  • Section 20(4) of the Arbitration Act, 1940.Sections 8 and 20(4) of the Arbitration Act of 1940
  • SECTION 11 ARBITRATION AND CONCILIATION ACT 1996
  • Section 1.1(6) read with Section 11(2) and not Section 11(5)
  • Section 41 read with Schedule 2 of the old Act,
  • Arbitration Clause 65.2, Arbitration Act, 1940
  • Sections 4, 8, 9, 10 and 20 of the old Act.
  • ARBITRATION ACT 1940
  • Section 9 of the New Act of 1996
  • Act of 1940 as the Act of 1996
  • Order 39 Rules 1 & 2 CPC,
  • Order 39 Rules 1
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 20(4) of the Arbitration Act, 1940.Sections 8 and 20(4) of the Arbitration Act of 1940
  • SECTION 11 ARBITRATION AND CONCILIATION ACT 1996
  • Section 1.1(6) read with Section 11(2) and not Section 11(5)
  • Section 41 read with Schedule 2 of the old Act,
  • Arbitration Clause 65.2, Arbitration Act, 1940
  • Sections 4, 8, 9, 10 and 20 of the old Act.
  • ARBITRATION ACT 1940
  • Section 9 of the New Act of 1996
  • Act of 1940 as the Act of 1996
  • Order 39 Rules 1 & 2 CPC,
  • Order 39 Rules 1
Smart Summary

Structured Summary of the Opinion — A.A. 181/99 & I.A. 5714/99

Factual and Procedural Background

This application (A.A. 181/99) under Section 11 of the Arbitration & Conciliation Act, 1996 seeks appointment of an arbitrator under Clause 15 of a Licence Agreement dated 28.3.1995 between the President of India and M/s Rama Associates Ltd. (later assigned to the petitioner). The Licence authorised operation of a VSAT-based service and contained detailed obligations (site clearances, allocation of space segment, licence fees, bank guarantees, performance guarantees and timelines for commissioning within one year).

The original licensee (M/s Rama) had earlier instituted arbitration proceedings (A.A. 101/96) against invocation of bank guarantees; that matter resulted in a settlement recorded by consent order dated 28.2.1997. Rights under the Licence were assigned by M/s Rama to the petitioner by a tripartite agreement dated 22.9.1997. Arrears then accumulated, demands were made by the respondents (including letters dated 17.2.1999 and 19.4.1999), bank guarantees were invoked on occasions, and the petitioner disputed liability and invoked Clause 15. The petitioner filed A.A. 181/99 for appointment of an arbitrator and I.A. 5714/99 under Section 9 of the Act for interim relief (restraining withdrawal of space segment, termination of the Licence Agreement, invocation of bank guarantees and related reliefs).

Legal Issues Presented

  1. Whether the disputes raised between the parties fall within the scope of the arbitration clause (Clause 15) of the Licence Agreement.
  2. If the disputes are arbitrable under Clause 15, who is to be appointed as arbitrator (specifically whether the designated authority named in Clause 15 — the Director General, Telecommunications, or his successor/nominee — should be appointed or whether the Court should appoint a different arbitrator).

Arguments of the Parties

Petitioner's Arguments

  • Certain amounts claimed as arrears by the respondents were not due because the respondents failed to discharge their obligations in time; for delays on respondents' part, fees/charges are not payable.
  • Disputes have arisen under the Licence Agreement and Clause 15 contemplates arbitration; the respondents failed to appoint the arbitrator despite notice and thereby abdicated their power to appoint.
  • The designated arbitrator (Director General, Telecommunications) is not independent or impartial and is prejudiced in favour of the respondent; hence an impartial and independent arbitrator should be appointed under Section 11 of the Act.
  • Relied on authorities including Nandyal Cooperating Spinning Mills Ltd. v. K.B. Mohan Rao and other precedents to support appointment by the Court where the designated authority fails to act.

Respondents' Arguments

  • The petitioner failed to fulfill obligations under the Licence Agreement and large arrears are due; the agreement expressly gives the respondents power to terminate and to invoke bank guarantees and that decision is final.
  • There is no dispute which can be referred to arbitration — in view of earlier settlement A.A. 101/96, no disputes survive or can be re-agitated.
  • The parties had agreed that only the designated authority (or his nominee) could be appointed as arbitrator under Clause 15, so no third person should be appointed.
  • Relied on authority (Dwarikesh Sugar v. Prem Heavy Engg. Works) on principles governing invocation of bank guarantees.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Nandyal Cooperating Spinning Mills Ltd. v. K.B. Mohan Rao (1993) 2 SCC 654 Under the old Arbitration Act, where an administrative head empowered to appoint an arbitrator fails to do so within the prescribed time (15 days in that case), the administrative head is deemed to have abdicated his power and the Court can appoint an arbitrator. The court discussed Nandyal to explain the position under the old Act and to contrast it with the 1996 Act; it recognized the abdication principle under the old law but considered the different scheme under the 1996 Act when deciding who should be appointed under Clause 15.
G. Rama Chandra Reddy (citation in text) Courts should endeavour to give effect to the contractual appointment of an arbitrator; where the contract names a person, parties are normally bound by that term and the Court should not appoint another arbitrator unless the named arbitrator refuses or neglects to act. The court relied on this principle to support giving effect to the parties' agreement to the designated authority as arbitrator unless that person is unable or unwilling to act.
Airtech Pvt. Ltd. v. NDMC & Others (DLT precedents cited) Instances where courts appointed arbitrators under provisions of the old Arbitration Act (Section 20(4) / Section 8) when the designated authority failed to act. The court noted these earlier decisions as examples where courts had appointed arbitrators under the old Act, but contrasted those facts and provisions with the scheme of the 1996 Act.
Dwarikesh Sugar v. Prem Heavy Engg. Works (1997) 6 SCC 450 Principles governing invocation of unconditional bank guarantees: beneficiary of an unconditional bank guarantee is ordinarily entitled to encash it irrespective of disputes; courts will be slow to grant injunctions restraining invocation except in narrow exceptions (fraud or irretrievable harm). The court applied the principles from Dwarikesh (and related authorities) to conclude that the petitioner had not established either fraud or irretrievable harm; thus the petitioner was not entitled to a general injunction restraining invocation of bank guarantees.
U.P. State Sugar Corporation v. Sumac International Ltd. 1997 (1) SCC 568 Sets out the general principles about enforcement/encashment of unconditional bank guarantees and the limited exceptions to restrain such encashment (fraud; exceptional irretrievable harm). The court quoted and relied upon these principles to hold that the petitioner had not met the strict tests required to restrain invocation of the bank guarantees.
Bolivinter Oil SA v. Chase Manhattan Bank 1984 (1) All E.R. 351 Authority stating that an injunction to restrain bank payment under an unconditional guarantee is appropriate only where it is proved that the bank knows a demand is clearly fraudulent; stringent proof required. The court reiterated this high standard for fraud-based relief and found the petitioner had not established such fraud or the bank's knowledge of fraud.
Sundram Finance Ltd. v. NEPC India Ltd. 1996 (2) SCC 479 Observation that the Arbitration & Conciliation Act, 1996 is materially different from the Arbitration Act, 1940 and must be construed with reference to the UNCITRAL Model Law; provisions of the old Act should not unduly influence interpretation of the new Act. The court invoked this observation to justify interpreting Section 11 of the 1996 Act on its own terms (and to distinguish provisions and outcomes under the old Act).
Union of India v. Praffula Kumar Sanyal 1979 (3) SCC 631 (AIR 1979 SC 1257) Interpreting Section 20(4) of the old Act: if an arbitrator had been appointed in an agreement the Court should make an order of reference to him; where parties cannot agree the Court can appoint an arbitrator; desirability that the Court consider feasibility of appointing an arbitrator according to contract terms. The court cited this case for the proposition that the Court should, where feasible, follow the contractually agreed appointment process and give effect to the contractually nominated arbitrator.
India Drugs Pharmaceuticals Ltd. v. Indo Swiss S. Gem Manufacturing Co. Ltd. AIR 1996 SC 543 Where arbitration clause provides appointment by a specified officer (e.g., Chairman & Managing Director), that contractual arrangement cannot be disregarded and the Court should not substitute an arbitrator without proper challenge to the clause. The court relied on this authority to reinforce the principle that parties are bound by the contractual choice of arbitrator and that the Court should respect that choice unless valid grounds exist.
Union of India v. HIMCO (India) Pvt. Ltd. AIR 1965 Cal 404 Where the arbitration agreement contains adequate appointment machinery (including substitutional appointments), non-signification of willingness by the appointed arbitrator does not debar the Court from making an order of reference to him; if he later refuses, the contractually provided procedure governs substitution. The court cited this decision to support the view that contractual machinery for appointment and substitution should be given effect to and that initial non-signification does not prevent reference to the named arbitrator.

Court's Reasoning and Analysis

The Court identified two central questions: (1) whether the disputes fell within Clause 15 and (2) if so, who should be the arbitrator. The Court accepted that Clause 15 was the arbitration agreement and that the parties had specifically agreed that the Director General, Telecommunications (or his successor/nominee) would be the sole arbitrator.

The Court analysed the effect of the 1996 Act (noting authorities that the 1996 statute must be interpreted on its own terms and is different from the old 1940 Act). It examined Section 11 of the 1996 Act (quoting sub-sections (2), (5), (6) and (8) as relevant) and observed that where a party fails to act under an agreed appointment procedure or a person fails to perform a function under that procedure, a party may request the Chief Justice (or his designate) to take necessary measures unless the agreement provides other means.

Applying these provisions and the parties' contractual choice, the Court concluded that Section 1.1(6) read with Section 11(2) (as described in the text) — not Section 11(5) — was attracted. Because the respondent had failed to refer the disputes to the agreed arbitrator in spite of notice, the Court had power to take necessary measures to secure the appointment; "taking the necessary measure" in the circumstances meant securing appointment of the agreed arbitrator rather than appointing a different person.

The Court considered the petitioner's contention that the agreed arbitrator (Director General, Telecommunications) was not independent/impartial. The Court emphasised that when the parties themselves have selected the arbitrator they are presumed to have accepted his characteristics and any objection to bias is ordinarily waived by such an agreement. The Court found no valid ground (other than an assumed bias asserted by the petitioner) to depart from the contractual appointment and therefore concluded that the agreed arbitrator should be appointed.

With respect to the Section 9 application (I.A. 5714/99) seeking interim injunctions preventing invocation of bank guarantees and termination of the licence, the Court reviewed the facts, the ledger admissions in the petitioner's statements and prior settlement (28.2.1997), and the content/wording of the bank guarantees. The Court applied established principles (as summarised in Dwarikesh, U.P. State Sugar and Bolivinter) that an unconditional bank guarantee can ordinarily be encashed irrespective of disputes and that courts will only restrain invocation in two narrowly defined exceptions: (a) established fraud (with knowledge by the bank) and (b) exceptional irretrievable harm that would prevent restitution.

Finding neither exception established, and that the petitioner had not established a prima facie case or irreparable injury, the Court concluded that the petitioner was not entitled to an unconditional injunction restraining invocation of the bank guarantees. Given public interest and the Government's interest in realising dues, the Court declined a blanket injunction but sought to avoid hardship by imposing conditional relief: it stayed invocation of bank guarantees and termination of the licence subject to the petitioner paying arrears at the rate of Rs. 50.00 lakhs per month (first instalment within ten days, subsequent instalments monthly), keeping bank guarantees alive and providing an undertaking; failure would automatically vacate the stay.

Holding and Implications

Holding:
Application A.A. 181/99 is allowed — the Director General, Telecommunications (or, if his designation has changed or his office is abolished, the officer entrusted with his functions) is directed to act as sole arbitrator in terms of Clause 15 of the Licence Agreement dated 28.3.1995.

I.A. 5714/99 — interim relief is granted conditionally: invocation of bank guarantees and termination of the licence are stayed provided the petitioner pays arrears at Rs. 50.00 lakhs per month (first instalment within ten days, subsequent instalments monthly), keeps the bank guarantees alive and furnishes an undertaking within one week; failure to comply will automatically vacate the stay.

Consequences and implications:

  • Direct effect on the parties: The parties are to proceed to arbitration before the designated authority named in the agreement; the arbitrator should decide disputes "arising under or in connection with" the Licence Agreement and is asked to make an award as far as possible within six months of receipt of the order.
  • Interim financial consequence: The petitioner must comply with the conditional payment schedule and other conditions to maintain the stay; if it fails, the respondents may proceed with invocation of bank guarantees and termination measures without further order.
  • Precedential implication: The Court applied established principles from prior authorities concerning (a) respect for contractual appointment clauses for arbitrators under the new Act (while distinguishing the scheme of the old Act) and (b) the narrow exceptions to restraining invocation of unconditional bank guarantees. The judgment gives effect to the parties' contractual choice of arbitrator under the 1996 Act and reiterates the stringent standard required to restrain bank guarantees, but it does not assert a new legal principle beyond the authorities relied upon.

Final administrative note in the order: "Nothing stated herein shall be deemed to be expression of opinion on merit which may prejudice the parties in proceedings before the arbitrator. A.A No. 181/99 and I.A No. 5714/99 stand disposed of."

    Essel Shyam Communication Ltd. v. Union Of India & Ors

    J.B Goel, J.— This application (A.A 181/99) under Section 11 of the Arbitration & Conciliation Act, 1996 (for short “the Act”) seeks the appointment of an arbitrator under arbitration agreement (Clause 15 of the agreement).

    Briefly, the facts are that in pursuance of its policy to licence private parties for providing “Value Added Service”, a Licence Agreement dated 28.3.1995 to establish, maintain and operate Closed Users Group Domestic 64 KBPS Data Network via Insat Satellite System using VSAT (hereinafter called the service) throughout India under the Tndian Telegraph Act was entered into between the President of India and M/s. Rama Associates Limited (for short “Rama”) on the terms and conditions stipulated in the Agreement. This licence was on non-exclusive basis for a period of 10 years subject to being terminated earlier. The agreement contemplated inter alia (a) Clearance for Hub Station site from Standing Advisory Committee on Radio Frequency Allocations (SACFA), Ministry of Communication, (b) Allocation of Required Space Segment in the Designated Transponder/Satellite and frequency, (c) Issuance of requisite Operational Requirement and Qualitative Requirement, and (d) Licence from Wireless Planning and Coordination Wing (WPC), Department of Telecommunication permitting utilisation of appropriate radio frequency spectrum for the establishment and operation of the VSAT network. The licensee was to pay licence fee (1) @ Rs. 50,000/- Per V-SAT subject to a minimum of Rs. 1.00 crore per year in the first two years and Rs. 1.5,0 crores in the third year and thereafter to be fixed; 10% of the licence fee was to be paid at the time of acceptance of Letter of Intent and for the balance 90% financial bank guarantee was to be given. 15% licence fee was to be paid prior to the date of commission of service (2) fee for satellite space charges etc. and (3) performance bank guarantee of Rs. 50 lakhs.

    In pursuance of the agreement, 10% licence fee was paid, for 90% a financial bank guarantee of Rs. 90.00 lakhs for the first year and performance bank guarantee in the sum of Rs. 50.00 lakhs were furnished. The Licensee was to establish a Hub after getting the site clearance from SACFA. For that purpose, application was to be made within 4 weeks but the petitioner had submitted such application to SACFA on 20.7.1995 i.e after about four months, site chosen being at Gorai, Bombay. For want of Site clearance that site was abandoned by the licensee, intimation of which was given in November 1995. In the meantime, the petitioner selected another site at Noida and submitted application for clearance of Hub site to SACFA on 26.9.1995 This site clearance is alleged to have been given belatedly on 2.6.1997 In accordance with the terms of the licence, initial deposit of Rs. 22.73 lacs was also paid on 24.4.1995 towards space segment reservation fee.

    The Licensee was required to commission the service within one year of execution of agreement which was not done and space segment remained unutilised. The Licensee did not make payments of various dues as agreed and the respondents raised demand for their dues which having not been met, bank guarantees were invoked. Against this, the licensee-M/s. Rama filed an arbitration suit (A.A 101/96) in this Court for appointment of an arbitrator and also against invocation of bank guarantees. A settlement was arrived at and payments made. In the meantime, the Licensee M/s. Rama assigned their rights under the aforesaid agreement in favour of the petitioner by means of a tripartite agreement dated 22.9.1997 Arrears of dues accumulated. The petitioner made some part payments and also furnished two additional financial bank, guarantees of Rs. 50 lakhs and Rs. 15 lakhs. Part payments were made, but the arrears still remained outstanding. And vide letter dated 17.2.1999, the respondents raised a demand of Rs. 1.8750 crores towards arrears of licence fee and Rs. 181.84 lakhs on account of space segment charges for 1997-1998 and 1998-1999, and Rs. 20.00 lakhs as LD charges besides interest and it was notified that if the dues are not paid within 30 days of the receipt of the notice, the licence would be terminated. The petitioners made representation dated March 4, 1999 disputing their liability and invoked arbitration Clause 15. Some further part payments were also made by the petitioner. The arrears remained uncleared and vide letter dated 19.4.1999, the respondents demanded arrears of space segment charges of Rs. 1,59,11,000/- with interest within 30 days failing which the space segment allotted to the petitioner would be withdrawn. The petitioner has filed this petition on 26.5.1999 for appointment of an arbitrator invoking Clause 15 of the Licence Agreement. Along with this, another application under Section 9 of the Act seeking interim protection is also filed.

    The respondents are contesting the claim of the petitioner. It is alleged that the petitioner has failed to fulfill its commitments under the Licence Agreement and huge arrears are due; the agreement gives power to the respondents to terminate the licence agreement and to invoke the bank guarantees and the decision of the authority in this respect is final. There is no dispute which could be referred to or needed arbitration as in view of earlier similar petition (A.A 101/96) no disputes survive nor could be re-agitated. In any case, the parties had agreed to the appointment of the designated authority as the arbitrator under the arbitration Clause 15 and only that designated authority or his nominee could be appointed as arbitrator.

    I have heard the learned senior counsel for the petitioner and learned Additional Solicitor General for the respondents. Learned counsel for the petitioner has contended that various amounts claimed as arrears are not due and payable as the respondents did not discharge their obligations in time and for delay on their part, fees and charges are not payable and as such disputes have arisen between the parties in respect of the Licence Agreement and that in spite of notice for appointment of the arbitrator, the respondents failed to appoint the arbitrator and thus they have abdicated their power to appoint the arbitrator and also the designated arbitrator is not independent, but interested in the respondent and thus based against the petitioner; an impartial and independent arbitrator be appointed under Section 11 of the Act. He has relied on Nandyal Cooperating Spinning Mills Ltd. v. K.B Mohan Rao (1993) 2 SCC 654, G. Ramachandra v. Chief Engineer, Madras Zone, MES (1994) 5 SCC 142, Airtech Pvt. Ltd. v. NDMC & Others 67 (1997) DLT 582 (K.C Sharma v. Ndmc & Anr. 81 (1999) DLT 552(Delhi). Whereas learned Addl. Solicitor General has contended that the disputes raised are not contemplated to be resolved through arbitration inasmuch as the amounts as agreed in the Licence Agreement only are claimed which remain unpaid in spite of various opportunities and notices given and in the circumstances the competent authority has power to terminate the agreement and the exercise of that power could not be referred for arbitration and bank guarantees are being invoked in accordance with the terms and conditions of the Licence Agreement and in terms of bank guarantees. He has also contended that in view of settlement in earlier A A. 101/96 on 28.2.1997, no disputes arise nor could be re-agitated. He has relied on Dwarikesh Sugar v. Prem Heavy Engg. Works (P) Ltd. and Another (1997) 6 SCC 450 in support of invocation of bank guarantees.

    Clause 15 of the Licence Agreement which is an arbitration agreement reads as under:—

    “15. ARBITRATION OF DISPUTES:

    15.1.1 In the event of any question, dispute or difference arising under this licence, or in connection thereof, except as to the matter, the decision of which is specifically provided under this licence, the same shall be referred to the sole arbitration of the Director General, Telecommunications, or in case his designation changes, or his office is abolished, then, in such case, to the sole arbitration of the officer for the time being entrusted, whether in addition to the functions of the Director General, Telecommunications or by whatever designation such officer may be called (hereinafter referred to as the said officer), and if the Director General, Telecommunications or the said officer is unable or unwilling to act as such, then some other person appointed by the Director General, Telecommunications or the said officer, will act as the sole arbitrator.

    15.1.2 There will be no objection to any such appointment on the grounds that the Arbitrator is a Government servant, or he has to deal with the matter to which the licence relates, or that in the course of his duties as a Government servant, he has expressed views on all, or any of the matter in disputes or in differences. The award of the arbitrator shall be final and binding on the parties. It is a term of this licence, that in the event of such Arbitrator, to whom the matter is originally referred to, being transferred or vacating his office, or being unable to act for any reason whatsoever, such Director General, Telecommunications or the said officer shall appoint another person to act as Arbitrator, in accordance with the terms of the licence and the person so appointed shall be entitled to proceed with reference to the stage at which it was left out by his predecessor.”

    It is not disputed that the agreement is governed by this arbitration clause. Two questions arise (1) If the disputes raised are covered by this Arbitration Agreement, who should be or is to be appointed Arbitrator and (2) Whether the disputes contemplated under the agreement arise between the parties.

    In the agreement itself, the parties have agreed to the designated authority or his successor or nominee as their arbitrator. Relevant Clauses (2), (5), (6) and (8) of Section 11 of the Act which are relied by the learned counsel read as under:—“11. Appointment of arbitrators.-

    (1) x x x x x x x x

    (2) Subject to sub-section (6), the parties are free to agree on a procedure for appointing the arbitrator or arbitrators.

    (3) x x x x x x x x

    (4) x x x x x x x x

    (5) Failing any agreement referred to in sub-section (2), in an arbitration with a sole arbitrator, if the parties fail to agree on the arbitrator within thirty days from receipt of a request by one party from the other party to so agree the appointment shall be made upon request of a party, by the Chief Justice or any person or institution designated by him.

    (6) Where, under an appointment procedure agreed upon by the parties, -

    (a) a party fails to act as required under that procedure; or

    (b) x x x x x x x x

    (c) a person, including aft institution, fails to perform any function entrusted to him or it under that procedure,

    a party may request the Chief Justice or any person or institution designated by him to take the necessary measure, unless the agreement on the appointment procedure provides other means for securing the appointment.

    (7) x x x x x x x x

    (8) The Chief Justice or the person or institution designated by him, in appointing an arbitrator, shall have due regard to-

    (a) any qualifications required of the arbitrator by the agreement of the parties; and

    (b) other considerations as are likely to secure the appointment of an independent and impartial arbitrator.

    In the case of Nandyal (supra), the Arbitration Clause provided that the arbitrator is to be appointed by the Administrative head of the owner and the arbitration clause was specifically made subject to applicability of the provisions of Arbitration Act, 1940. Arbitrator was not appointed by the Administrative head in spite of 15 days' notice. The Supreme Court held that the Administrative head had abdicated his power to appoint the arbitrator and in view of its Arbitration Clause 65.2, Arbitration Act, 1940 applied and as such only the Court could appoint an arbitrator.

    In the other three cases relied by the learned senior counsel for the petitioner also, the arbitrator was to be appointed by the designated authority. Nandyal was followed and in the case of G.R Reddy, President was required to appoint arbitrator in accordance with the arbitration agreement and in other two cases, the Courts appointed arbitrator under Section 20(4) of the Arbitration Act, 1940.

    Sections 8 and 20(4) of the Arbitration Act of 1940 read as under:—

    “8. Power of Court to appoint arbitrator or umpire.-(1) In any of the following cases-

    (a) where an arbitration agreement provides that reference shall be to one or more arbitrators to be appointed by consent of the parties, and all the parties do not, after differences have arisen, concur in the appointment or appointments; or

    (b) if any appointed arbitrator or umpire neglects or refuses to act, or is incapable of acting, or dies, and the arbitration agreement does not show that it was intended that the vacancy should not be supplied, and the parties or the arbitrators, as the case may be, do not supply the vacancy; or

    (c) where the parties or the arbitrators are required to appoint an umpire and do not appoint him;

    any party may serve the other parties or the arbitrators, as the case may be, with a written notice to concur in the appointment of appointments or in supplying the vacancy.

    (2) If the appointment is not made within fifteen clear days after service of the said notice, the Court may, on the application of the party who gave the notice and after giving the other parties an opportunity of being heard, appoint an arbitrator or arbitrators or umpire, as the case may be, who shall have like power to act in the reference and to make an award as if he or they had been appointed by consent of all parties.

    20. Application to file in Court arbitration agreement.-

    (1)x x x x x x x x

    (2) x x x x x x x x

    (3) x x x x x x x x

    (4) Where no sufficient cause is shown, the Court shall order the agreement to be filed, and shall make an order of reference to the arbitrator appointed by the parties, whether in the agreement or otherwise, or, where the parties cannot agree upon an arbitrator, to an arbitrator appointed by the Court.”

    Section 8(2) expressly gives power to the Court to appoint an arbitrator “if the appointment is not made [in accordance with Section 8(1)] within 15 clear days after service of the notice”. Interpreting this provision in Nandyal case, it was held that if the Administrative head who was empowered to appoint an arbitrator did not make such appointment within 15 days of receipt of notice, he would be deemed to have abdicated his power to so appoint. In that case, parties themselves had not appointed an arbitrator. And Section 20(4) provides for making an order of reference to the arbitrator appointed by the parties whether in the agreement or otherwise, and where parties cannot agree upon an arbitrator, and an arbitrator is to be appointed by the Court, in case no arbitrator is agreed to be appointed by the parties.

    In Sundram Finance Ltd. v. NEPC India Ltd. 1996 (2) SCC 479 while interpreting the scope of Section 9 of the New Act of 1996 vis-a-vis that of Section 41 read with Schedule 2 of the old Act, it has been noticed that the Act of 1996 is very different from the act of 1940 and its provisions have to be construed uninfluenced by the principles underlying the Act of 1940 as the Act of 1996 has been enacted after taking into account the United Nations Commission on International Commercial Trade Law (UNCITRAL), so UNCITRAL Model Law rather than 1940 Act is more relevant to refer.

    In the present case in the arbitration clause itself, the parties have specifically agreed that designated authority or his nominee will be the arbitrator. No power is given in this clause to the Court to appoint any third person as arbitrator. Under the old Act, the Court would have appointed the agreed arbitrator under Section 20(4) and in such case section 8 of the old act would not have been applicable. In Union of India v. Praffula Kumar Sanyal 1979 (3) SCC 631 (AIR 1979 SC 1257) construing Section 20(4) of the Act the Supreme Court in paragraph 3 held as under:—

    “……if no such arbitrator had been appointed and when the parties cannot agree upon an arbitrator, the Court may proceed to appoint an arbitrator by itself. Thus if an arbitrator had been appointed whether in the agreement or otherwise the Court shall make an order of reference to him….”

    In this case, it is further observed that “it is desirable that the Court should consider the feasibility of appointing an arbitrator according to the terms of the contract.

    In G. Rama Chandra Reddy (supra) also, it had been laid down that the Court should endeavour that the contract should always be given effect to, though the contracted party have failed to act according to contract. It is to be seen, whether the contract provided for the appointment of a named arbitrator, and if so, the parties normally would be bound by the terms of the contract and the Court would not be justified to appoint any arbitrator uneless the arbitrator refused or neglected to enter upon the reference”. In India Drugs Pharmaceuticals Ltd. v. Indo Swiss S. Gem Manufacturing Co. Ltd. AIR 1996 SC 543, the arbitration clause stated that difference/disputes shall be referred “to an arbitrator appointed by the Chairman and Managing Director of IDPL.” The Supreme Court held that the said provision could not be given a go by merely at the askance of one of the parties which did not challenge its binding nature in an appropriate proceeding and disallowed the parties request for appointment of a retired High Court Judge as an arbitrator.

    In this respect, reference may also be made to Union of India v. HIMCO (India) Pvt. Ltd. AIR 1965 Cal 404 where Bachawat, J. observed that the arbitration agreement contained adequate and exhaustive machinery for appointment of arbitrators including substitutional appointments in case the appointed arbitrator refuses to act. The learned Judge observed the fact that the appointed arbitrator has not yet signified his willingness to act as arbitrator does not debar the Court from making an order of reference of the dispute to him. If he subsequently refuses to act as the arbitrator, the procedure laid down in the arbitration agreement will prevail and will have to be followed.

    In this case, Section 11 of the Act prescribes the procedure and mode of appointment of arbitrator. It replaces Sections 4, 8, 9, 10 and 20 of the old Act. In this case, the parties have agreed to the appointment of a particular person or his nominee as an arbitrator. Section 1.1(6) read with Section 11(2) and not Section 11(5) is attracted. Since the respondent has not referred the disputes raised to the appointed agreed arbitrator in spite of notice, the Court gets power to take necessary measures for securing the appointment. In that view, the Court will have no power to appoint another arbitrator. Taking the “necessary measure for securing the appointment” in the circumstances would mean to appoint the agreed arbitrator, if any. The agreement between the parties has to be given effect to and cannot be given go bye.

    Learned senior counsel for the petitioner has also contended that the agreed arbitrator (Director General, Telecommunications) is not an independent and impartial arbitrator because of his bias for the Department and moreover he must have dealt with the subject matter of the dispute so far and in that case he would have formed his own opinion and therefore, he has prejudged the matter. He thus will not be a fit and proper person to be appointed as an arbitrator.

    There is no doubt that justice must not only be done but seemingly appear to have been done and for that purpose it is of utmost importance that the judicial Tribunals should be honest, impartial and disinterested. However, when the parties themselves have chosen a person as arbitrator, they being the best judges of the person, the presumption is that the selection was made upon consideration of the pros and cons. Having specifically agreed to this appointment knowingly what the arbitrator is, the parties shall be deemed to have waived the objection of bias, if any. In this connection reference can be made to the following observations made in Nandyal's case (para 7):—

    “When the arbitration tribunal was chosen by the contracting parties, undoubtedly they had chosen to avail of the adjudication by that tribunal and to abide by his decision. Having so chosen and taken a decision it would no longer be open to turn around and contend that the tribunal was biased against the party…”

    The agreed designated arbitrator is a high ranking officer. The parties must have satisfied about the suitability, independence and impartiality of the arbitrator. In the present case except the ground of assumed bias of the arbitrator, there is no valid ground not to bind the parties to their agreed arbitrator and to appoint another arbitrator in supersession of the agreed arbitrator.

    This application is allowed.

    It is accordingly directed that the Director General, Telecommunication shall be the arbitrator in accordance with Clause 15 of the Licence Agreement dated 28.3.1995 for adjudication of the disputes between the parties and in case the designation of the Director General, Telecommunication has changed or his office is abolished, in that case the officer entrusted with or discharging the functions of such Director General shall act under said Clause 15. The arbitration clause is wide and the arbitrator shall decide such disputes as arise under or in connection with the Licence Agreement dated 28.3.1995 The arbitrator shall make his award as far as possible within six months of receipt of this order.

    IA 5714/99

    This is an application under Section 9 of the Act seeking following injunctions by way of interim measures, restraining the respondents:—

    (1) from withdrawing the space segment on the transporter allotted to the petitioner in pursuance letter dated 19.4.1999;

    (2) from terminating the Licence Agreement;

    (3) from invoking the three financial bank guarantees (a) 12/97 for Rs. 1 Crore, (b) 915/98 for Rs. 50 lakhs (c) 20/98 for Rs. 15 lakhs and performance bank guarantee No. 17/97 for Rs. 50 lakhs;

    (4) from recovering any amounts towards licence fees, transponder charges, liquidated damages, penalty or interest except reckoning the effective date from 31.3.1998; and

    (5) from excluding the petitioner while considering the allotment of fresh transponder/space segment.

    The Licence Agreement dated 28.3.1995 was subject to the terms and conditions mentioned in Schedule C and was for a period of 10 years on non-exclusive basis but revocable by giving requisite notice on breach of any of its terms and conditions including default of payment of any consideration payable thereunder. For termination, the decision of the ‘Authority’ will be final. Under the Licence Agreement, licence fee of Rs. 50,000/- from per V-SAT subject to a minimum of Rs. 1 Crore per year for first two years and Rs. 1.5 crores for the 3rd year and thereafter to be reviewed was agreed to be paid. Minimum licence fee is payable in advance but could be paid in equal quarterly instalments and the licence fee in excess of the agreed minimum is payable at the end of the year. The year for the purpose of charging the licence fee is reckoned as 12 months from the date of signing of the Licence Agreement. Clause 5 provided for interest on overdue payments and in case of default dues could be recovered through bank guarantee. For payment of license fee escrow account was to be opened and till it became sufficiently healthy, the licensee was to give financial bank guarantee to the extent of 90% of the licence fee for first year and 10% to be paid in advance and another 15% to be paid 15 days prior to the date of commencement/operation of the service. Besides licence fee, other charges mentioned in Schedule C were also payable.

    Under clause 1(d) of Schedule C, the Licence Agreement came into force on 28.3.1995 when it was signed, 10% licence fee was paid and financial bank guarantee was furnished. Under Clause 3.6 the Licensee was to provide the service within 12 months. Clause 4 provided for liquidated damages in case the service is not provided within the prescribed period for which time was of the essence. Clause 8 provided for termination of the licence, inter alia, in case of defaults as provided. Clause 18 provided for furnishing performance bank guarantee for the licence period and for financial guarantee for financial lability. Clause 20 provided that required space segment shall be reserved from the date of signing of the Licence Agreement in the transponder Nos. 13 and 14 on INSAT II satellite on pre-emptive basis for which the licensee shall pay in advance reservation charges equal to 25% of the annual space segment charge from the date of the signing of the Licence Agreement till the service is commissioned and if 12 months period lapses prior to the start of the service after initial 12 months, full segment charges are payable. Under Clause 21, a licence was required from the WPC (Wireless Planning and Coordination Wing of Ministry of Communications) for utilisation of appropriate radio frequency spectrum for operation of the V-SAT network. Under Clause 21.2 site clearance in respect of HUB Station/V-SAT shall be obtained for which an application was to be submitted to SACFA (Standing Advisory Committee on Frequency Allocations) in the prescribed form. In Clause 21.3, other licence fee and royalty was payable.

    The service did not start within the period of 12 months and even thereafter for some time. Various charges became due and remained unpaid in spite of demands. First licensee M/s Rama had filed a petition under section 11 on the act for 31.8.1996 being A.A 101/96 for appointment of an arbitrator invoking the arbitration Clause 15 and also separate application under Section 9 of the Act of interim protection against invocation of bank guarantees disputing liability and seeking adjudication of the disputes which substantially are the same raised now.

    This Court on 28th February, 1997 passed consent order, the parties agreeing that Rs. 97,79,590/- including penal interest up to January 23, 1997 and interest there-alter were due from the petitioner up to March, 1997 on account of license fee. Against these dues, Rs. 43,00 lakhs by way of FDR and two pay orders of Rs. 25 lakhs each i.e Rs. 93 lakhs were paid to the respondent on 28th February, 1997 and for the balance amount due including interest up to March 1997, the petitioner could approach the respondent for waiver of interest which, if not accepted, would not be disputed and was to be paid on receipt of demand from the respondent. As regards the space segment charges it was agreed that petitioner would pay dues amounting to Rs. 1,04,62,634/- by March 1997.

    It was stated at the Bar by the learned Additional Solicitor General on 28.5.1999 that this request for waiver was made but rejected.

    The license was assigned by M/s Rama to the petitioner by a tripartite license agreement dated 22.9.1997 whereby the petitioner as assignee took over rights, obligations and liabilities of M/s. Rama arising out of the License Agreement dated 28.3.1995 On payment of the dues then due, various clearances from Government authorities required under the license were released. The petitioner then made a representation dated March 23, 1998 giving the background and the reasons for delays in commissioning of the service in time and sought “for waiver of license fee and transponder charges for the period of 30 months from 28.3.1995 to 22.9.1997 and also waiver of the liquidated damages for delayed commissioning of services”. This was not accepted and as the dues were not paid, the respondent vide their letter dated 17.7.1998 invoked the financial bank guarantee of Rs. 1 crore notifying that license fee dues amounts to over Rs. 1.5 crores excluding interest on over due payments had remained unpaid. Another demand of Rs. 1,81,84,000/- as arrears of space segment charges for the years 1997-1998 and 1998-1999 with interest at the rate of 18% per annum was also made on 22.7.1998 The petitioner offered renewal of the financial bank guarantee (FBG) and to furnish additional bank guarantee of Rs. 50 lakhs and to pay Rs. 25 lakhs, out of which Rs. 15 lakhs was remitted by means of demand draft. On this, invocation of FBG was withdrawn on 30.7.1998 subject to compliance of those conditions. Rs. 10 lakhs were paid on 17.8.1998 and other conditions were also complied. The respondent vide letter dated 14.9.1998 again made further demand of Rs. 1,81,84,000/- as arrears of space segment charges due upto 31.3.1998 with interest, which having not been cleared, the respondent again vide their letter dated 18.11.1998 invoked the bank guarantees of Rs. 1 crore and Rs. 50 lakhs. On some payments being made, the invocation of the bank guarantee was again withdrawn on 20.11.1998 On 17.2.1999, the following demand of the arrears was made:—

    (a) Licence fee dues for 28.9.97 to 28.12.98: Rs. 1.8750 crores

    (b) space segment charges 1997-1998, 1998-1999: Rs. 181.84 lakhs

    (c) LD charges (liquidated damages): Rs. 20 lakhs

    (d) Interest on these dues.

    It was notified that if these dues were not paid within 30 days the licence shall be terminated. The petitioner in reply dated March 4, 1999 again disputed their liability and invoked arbitration clause 15, and requested not to invoke the bank guarantees. Some more payments were also made in the meantime. The respondent then vide letter dated 19.4.1999 demanded payment of Rs. 1,59,11,000/- on account of arrears of space segment charges within thirty days failing which it was notified that allocated space segment will be withdrawn. Yet some more payments were made but not all the dues claimed. And thus these proceedings have been instituted.

    By means of interim order dated 28-5-99 subject to payment of 25% of the amount claimed towards licence fee and space segment charges including interest being paid within 15 days, invocation of the bank guarantee and termination of the license was stayed.

    Three financial bank guarantees of Rs. 1.00 crore, Rs. 50,00 lakhs and Rs. 15.00 lakhs which are in identical language furnished by the Canara Bank provided:—

    “2. We, the bank, hereby undertake to pay to the Authority an amount not exceeding Rs. 1,00,00,000/- (Rupees Hundred lacs only) against any loss or damage caused to or suffered or would be caused to or suffered by the Authority by reason of any failure of the licensee to pay all the above mentioned fees, dues and charges or any part therefore within the period stipulated in the licence.

    3. We, the bank hereby further undertake to pay as primary obliger and not merely as surety to pay such sum not exceeding Rs. 1,00,00,000/- (Rupees Hundred lacs only) to the Authority immediately on demand and without demur stating that the amount claimed is due by way of failure of the licensee to pay any fees or charges or any part thereof in terms of the said licence.

    4. We, the Bank, DO HEREBY DECLARE AND AGREE that the decision of the Authority as to whether licensee has failed to pay the said licence fees or any other fees of charge of any part thereof payable under the said Licence Agreement and as to the amount payable to the Authority by the Bank hereunder shall be final and binding on us.”

    And the performance bank guarantee provides:—

    “2. We, the bank hereby undertake to pay to the Authority an amount not exceeding Rs. 50,00,000/- (Rupees Fifty Lakhs only) against any loss or damage caused to or suffered or would be caused to or suffered by the Authority by reason of any breach by the said Licensee of any of the terms and conditions contained in the he said Licence Agreement.

    3. We, the bank hereby, in pursuance of the terms of the said Licence agreement, absolutely, irrevocably and unconditionally guarantee as primary obliger and not merely as surety the payment of an amount of Rs. 50,00,000/- (Rupees Fifty Lakhs only) to the Authority to secure due and faithfully performance by the Licensee of all his/their obligations under the said Licence Agreement.

    4. We, the bank hereby also undertake to pay the amounts due and payable under this guarantee without any demur, merely on a demand from the Authority stating that the amount claimed is due by way of loss or damage caused or would be caused to or suffered by the Authority by reason of breach by the said Licensee for any of the terms or conditions contained in the said Licence Agreement or by reasons of the Licensee's failure to perform any of its obligations under the said Licence Agreement.”

    The petitioner in the statements of account filed in these proceedings has admitted that towards segment charges for the period 28.3.1995 to 28.3.1999, against total dues amounting to Rs. 3,86,41,000/- only Rs. 2,95,49,000/- have been paid. This means balance amount of Rs. 90,92,000/- due as on 28.3.1999 still remains unpaid. Similarly towards licence fee for the period 28.3.1995 to 31.6.1999, against total dues amounting to Rs. 3,69,58,333/-, only Rs. 2,27,50,000/- have been paid leaving a balance of Rs. 1,42,08,333/-. Other dues like liquidated damages, overdue interest would also be due. This liability exceeds the amounts of the bank guarantees.

    The principles of law against invocation of bank guarantee are well established. Recently a three Judges Bench of the Supreme Court in Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engg. Works Pvt. Ltd. (1997) 6 SCC 450 after referring to the relevant case law has referred to with approval the general principles as laid down in the case of U.P State Sugar Corporation v. Sumac International Ltd.. 1997 (1) SCC 568 where it has been laid down as under:—

    “The law relating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realise such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The courts should, therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take the advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplate under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country.”

    It has been held that fraud has to be an established fraud and has reiterated with approval the following observations made in Bolivinter Oil SA v. Chase Manhattan Bank 1984 (1) AII E.R 351:—

    “….The wholly exceptional case where an injunction may be granted is where it is proved that the bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear, both as to the fact of fraud and as to the bank's knowledge. It would certainly not normally be sufficient that this rests on the uncorroborated statement of the customer, for irreparable damage can be done to a bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the bank to have it discharged.”

    And as regards the second exception of irrerievable injury, it has been reiterated as under:—

    “The second exception to the rule of granting injunction, i.e, the resulting of irretrievable injury, has to be such a circumstance which would make it impossible for the guarantor to reimburse himself, if he ultimately succeeds. This will have to be decisively established and it must be proved to the satisfaction of the court that there would be no possibility whatsoever of the recovery of the amount from the beneficiary, by way of restitution.”

    Both these conditions are not attracted in this case. Canara Bank is bound to honour its commitment under the contract of Bank guarantees. What cannot be done directly would not be allowed to be achieved indirectly. The power of Court under Section 9 of the Act in this respect is not different to the power of the Court under Order 39 Rules 1 & 2 while trying a suit. Before an injunction could be granted under Order 39 Rules 1 & 2 cpc, plaintiff has to establish that it has prima facie case, i.e, there was a bona fide contention between the parties or a serious question to be tried in the facts and circumstances of the case. The petitioner as assignee is bound by the obligations emanating from Licence Agreement dated 28.3.1995 The licensee had furnished financial bank guarantees and performance bank guarantee for fulfillment of its obligation under the licence. These were renewed. The petitioner had also furnished two additional guarantees of Rs. 50 lakhs and Rs. 15 lakhs to secure excess liability remaining outstanding. The Licence Agreement has been in force, operated and acted upon by the petitioner and its predecessor in interest for well over four years. The petitioner is bound to fulfill their commitments voluntarily agreed. Great public interest will suffer if the Governmental dues are allowed to be delayed or avoided to be paid. No Government can run and discharge its financial obligations on mere paper bank guarantees. It needs money. As already noticed, the disputes about the liability as existing on 31st March, 1997 were resolved mutually on 28.2.1997 in earlier arbitration proceedings A.A No. 101/96. The petitioner would not be entitled to rake up the settled disputes. No prima facie case is made up. The balance of convenience in the circumstances also does not lie in allowing the petitioner to shirk its financial obligations. The petitioner has also failed to establish that they would be put to any loss or injury what to talk of irreparable loss. On the other hand, it is the respondent who is deprived of its lawful dues. In the circumstances, no case for restraining invocation of the bank guarantees is made out. To that extent, this petition seems to be misuse of the process of the Court and has no merit. The licence is also terminable on account of breach of its terms. However, it is seen that the licence is in the middle of its operation and by now substantial amounts have also been paid under the agreement. Government seems to be more interested in realising its overdue charges rather than in terminating the licence. It will be in the interest of both the parties to stick to the obligations undertaken in the agreement. This action on the part of the petitioner seems to be a misadventure. To avoid hardship and loss that is likely to be caused to both the parties, it seems just and proper that till the arbitration proceedings are decided, the petitioner should clear the dues as demanded and also to continue to pay the same as agreed in the Licence Agreement. Accordingly, it is ordered that if the petitioner pays the arrears of uptodate dues as demanded @ Rs. 50.00 lakhs per month and continue to pay further fees and charges as and when become due, first instalment being paid within ten days of this order and each subsequent instalment within 30 days thereafter every month and the Bank Guarantees being kept alive, the invocation of bank guarantees and termination of the licence shall remain stayed. This is further subject to the condition that petitioner gives an undertaking within one week hereafter to the satisfaction of the Registrar of this Court accepting these conditions. In case of failure to furnish such undertaking or to pay the arrears or any instalment thereof as aforesaid, the stay shall automatically stand vacated.

    It is ordered accordingly. Nothing stated herein shall be deemed to be expression of opinion on merit which may prejudice the parties in proceedings before the arbitrator. A.A No. 181/99 and I.A No. 5714/99 stand disposed of.