Factual and Procedural Background

The petitioner challenged an arbitral award dated 15 January 2009 under Section 34 of the Arbitration and Conciliation Act. The Tribunal had allowed the respondent's claims for (a) balance milestone payments of USD 72,730 and INR 3,904,510.03, (b) VAT and service tax not refunded of USD 18,045 and INR 266,460, (c) balance 25% of retention money, and (d) costs of arbitration, awarding 12% interest on the amounts if not paid within 15 days of the award. The dispute arose from a sub-contract ("TVS sub-contract") in which the petitioner had deducted certain amounts from payments due to the respondent and had not refunded VAT/service tax or paid the retention monies, leading the respondent to invoke arbitration. The petitioner sought to set aside the arbitral award before this Court.

Legal Issues Presented

  1. Whether the arbitral award should be set aside under Section 34 of the Arbitration and Conciliation Act on grounds of breach of natural justice or unequal treatment of parties.
  2. Whether the Arbitral Tribunal's conclusion that the petitioner was not entitled to deduct amounts on account of alleged customs duty exemptions/back-to-back adjustments was legally unsustainable or lacked reasons.
  3. Whether the award was an unreasoned award because the Tribunal allegedly failed to link conclusions to material placed on record.

Arguments of the Parties

Petitioner's Arguments

  • The TVS sub-contract was a lump-sum contract inclusive of all taxes, royalties and duties (except certain custom duties exempt under notifications), and the petitioner was entitled to make deductions for deviations in custom duty rates.
  • The petitioner claimed entitlement to deduct amounts on account of custom duty exemptions enjoyed by the respondent and to recover amounts recovered by the petitioner from Samsung on a back-to-back basis.
  • The petitioner alleged the Tribunal did not treat the parties equally, acted against principles of natural justice, failed to give reasons for conclusions, and did not properly link material to conclusions; also relied on timing of the sub-contract (entered 6 June 2003) to argue unfairness.

Respondent's / Claimant's Position

  • The respondent asserted that the petitioner had improperly deducted USD 72,730 and INR 3,904,510.03, had not refunded VAT and service tax, and had not paid the remaining 25% retention money, giving rise to the arbitration claim.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court reviewed the Tribunal's examination of the contract terms, noting the Tribunal's factual findings that the fixed lump-sum price did not contain a component of custom duty, there was no evidence of custom duty charged and paid to the Government on the imports under the contract, and the petitioner failed to prove any adjustment by the principal contractor (Samsung) or produce Samsung's invoices showing custom duty components. The Court observed that the Tribunal had considered the relevant contractual clauses and documents and had given detailed reasoning. Applying Section 34 of the Arbitration and Conciliation Act, the Court emphasised that it cannot act as an appellate forum to re-appreciate evidence or substitute its view for that of the Arbitral Tribunal; interference is limited to grounds enumerated in Section 34. The Court found the petitioner's objections to be vague and unsupported, and that both parties had been given adequate opportunity before the Tribunal. On this basis, the Court concluded none of the petitioner's grounds justified setting aside the award.

Holding and Implications

PETITION DISMISSED

Direct effect: The arbitral award dated 15 January 2009 stands and the petition to set it aside under Section 34 is dismissed. The decision upholds the Tribunal's findings regarding non-entitlement of the petitioner to the contested deductions, entitlement of the respondent to VAT/service tax refund and retention monies, and the award of interest and costs as ordered by the Tribunal. The opinion does not discuss broader precedent-setting implications; no new legal principle was announced beyond the application of settled Section 34 principles.

To access the original judgment, please Sign In or Subscribe.

    Samho Gunyoung Co. Ltd. Petitioner v. Flakt (India) Ltd. & Ors.

    1. By this petition under Section 34 of the Arbitration and Conciliation Act, the petitioner has assailed an award of the Tribunal dated 15th January, 2009 whereby the Tribunal allowed the claim of the respondent in respect of balance amount of milestone payment to the tune of USD 72,730/- and INR 39,04,510.03 and also allowed a claim of USD 18,045/- and INR 2,66,460/- against vat and service tax not refunded. Tribunal awarded 12% interest on these amounts from the date they became due and payable, in case the amounts were not paid within 15 days of the passing of award, till realization. The Tribunal also directed the petitioner to pay balance 25% of the retention money of the claim and costs of arbitration proceedings.

    2. The respondent/claimant had entered into a sub-contract with the petitioner, called as ‘TVS sub-contract’ and the petitioner had deducted an amount of USD 72,730/- and INR 39,04,510.03 out of the payments due towards the respondent and had also not refunded vat and service tax in terms of contract and had not paid remaining retention money to the tune of 25% which resulted into invocation of the Arbitration agreement by the respondent and passing of the award by the Tribunal in favour of the respondent. The contention of the counsel for the petitioner is that the sub-contract entered into between the petitioner and the respondent though was a lumpsum contract inclusive of all taxes, royalty, custom duties (other than custom duties, i.e, basic custom duty, CVD and SAD of specified imported items which were not payable under the special exemption notification under the Customs Act, 1962 as described in terms of payment, Annexure-4), excise duty and other duties, still the petitioner was entitled to make deductions in case of an eventuality of deviation in the custom duty rates. The petitioner contended that it was entitled to deduct the amount on account of exemption of custom duty enjoyed by respondent under different notifications. The contracted lumpsum price entitled the petitioner to make recoveries of the amounts recovered from the petitioner by Samsung, on back-to-back basis.

    3. The learned Arbitral Tribunal considered the contract between the parties and the specific clauses regarding custom duty and came to conclusion that the petitioner's assumption that the fixed lumpsum price under the sub-contract was variable as per custom duty, was factually not correct. It was observed that there was no component of custom duty in the fixed lumpsum price agreed under the contract nor there was any incidence of custom duty charged and paid to the Government thereafter in respect of any of the imports into the country under the contract. The Tribunal also observed that the petitioner neither pleaded nor proved if any amount towards the exemption of custom duty was adjusted by the principal contractor (Samsung) from amount payable to the petitioner. It was also observed that the petitioner had failed to produce on record the invoices raised by Samsung on them having a component of custom duty, unlike the invoices raised by the respondent on the petitioner. The Arbitral Tribunal thus came to conclusion that the petitioner was not entitled to deduct the amount from the bills of respondent and allowed the claim of the respondent regarding these deductions. There is no dispute that the claimant/respondent was entitled for vat and service tax refund and during the arbitration proceedings, the petitioner had admitted a part of the claim and undertaken to release the said amount to the respondent/claimant at the earliest and as and when the same was received by the petitioner from the principal director.

    4. It is not disputed that the retention money to the tune of 25% was not paid to the claimant/respondent because of the alleged adjustments made by the petitioner and the Tribunal allowed the claim to that extent as well.

    5. The petitioner has assailed the award on the ground that the Tribunal had not treated the parties with equality and acted against the elementary principle of natural justice and fair play. It is also submitted that the Tribunal had not given reasons or justification for the conclusions arrived at and there was no link between the material placed on record before the Tribunal by the petitioner and the conclusions arrived at. It is also submitted that the Tribunal failed to appreciate that ‘TVS sub-contract’ agreement was entered on 6 June, 2003, i.e after Samsung (principal employer) had negotiated the price with the respondent. The respondent did not disclose to the Tribunal as to when the price was negotiated by Samsung and when Samsung asked the respondent no. 1 to enter into firm sub-contract with the petitioner. Thus, the award given by the Tribunal was unfair.

    6. The petitioner and the respondent had entered into a written contract between them. Samsung was not a party to the contract. It was for the petitioner to consider the contract carefully at the time of entering into it. If the petitioner had entered into a contract at the instance of Samsung (principal employer), that cannot be a ground to hold that the contract between the petitioner and the respondent was a back-to-back contract and whatever deductions were made by Samsung from the petitioner's bills are liable to be borne by the respondent. The contract between the petitioner and the respondent is an independent contract and is governed by its own terms and conditions. Unless and until the contract provided that it was a back-to-back contract and all deductions made by Samsung from the petitioner would be the responsibility of the respondent, the petitioner could not make those deductions from the respondent. The learned Arbitral Tribunal considered the terms of the contract between the parties and taking into account the terms of the contract passed the award.

    7. It is settled law that under Section 34 of Arbitration and Conciliation Act, this Court does not sit as an appellate court over the decision of the Arbitral Tribunal and cannot re-appreciate the evidence and arrive at a different conclusion. The Arbitral Tribunal is a judge of the facts and of law and has right to interpret the contract between the parties. This Court cannot substitute its own opinion against the opinion of the Arbitral Tribunal regarding quality, quantity and appreciation of the evidence, import of the documents and interpretation of the contract between the parties. The Court can interfere only under the circumstances as enumerated under Section 34 of the Arbitration and Conciliation Act 1996. The petitioner in this case had challenged the award only on vague and unspecified grounds. Though the award analysed the contract between the parties and gave detailed reasoning, still it is alleged that the award is an unreasoned award. The award has considered what were the relevant documents effective between the parties and required to be considered, still the allegation is made that the Arbitral Tribunal had not considered the documents. The proceedings before the Arbitral Tribunal as filed by the petitioner show that both the parties were given equal and adequate opportunity to present their case before the Tribunal, still the allegations are made by the petitioner that the Tribunal did not treat the parties equally.

    8. I find that none of the grounds made by the petitioner in the petition is tenable. I also find that the challenge to the award made by the petitioner is not sustainable under Section 34 of the Arbitration and Conciliation Act. The petition is hereby dismissed.

    SHIV NARAYAN DHINGRA, J.