted. The court treated Lalappa as providing a "complete answer" to the petitioners' argument, applying its reasoning to Section 25-B(1) and (2) because of identical language; relied on Lalappa to hold that badli employees are not in continuous service for the periods they were not given work.
The Delhi Cloth Mills' case (AIR 1970 SC 919) Recognized that continuity of service may not exist for badli employees. Referenced within the Lalappa decision; relied upon indirectly through Lalappa to support the conclusion that badli employees lack continuity of service for the non-working periods.
Vallabhdas Kanji (P) Ltd. v. Esmail Koya (1978 Lab IC 809 (Kar)) Taken in some decisions to support a contrary view that badli employees could be covered by continuous service provisions. The court noted that Vallabhdas Kanji's contrary view "does not appear to lay down a good law" and preferred the reasoning in Lalappa and Delhi Cloth Mills.
Mahadev Textile Mills v. Additional Industrial Tribunal (1976 1 K.L.J 315) Indicates that a badli worker cannot be regarded as in the employment of the employer for days on which he had not worked. Used to support the court's conclusion that Section 25-B(1) could apply only to a workman in service throughout the specified period and not to badli workers who were not in employment on days they did not work.

Court's Reasoning and Analysis

The court's analysis proceeds from statutory interpretation of Section 25-B of the Industrial Disputes Act and an examination of the Corporation's Regulation 16 governing Badli workers.

  1. Textual Interpretation of Section 25-B(1): The court parsed Section 25-B(1), observing that it applies where a person "is, for that period, in uninterrupted service" and that specified interruptions (sickness, authorised leave, accident, lawful strike, lock-out, or cessation not due to workman's fault) are to be ignored so as to deem the service continuous. The court emphasized that the prerequisite for Section 25-B(1) is that the person must have been in the service of the employer throughout the period in question, not merely employed for isolated days.
  2. Meaning of Section 25-B(2): The court accepted the settled position (citing Huchaiah and Boraiah) that Section 25-B(2) applies when a worker actually rendered 240 days of service during the relevant twelve calendar months immediately preceding the date with reference to which the calculation is made.
  3. Application of Regulation 16: The court examined Regulation 16 of the K.S.R.T.C. Cadre and Recruitment Regulations (procedure for appointment of Badlis) which defines a Badli worker as one employed on a day-to-day basis to fill vacancies caused by absence, paid for the days worked, and selected on a first-come-first-served basis at the depot. The court concluded that on days when no job is given, there is no employer-employee relationship between the Corporation and the Badli worker; the Depot Manager engages day-to-day labor and not the appointing authority for the post.
  4. Rejection of Petitioners' Construction of Section 25-B(1): The court found the petitioners' reading (that day-to-day work and absence of work through "no fault" of the worker should be treated as interruption under Section 25-B(1) and thus deemed continuous) to be unreasonable and unintended by the provision. The court illustrated the absurdity of that construction by hypothetical seasonal employment (e.g., being given 10 days' work during a festival and claiming continuous service for the remaining 355 days).
  5. Beneficial Interpretation Not Available: The court explained that the principle of giving a beneficial construction applies only when two reasonable interpretations are available; where only one reasonable reading exists, invoking benevolent construction is not appropriate. The petitioners' interpretation was found patently unreasonable and would render Section 25(2) otiose.
  6. Precedent Considerations: The court reviewed Mohanlal, finding that passage relied upon does not support the petitioners' expansive construction of Section 25-B(1) because Mohanlal requires that the person must have been in employment during the period (including days not worked for specified reasons). The court found Lalappa directly on point: badli employees are substitutes and are not covered by the substantive notion of continuous service for periods with no work, and therefore Lalappa applies "on all fours" to Sections 25-B(1) and (2) due to identical language.
  7. Other Factors: The court noted that the opening of a provident fund account for one petitioner (if accidental or otherwise) does not alter the statutory analysis regarding Section 25-B(1). The court also accepted the Corporation's submission that Section 25-B(2) requires the 240-day presence within the 12 months immediately preceding the reference date, and where there is a factual dispute about 240 days worked, the remedy is to raise an industrial dispute.
  8. Delay/Laches: For a second group of petitions filed after three years of removal from the Badli list, the court found delay and laches to be an additional ground for dismissal, referencing prior orders (W.P. No. 21409 of 1983 & connected cases dated 28-3-84).

Holding and Implications

Holding: The court dismissed the writ petitions. The court ordered no costs.

Implications for the parties (direct effects):

  • The terminations (deletion from the Badli list and consequent cessation of day-to-day engagement) were upheld: the petitioners were not held to be in "continuous service" under Section 25-B(1) on the basis of intermittent day-to-day Badli employment.
  • The petitioners did not satisfy Section 25-B(2) as none had proven (or the court found) that they had worked 240 days in the relevant twelve-month period preceding termination; where a factual dispute exists on whether a petitioner worked 240 days in a year, the petitioner is at liberty to raise an industrial dispute to resolve that fact.
  • Certain petitions filed more than three years after removal from the Badli list were dismissed on the additional ground of delay and laches.

Broader legal implications: The opinion applies and follows existing authority (including Lalappa and Mohanlal) to confirm that badli/substitute/day-to-day workers are not to be treated as in continuous employment for periods when they were not given work; the judgment does not purport to lay down a novel precedent beyond applying settled principles to the facts before the court.

Disposition: Writ Petitions dismissed; No costs.

    Honnayya v. General Manager, Ksrtc

    Rama Jois, J.:—

    The Petitioners, who are ex-employees of the Karnataka State Road Transport Corporation (‘Corporation’ for short), have presented these Petitions questioning the legality of the order terminating the services of each of the petitioners on the ground that they had been made in violation of the mandatory requirements of Section 25-F of the Industrial Disputes Act (‘the Act’ for short).

    2. The facts of the case, in brief, are as follows:

    The name of each of the petitioners had been included in a list called ‘Badli list’ prepared by the concerned officers of the Corporation. The list so prepared was for the purpose of utilizing their services on days on which regular employees of the Corporation remained absent by taking leave. Accordingly the petitioners, whose names were included in the Badli List were being given appointments only on days on which the regular employees were on leave. By each of the orders, impugned in these Petitions, the names of the petitioners were deleted from the Badli List on ground of unsuitability. Prior to the order of termination none of the petitioners had put in 240 days of service in any of the years. The contention of the petitioners, however, is that their cases fall within the scope of Section 25-B(1) of the Act as they had worked on all days in a year on which they were given work and as the work was not given on other days for no fault of theirs, notwithstanding the intervening period on which they had not worked, they must be deemed to be in continuous service.

    3. As against this, the contention of the Corporation is that the inclusion of the names of the petitioners in Badli List did not mean that they became employees of the Corporation. It was only for the purpose of providing them appointment on day to day basis against leave vacancies as is evident from Regulation 16 of the K.S.R.T.C Cadre and Recruitment Regulations, 1968. As they had not worked for 240 days in any year, they did not come within the purview of Section 25-B(2) and as they were not in employment of the Corporation on the days on which they had not worked, they were not governed by Section 25-B(1) also. Therefore, Section 25-F was not at all attracted to their cases.

    4. Section 25-B of the Act reads as follows:

    “25-B. For the purpose of this Chapter, —

    (1) a workman shall be said to be in continuous service for a period if he is, for that period, in uninterrupted service, including service which may be interrupted on account of sickness or authorised leave or an accident or a strike which is not illegal, or a lock-out or a cessation of work which is not due to any fault on the part of the workman;

    (2) where a workman is not in continuous service within the meaning of clause (1) for a period of one year or six months, he shall be deemed to be in continuous service under an employer -

    (a) for a period of one year, if the workman, during a period of twelve calendar months proceeding the date with reference to which calculation is to be made, has actually worked under the employer for not less than -

    (i) one hundred and ninety days in the case of a workman employed below ground in a mine; and

    (ii) two hundred and twenty days, in any other case.”

    The language of the provision indicates that clause (1) applies to cases where a person is in the service of an employer, but in a given year, he had not worked on certain days for one or the other reasons set out in the sub-section, namely, sickness, authorised leave or an accident or a strike which is not illegal, or a lock-out or cessation of work not due to any fault on the part of the workman. The sub-section presupposes the continued existence of employer and employee relationship during the period in which the workman was unable to work for one or the other reason, set out in Section 25-B(1) or even if he was in a position to work, either because the employer was unable to give the work or because the employer deliberately prevented the workman from working, there was interruption in the service of the employee. In cases where the employer prevents the workman from working on any day or for any period, the workman does not cease to be in service and he would therefore be entitled to claim wages for such period and for that purpose he could make an application under Section 33-C(2) of the Act before a Labour Court or under Section 15 of the Payment of Wages Act, on the ground that non-payment of wages for such period amounts to deduction of wages within the meaning of that expression used in the Payment of Wages Act. In cases where the non-assignment of work was not on account of any deliberate Act on the part of the employer, still the workman would be in the service of the employer during that period and would be deemed to be in continuous service notwithstanding the cessation of work during such period.

    5. As far as the scope of Section 25-B(2) is concerned, there is no dispute. For attracting this clause, all that is necessary is the workman concerned must have worked under an employer for 240 days in a year. If he has worked, he stands governed by this clause irrespective of the nature of employment (See: Huchaiah v. K.S.R.T.C . 1983 1 LLJ 30. and K.S.R.T.C v. Boraiah . 1984 1 SCC 244.

    6. Bearing in mind, the scope of Section 25-B(1) the case put forward by the petitioners have got to be examined. The scheme under which the petitioners were given work on certain days in a year is as follows: It is natural that when a large number of personnel are in the employment of the Corporation employed in connection with its transport services, some of them would be applying for leave on many days on account of personal reasons or illness. Therefore it becomes necessary for the Corporation to engage the services of some other person in the place of the employee of the Corporation, who applies for leave for the day or days, on which he applied for leave. In order to know as to who could be engaged on such days, the Corporation has got a system of preparing a list of names called ‘Badli List’, in which the names of those unemployed persons, who are desirous of securing work against leave vacancies are included. Such lists are prepared and sent to the depots concerned which are the starting point of stage carriages or contract carriages of the Corporation in different parts of the State. Persons whose names are in the Badli List, if they so desire, are at liberty to come to the depot at the commencement of the working hours and find out whether any employee of the Corporation had applied for leave and whether they could get work in his place on the date on which the employee had applied for leave on payment of prescribed wages for the day. In fact to regulate such day-to-day employment or engagement, Regulation 16 is incorporated in the Service Regulations of the Corporation. It reads —

    “16. PROCEDURE FOR APPOINTMENT OF BADLIS.

    1. A BADLI worker is one who is employed on day-to-day basis in any vacancy caused by the absence of any employee and who is paid for the number of days he works as such, either daily or once in a month.

    2. A List of Badli workers shall be maintained in a Depot or workshops. The appointment of a Badli worker shall be made from among those in the list of Badli workers who are present at the Depot/Workshops, preference being given to the person who arrives first at the place of duty. If for any reason a Badli worker is not found suitable for the post, his name may be removed from the list of Badli workers.

    3. A Badli worker would be eligible for such day-to-day appointment as long as his name figures in the list of Badli workers.”

    (Underlined by me)

    The language of Regulation 16 is clear and unambiguous. The persons whose names are included in the Badli List would secure employment for the day and that would be given on first come first served basis. Thus it may be seen that except the fact that persons like the petitioners are given job on daily wages for the day concerned, on the days on which no job is given, there is no employer and employee relationship between the Corporation and the petitioners. The day-to-day appointment is given by the Depot Manager, who is authorised to engage workman for the day and not by the appointing authority for the post.

    7. I fail to appreciate how a workman who secured work against leave vacancies for those days stands covered by Section 25-B(1) of the Act. It would be travesty of law to say that if a person is given work for one or for a few days in a year by an employer, either as leave substitute or to meet the extra work arising on any occasion, the rest of the days on which no work is given, amounts to ‘cessation of employment’ within the meaning of Section 25-B(1) and that the workman must be deemed to be in continuous service of such person. The following illustration would bring forth the fallacy of the construction of Section 25-B(1) suggested for the petitioners. Take for instance that during the Dasara Festival, the Corporation is in need of more drivers and conductors as it is required to run more trips to meet the seasonal traffic and, therefore, some persons who are qualified to be drivers or conductors and whose names are in Badli list or not are given work for a period of about 10 days. According to the construction of Section 25-B(1) by the petitioners, as for other 355 days in the year, it is the Corporation, who failed to give the work and therefore cessation of work was for no fault of workman and, therefore, would constitute interruption within the meaning of Section 25-B(1) of the Act. In such a case, in reality all that can be said is, the Corporation gave work for 10 days and not that the Corporation denied work for 355 days.

    8. Learned Counsel for the petitioners maintained that Section 25-B(1) of the Act was a beneficial legislation and, therefore, such an interpretation has to be given.

    9. The principle of giving beneficial interpretation to a provision arises, when two reasonable interpretations of a provision are possible and one of it is advantageous to the workman and the other is not, but not in a case where no other interpretation is possible. The interpretation suggested for the petitioners is unintended by the provision and is patently unreasonable and would lead to unjust results. Learned Counsel maintained that if an employer takes the services of a workman even for a day in a year the rest of the 364 days would have to be treated as interruption in service and Section 25-B(1) would apply to his case. Neither the text nor the context of Section 25-B(1) of the Act permits any such construction. Such construction would also render Section 25(2) otiose and therefore impermissible.

    10. Learned Counsel for the petitioners, however, submitted that the judgment of the Supreme Court in Mohanlal v. Management, Bharath Electronics Ltd. . AIR 1981 SC 1252. supports the submission. The relevant portion of the judgment reads—

    “Mr. Markandey contended that clauses (1) and (2) Section 25B provide for two different contingencies and that none of the clauses is satisfied by the appellant. He contended that sub-section (1) provides for uninterrupted service and sub-section (2) comprehends a case where the workman is not in continuous service. The language employed in sub-sections (1) and (2) does not admit of this dichotomy. Sub-sections (1) and (2) introduce a deeming fiction as to in what circumstances a workman could be said to be in continuous service for the purposes of Chapter VA. Sub-section (1) provides a deeming fiction in that where a workman is in service for a certain period he shall be deemed to in continuous service for that period even if service is interrupted on account of sickness or authorised leave or an accident or a strike which is not illegal or a lockout or a cessation of work which is not due to any fault on the part of the workman. Situations such as sickness, authorised leave, an accident, a strike not illegal, a lockout or a cessation of work would ipso facto interrupt a service. These interruptions have to be ignored to treat the workman in uninterrupted service and such service interrupted on account of the aforementioned causes which would be deemed to be uninterrupted would be continuous service for the period for which the workman has been in service. In industrial employment or for that matter in any service, sickness, authorised leave, an accident, a strike which is not illegal, a lockout and a cessation of work no due to any fault on the part of the workman, are known hazards and there are bound to be interruptions on that account. Sub-section (1) mandates that interruptions therein indicated are to be ignored meaning thereby that on account of such cessation an interrupted service shall be deemed to be uninterrupted and such uninterrupted service shall for the purposes of Chapter VA be deemed to be continuous service. That is only one part of the fiction.”

    (Underlined by me)

    I fail to see how the above paragraph supports the construction of Section 25-B(1) of the Act made by the Learned Counsel for the petitioners. The above paragraph also indicates that in order to attract provisions of Section 25-B(1) of the Act, the condition precedent is that the person must have been in service during the period i.e, not only on days when he actually worked, but also on days he could not work under circumstances set out in Section 25(1). In other words, in order that Section 25-B(1) is attracted to the case of an employee, he should have been in the employment of the employer concerned not only on days on which he has worked, but also on the days on which he had not worked, either on account of his inability or on account of his being prevented by the employer from working.

    11. On the other hand, the judgment of the Supreme Court in Lalappa v. Laxmi Vishnu Textile Mills . 1981 2 SCC 238 provides a complete answer to the Point raised by the petitioners. In the above case, the Supreme Court was interpreting the meaning of the expression ‘continuous service used’ in Section 2(c) of the Payment of Gratuity Act, which is in pari materia with Section 25-B(1) of the Act and the explanation below it which is similar to Section 25-B(2) of the Act. Repelling the contention that a person who had been employed as a substitute on a few days in a year in the place of an absentee workman should be deemed to be in continuous service under the main part of the Section on the ground that on the rest of the days there was cessation of the employment for no fault of the workman concerned, the Supreme Court stated thus:

    “The Report of the Badli Labour Enquiry Committee, Cotton Textile Industry, 1967, no doubt shows that the badli employees are an integral part of the textile industry and that they enjoy most of the benefits of the permanent employees; but there may not be any continuity of service as observed by this Court in The Delhi Cloth Mills' case (AIR 1970 SC 919) (supra). The badli employees are nothing but substitutes. They are like ‘spare men’ who are not ‘employed’ while waiting for a job; Conlon v. Glasgow, 36 Scott LR 652, Vallabhdas Kanji (P) Ltd. v. Esmail Koya, 1978 Lab IC 809 (Kar) taking the view to the contrary does not appear to lay down a good law. Accordingly, we uphold the view that the badli employees are not covered by the substantive part of the definition ‘continuous service’ in section 2(c), but came within Explanation I and therefore, are not entitled to payment of gratuity for the badli period i.e, in respect of the years in which there was no work allotted to them due to their failure to report to duty.”

    (Underlined by me)

    The interpretation of the aforesaid provision of the Payment of Gratuity Act applies on all fours to Section 25-B(1) and (2) of the Act as the language of both the provisions are identical.

    12. The decison of this Court in Mahadev Textile Mills v. Additional Industrial Tribunal . 1976 1 K.L.J 315. also clearly indicates that ‘Badli’ cannot be regarded as in the employment of an employer on the days on which he had not worked. Section 25-B(1) therefore could only apply to the case of a workman in the service of an employer throughout a specified period, but was unable or prevented from working on certain days or period. Having regard to Regulation 16 of the Recruitment Regulations of the Corporation, the petitioners cannot be regarded as in the service of the Corporation on days on which the petitioners were not given appointment.

    13. Learned Counsel for the petitioners submitted that in the case of one of the petitioners, a provident fund account had also been opened. As stated earlier, none of the facts concerning the giving of work to the petitioners on certain days have been disputed. That being the position, the fact whether by mistake or otherwise a provident fund account had been opened does not make any difference as far as the applicability of Section 25-B(1) of the Act is concerned.

    14. In some of the petitions an alternative contention was raised to the effect that though each of the petitioners had not worked for 240 days, preceding the date of termination, if calculation is made from the date of commencement of appointment, they had worked for 240 days in some or the other year, and, therefore, they should be regarded as having been in continuous service for one year in view of Section 25-B(2) and, therefore, termination of their service without complying with Section 25-F of the Act was void.

    15. As against the above submission, Learned Counsel for the Corporation submitted that none of these petitioners, had worked for 240 days in any of the year. He also submitted that Section 25-B(2) could be attracted only if the workman concerned had worked for 240 days within a period of twelve months immediately proceeding the date of termination. In support of this submission Counsel for the Corporation relied on the following observations of the Supreme Court in Mohan Lal's case.

    “Sub-section (2) incorporates another deeming fiction for an entirely different situation. It comprehends a situation where a workman is not in continuous service within the meaning of sub-section (1) for a period of one year or six months, he shall be deemed to be in continuous service under an employer for a period of one year or six months, as the case may be, if the workman during the period of 12 calendar months just preceding the date with reference to which calculation is to be made, has actually worked under the employer for not less than 240 days. Sub-section (2) specifically comprehends a situation where a workman is not in continuous service as per the deeming fiction indicated in sub-section (1) for a period of one year or six months. In such a case he is deemed to be in continuous service for a period of one year if he satisfies the conditions in Clause (a) of sub-section (2). The conditions are that commencing the date with reference to which calculation is to be made, in case of retrenchment the date of retrenchment, if in a period of 12 calendar months just preceding such date the workman has rendered service for a period of 240 days, he shall be deemed to be in continuous service for a period of one year for the purposes of Chapter VA.”

    16. Learned Counsel for the petitioners relied on paragraph 22 of the judgment of this Court in Huchaiah's case and submitted that if a workman had worked for 240 days in any of the year preceding the date of retrenchment, Section 25-F would be attracted.

    17. Learned Counsel for the Corporation submitted that he had conceded in all cases in which a workman had worked for 240 days in any year, but these petitioners had not worked for 240 days in any year. As there is a dispute on question of fact, if any of the petitioner considers that he had worked for 240 days in a year, he is at liberty to raise an industrial dispute.

    18. In the second group of cases, there is an additional objection to the effect that they are liable to be dismissed on the ground of delay. All these Petitions have been presented after three years after the date on which they were removed from Badli list. Hence they are liable to be dismissed on the ground delay and laches. (See: Orders in W.P No. 21409 of 1983 & connected cases D.D 28-3-84.)

    19. In the result, I make the following order:

    (i) The Writ Petitions are dismissed.

    (ii) No costs.