Factual and Procedural Background

The petitioner entered into a contract agreement with respondent No. 1 for the construction of 60 Janata Houses at Dilshad Garden, Delhi. The contract contained an arbitration clause (Clause No. 25). Disputes arose between the parties concerning the contract, which were referred to arbitration by the Engineer Member of respondent No. 1, the Appointing Authority. Respondent No. 2 was appointed as the Sole Arbitrator who, after hearing the parties and reviewing evidence, published an award on 10.4.1991. The award was filed in this Court, and objections were filed by the respondents (registered as I.A No. 13100/1991). This opinion disposes of those objections as well as the suit filed by the petitioner.

Legal Issues Presented

  1. Whether the award passed by the Arbitrator in respect of Claims No. 2, 3, 4, and 8 and Counter Claim No. 3 is in accordance with law.
  2. Whether the Arbitrator had jurisdiction to adjudicate claims related to security deposit refund and uncontemplated expenditure for keeping the Bank guarantee alive.
  3. Whether the Arbitrator erred in awarding compensation for work done beyond the stipulated period due to alleged breaches by respondent No. 1.
  4. Whether the Arbitrator could award compensation contrary to Clause 10 of the contract which excludes compensation for delay due to non-supply of materials.
  5. Whether the levy of compensation under Clause 2 of the agreement is an excepted matter outside the jurisdiction of the Arbitrator.
  6. Whether the award granting pre-suit interest to the petitioner is sustainable.

Arguments of the Parties

Respondents' Arguments

  • Challenged the award in respect of Claims No. 2, 3, 4, and 8 and Counter Claim No. 3.
  • Claim No. 2: Security deposit should not be released as the petitioner allegedly failed to duly fulfill the contract; the contract work was incomplete with defects.
  • Claim No. 3: The petitioner was liable to keep the Bank guarantee alive and therefore not entitled to recover expenditure incurred for it.
  • Claim No. 4: No extra claim for prolongation of contract is admissible under Clause 10 of the agreement even if delay was due to non-supply of materials by respondent No. 1.
  • Counter Claim No. 3: Levy of compensation under Clause 2 is final and binding upon decision of the Superintending Engineer and not arbitrable.

Petitioner's Arguments

  • The Arbitrator was an experienced technical person, and the Court should not interfere with his findings.
  • Claim No. 2: The work was completed in March 1984, possession was taken by respondents and allottees, so no defects justified withholding the security deposit.
  • Claim No. 3: Entitled to recover expenditure for keeping the Bank guarantee alive.
  • Claim No. 4: Claimed compensation for work done beyond stipulated period due to breaches by respondent No. 1 causing delays; supported by documents and cost indices.
  • Counter Claim No. 3: If levy of compensation by the Engineer is subsequent to reference, the Arbitrator is competent to decide it.
  • Relied on various precedents supporting the Arbitrator’s competence to award compensation for breach-related delays and price escalation.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Hind Builders v. Union Of India, (1990) 3 SCC 338 : AIR 1990 SC 1340 Supports that an experienced technical Arbitrator's findings should not be lightly interfered with. Accepted that the Arbitrator was experienced but not infallible; scrutiny of award necessary.
Madan Lal v. Union of India, 1990 (1) Arbitration Law Reporter 159 Confirms no universal rule that technical Arbitrators cannot commit errors apparent on record. Used to support the need for court scrutiny of the Arbitrator’s award.
Jagdish Chander v. Hindustan Vegetable Oils Corporation, 1989 (2) AIR 189 Similar principle as above regarding Arbitrator errors. Supported the court’s approach to examine the award for errors.
Continental Construction Co. Ltd v. State Of Madhya Pradesh, (1988) 3 SCC 82 : AIR 1988 SC 1166 Arbitrator bound by contract terms; no extra claims if contract excludes them. Applied to hold that claim for prolongation compensation was barred by contract clause.
Seth Thawardas Pherumal v. Union Of India, AIR 1955 SC 468 Supports that Arbitrator must act within contract terms and cannot award contrary to them. Reinforced the principle that Arbitrator’s award must conform to contract provisions.
Sudershan Trading Co. v. The Government of Kerala, AIR 1989 SC 890 Arbitrator is bound by contract; court cannot substitute Arbitrator’s interpretation once dispute is referred. Used to emphasize that compensation clauses must be respected and Arbitrator cannot award beyond contract.
Salwan Construction Company v. Union of India, ILR (1977) II Delhi 748 Arbitrator competent to award general increase in prices as compensation for breach of contract. Supported petitioner’s claim for price escalation compensation.
A.T Brij Paul Singh & Brothers v. State of Gujarat, (1984) 4 SCC 59 : AIR 1984 SC 1703 Contractor need not lead evidence for loss of profit; Arbitrator entitled to award percentage-based compensation. Supported the award of 20% increase on work done beyond stipulated period.
Hyderabad Municipal Corporation v. M. Krishna Mudiliar, (2011) 8 SCC 155 : AIR 1985 SC 607 Contractor can be granted extra payment at increased rates due to delays. Supported the partial allowance of price escalation claim.
Sunder Lal Khatri v. Delhi Development Authority, 1994 (2) ALR 479 High Court upheld Arbitrator’s award granting 30% price rise. Supported petitioner’s claim for reasonable price escalation.
G.D Tewari v. Delhi Development Authority, Suit No. 2376/1993 Court upheld Arbitrator’s award granting 33% price rise. Further supported petitioner’s claim for escalation.
Vishwanath Sood v. Union of India, (1989) 1 SCC 657 at 658 Levy of compensation under certain contract clauses is final and not arbitrable. Applied to hold that compensation under Clause 2 was outside Arbitrator’s jurisdiction.
Bhartiya Construction Ltd. v. Delhi Development Authority, (1997) 2 Arb. L.R 369 If levy of compensation by Engineer is subsequent to reference, Arbitrator may decide it. Petitioner relied on this to argue Arbitrator’s jurisdiction over Counter Claim No. 3.

Court's Reasoning and Analysis

The Court examined the claims and objections claim-wise. It accepted that the Arbitrator was a technical and experienced person, but emphasized that this does not preclude errors apparent on record. The Court scrutinized the award in light of the contract terms and evidence.

Regarding Claim No. 2 (refund of security deposit), the Court found no error in the Arbitrator’s conclusion that the security deposit should be released as possession was taken by allottees and no action was taken to rescind the contract or rectify defects.

For the claim regarding expenditure to keep the Bank guarantee alive, the Court upheld the Arbitrator’s award, finding no error.

On Claim No. 4 (compensation for work beyond stipulated period), the Court analyzed Clause 10 of the contract, which excluded compensation for delay due to non-supply of materials by respondent No. 1. The Court relied on binding Supreme Court precedents and earlier decisions, concluding that the Arbitrator erred in awarding compensation contrary to the contract clause. Therefore, this part of the award was set aside.

The Court upheld the award granting pre-suit interest to the petitioner, citing settled principles and Supreme Court decisions granting Arbitrators discretion in this regard.

With respect to Counter Claim No. 3 (levy of compensation under Clause 2), the Court held that this was an excepted matter outside the Arbitrator’s jurisdiction since the contract provided a final and binding decision by the Superintending Engineer. The award on this claim was set aside.

Overall, the Court made the Arbitrator’s award a Rule of the Court except for the portions relating to Claim No. 4 and Counter Claim No. 3, which were set aside. The petitioner was also entitled to interest at 15% per annum on the awarded amounts from the date of payment until realization.

Holding and Implications

The Court upheld the award passed by the Arbitrator except in respect of Claim No. 4 and Counter Claim No. 3, which were set aside.

The direct effect of this decision is that the petitioner will receive the amounts awarded under the upheld claims along with interest at 15% per annum. The awards relating to compensation for delay due to breach by respondent No. 1 (Claim No. 4) and levy of compensation under Clause 2 (Counter Claim No. 3) are nullified as beyond the Arbitrator’s jurisdiction or contrary to contract terms. No new precedent was established; the Court applied existing principles on arbitrability and contractual interpretation.

    M.L. Mahajan v. Delhi Development Authority

    Dr. M.K Sharma, J.— The petitioner entered into a contract agreement with the respondent No. 1 for construction of 60 Janata Houses at Dilshad Garden Delhi. The said contract agreement contained an arbitration clause being Clause No. 25. Disputes arose between the parties in respect of the aforesaid contract and accordingly the said disputes were referred to arbitration by the Engineer Member of the respondent No. 1, who was the Appointing Authority under the contract. The respondent No. 2 was appointed as the Sole Arbitrator to adjudicate upon the claims of the parties and the said Arbitrator after hearing the parties and receiving evidence on record, made and published his award on 10.4.1991 The said award was filed in this Court as against which objections were filed by the respondent, which were registered as I.A No. 13100/1991. This order shall dispose of the aforesaid objections filed by the respondents as also the suit filed by the petitioner.

    2. I have heard the petitioner who appears in person as also Mr. Abhilekh Verma, appearing for the respondents. Counsel appearing for the respondent/Objector challenged the award passed by the Arbitrator in respect of Claims No. 2, 3, 4 & 8 and Counter Claim No. 3. The Arbitrator appointed by the Appointing Authority was admittedly a technical person. The petitioner who appeared in person submitted that since the Arbitrator was an experienced and a technical hand the Court should not interfere with his findings. In support of his submission the petitioner relied upon the decision in Hind Builders v. Union Of India., (1990) 3 SCC 338 : AIR 1990 SC 1340. In Madan Lal v. Union of India, 1990 (1) Arbitration Law Reporter 159 and Jagdish Chander v. Hindustan Vegetable Oils Corporation, 1989 (2) AIR 189. There is no dispute with regard to the aforesaid proposition of law laid down. Although the Arbitrator is a technical and experienced person there is no universal rule that such an Arbitrator cannot faulter and/or commit error apparent on the face of the record while adjudicating upon and deciding the disputes between the parties. Thus it would be necessary to scrutinise the award passed by the Arbitrator in the light of the submissions made by the Counsel appearing for the parties and in order to find out whether the award passed is in accordance with law or not.

    3. In the context of the submission of the learned Counsel for the parties I propose to answer the issues raised in the present proceedings claim-wise seriatim.

    4. Objection has been raised by the Counsel for the respondent No. 1 with regard to the award passed by the Arbitrator in Claim No. 2. Claim No. 2 relates to claim of Rs. 71,623/- towards refund of security deposit. The aforesaid amount was deposited by the petitioner in the shape of Bank guarantee. The respondent refused to release the aforesaid amount on the ground that the petitioner has failed to duly fulfil the contract. According to respondent No. 1 the contract work was not completed and there were many defects yet to be rectified and as such security deposit should not be released. The petitioner however, stated that they completed the work in March, 1984 and the possession of the entire flats was taken over by respondents No. 1 and were already allotted to various allottees. It was stated that since the said allottees had also taken over possession of the said flats, it could not be said that there were defects in carrying out the aforesaid contract work. On the evidence on record Arbitrator has also found that the respondent No. 1 had neither taken any action to rescind the contract nor called upon the petitioner for rectification of the aforesaid defective work till date. The Arbitrator, upon consideration of the evidence on record was satisfied that there was no justification for respondent to withhold the security deposit and accordingly directed that the security deposit of the petitioner deposited with the respondent in the shape of Bank guarantee be released. Counsel appearing for respondent No. 1 however, submitted that the security deposit is payable only upon due fulfilment of the contract as laid down under Clause 9. He further submitted that the decision of the Superintending Engineer that there has not been due fulfilment of the contract is final and binding and is not arbitrable and is an excepted matter and as such the Arbitrator committed an error apparent on the face of the record to give an award on such excepted matter. In my considered opinion the aforesaid submission is fallacious. The Arbitrator has found that the possession of the flats has already been handed over to the allottees about 5 years back and that there has been no communication issued by respondent No. 1 for rescinding the contract or for calling upon the petitioner to rectify the defective work, if any. Only because the Superintending Engineer has felt that the petitioner has not duly fulfilled the contract the payment of the security deposit could be kept withheld by the respondent No. 1 in perpetuity without taking an action for rescission of the contract or for getting the defective work, if any, rectified. Thus I find no error in the award passed by the Arbitrator in respect of this claim and the same stands upheld.

    5. Objection was also filed by the respondent No. 1 in respect of the award of the Arbitrator for an amount of Rs. 2,150/- for the claim of the petitioner towards uncontemplated expenditure incurred for keeping the Bank guarantee alive. Learned Counsel appearing for respondent No. 1 sought to assail the aforesaid award on the ground that it was the liability of the petitioner to keep the Bank guarantee alive and therefore, he was not entitled to claim the aforesaid amount for keeping the Bank guarantee alive. The Arbitrator has awarded the aforesaid amount upholding the claim on the same reasoning on which the award was given for releasing the security deposit. I also do not find any error occurring in the findings and and conclusion of the Arbitrator in respect of this claim. The same accordingly stands upheld.

    6. Next objection of respondent No. 1 is in respect of the award passed by the Arbitrator awarding an amount of Rs. 2,64,688/- against the claim of Rs. 3,94,737/- of the petitioner on account of work done beyond the stipulated period due to prolongation of contract because of the alleged breaches caused by the department. The Arbitrator considered the statements and submissions of both the petitioner and respondent No. 1. The Arbitrator, on consideration of the aforesaid statements and submissions came to the finding and conclusion that from the evidence adduced and the arguments advanced by the parties it was established that from time to time breaches were caused by the respondent in respect of supply of materials, drawings and decisions etc. which were responsible for causing delay in the performance of the contract. He further held that the petitioner treated such breaches as partial and continued performance of the contract even beyond stipulated period of time and claimed for 20% increase in the agreement rates due to rise in the market prices and quantum of work executed thereafter. The Arbitrator held that after going through the calculations submitted by the petitioner, an increase @ 20% on the agreement rates for work executed after stipulated date of completion deducting the amount of materials supplied by the department and also the payment already made under Clause 10C of the agreement was found reasonable and therefore, the amount of the award against this claim was found justified working out the same to Rs. 2,64,688/-. For arriving at the aforesaid amount the calculation for the same is also set out in the award itself.

    7. Counsel appearing for the respondent vehemently objected to the aforesaid award on the ground that under the provisions of Clause 10 of the agreement the parties agreed that no extra claim would be entertained for prolongation of the contract even if such prolongation becomes necessary due to non-supply of the material by respondent No. 1. In support of his submission the learned Counsel relied upon an un-reported decision of this Court in M.L Mahajan v. Delhi Development Authority, (Suit No. 2185/1987 & S.No 2295-A/1987) disposed of on 20.7.1990 The learned Counsel also relied upon the decisions of the Supreme Court in Continental Construction Co. Ltd v. State Of Madhya Pradesh., (1988) 3 SCC 82 : AIR 1988 SC 1166; and Seth Thawardas Pherumal v. Union Of India, AIR 1955 SC 468 and also another decision of the Supreme Court in Sudershan Trading Co. v. The Government of Kerala, AIR 1989 SC 890.

    8. The petitioner who appears in person however, submitted that the petitioner has made the aforesaid claim on account of work done beyond stipulated period on account of breach committed by respondent No. 1. He also submitted that in support of the aforesaid claim the petitioner has placed on record the documents indicating such expenses namely Exs. C-18, C-19 etc. He also stated that before the Arbitrator he had filed cost indices to show that there was rise of 26.34% in the cost of material and labour against which the petitioner claimed enhancement of only 20%. Since the Arbitrator has given adjustment to the respondent of ah amount of Rs. 82,889/- paid by it under Clause 10-C and also deducted Rs. 5,67,189/- on account of the rise in prices of the material supplied by the respondent, the petitioner is entitled to the aforesaid amount claimed by him at the reasonable rate which claim was partially allowed by the Arbitrator. In support of his contention the petitioner relied upon the decision of Salwan Construction Company v. Union of India, ILR (1977) II Delhi 748, wherein it was held that the Arbitrator was competent to award general increase in prices which is compensation for loss suffered owing to breach of contract.

    9. He also relied upon the decision of the Supreme Court in A.T Brij Paul Singh & Brothers v. State of Gujarat, (1984) 4 SCC 59 : AIR 1984 SC 1703 wherein it was held by the Supreme Court that in support of claim for loss of profit or damages the contractor was not required to lead any evidence and the Arbitrator was entitled to grant at percentage basis. In the said case their lordships of the Supreme Court upheld 15% extra on the amount of the remaining work.

    10. Reference was also made to the decision in Hyderabad Municipal Corporation v. M. Krishna Mudiliar, (2011) 8 SCC 155 : AIR 1985 SC 607, wherein it was held that the contractor can be granted extra payment at increased rate and in that case the Supreme Court upheld the award of 20% extra over and above the original rates agreed.

    11. He also relied upon a decision of this Court in Sunder Lal Khatri…Plaintiff; v. Delhi Development Authority…Defendant., 1994 (2) ALR 479 wherein the High Court upheld the award of the Arbitrator granting 30% rise. Reference was also made to the decision in Suit No. 2376/1993 titled G.D Tewari v. Delhi Development Authority, wherein this Court upheld the rise granted by the Arbitrator to the tune of 33%.

    12. In order to resolve the dispute and to come to a conclusion in respect of the aforesaid award I looked into the provisions of Clause 10 of the Contract. The said clause provides that stores would be supplied by DDA. Relevant portion of the said clause may be extracted below:

    “all materials so supplied to the contractor shall remain the absolute property of DDA and shall not be removed on any account from the site of the work……… … provided that the contractor shall in no case be entitled to any compensation or damages on account of any delay in supply or on supply thereof all or any such materials and stores. Provided further that the contractor shall be bound to execute the entire work if the material supplied by the DDA within the schedule time for completion of the work plus 50% thereof …. …. for the completion of the rest of the work the contractor shall be entitled to such extension of time as may be determined by the Engineer Incharge whose decision in this regard shall be final and binding.”

    13. Relying on the aforesaid provision Counsel for respondent No. 1 submitted that in view of the aforesaid provisions even if there be any delay on the part of respondent No. 1 for the supply of material to the petitioner he would not be entitled to any compensation. Counsel submitted that in view of the aforesaid provision the Arbitrator committed manifest error of law in awarding the aforesaid amount to the petitioner in the present case. The aforesaid Clause 10 came to be interpreted by this Court in case of M.L Mahajan (supra). This Court after considering the implications of the aforesaid Clause 10 and in the light of the decision on similar issues by the Supreme Court came to the conclusion that the delay could have been mostly due to non-supply of material but because of Clause 10 of the contract no extra claim was entertainable by the Arbitrator. This Court held that from the award it is impossible to bifurcate the sum awarded as representing damages on account of delay of decisions etc. and delay on account of non-supply of cement and thus an objection raised on behalf of the DDA was upheld and sustained and the award of the Arbitrator was set aside.

    14. In Sudershan Trading Company case (supra) the Supreme Court had occasion to deal with a case whether a contractor had been awarded a sum of money contrary to the terms of the contract. While dealing with the said case the Supreme Court observed as follows:

    “Insofar as the Court held therein that an Arbitrator deciding a dispute under the contract is bound by the contract, the Court is right. The Court cannot, however, substitute the decision of the Arbitrator as to what was meant by the contract, once that dispute is conceded to the Arbitrator. In so far and to the extent the aforesaid decision of the Kerala High Court decided to the contrary, the same is not the correct law.”

    15. The aforesaid observations of the Court disapproved the Arbitrator awarding money contrary to the terms of the contract and it observed that the Arbitrator was bound by the contract. In Continental Construction Company case (supra) the Supreme Court had occasion to consider a clause similar to clause 10 of the present case. In that case the clause which the Supreme Court considered was clause 3.3.15 which reads as under:

    “Time limit for unforeseen claims—Under no circumstances whatever shall the contractor be entitled to any compensation from Government on any account unless the contractor shall have submitted claim in writing to the Engineer-in-Charge, within one month of the cause of such claim occurring.”

    16. It was contended in that case that the claimant was not entitled to extra cost for material and labour. Dealing with the aforesaid the Supreme Court held thus:

    “The District Judge found and in our opinion rightly, that the question regarding extra cost was a general question and not a specific legal question and the decision of the Arbitrator was not final one. The Arbitrator misconducted himself in allowing claim without deciding the objection of the State. In view of the specific clauses, the appellant was not legally entitled to claim for extra cost.”

    17. In my considered opinion, the ratio laid down by the aforesaid Supreme Court decision in Continental Construction Company case (supra) and M.L Mahajan case (supra) squarely applies to the facts and circumstances of the present case.

    18. In terms of Clause 10 of the contract no compensation is to be awarded although there is a delay in completion of the work on account of non-supply of any material or stores. The Arbitrator has awarded the aforesaid amount for breaches committed by the respondent in respect of materials, drawings and decisions which were responsible for causing delays in the performance of the contract. The aforesaid decision of the Supreme Court is binding on me and relying upon which the decision in M.L Mahajan (supra) was delivered, with which I respectfully agree. Since the parties have agreed upon not to claim any compensation or damages on account of any delay in supply of all or any such materials and stores, the Arbitrator as well as this Court has to give effect to the aforesaid intention of the parties in all matters and the Arbitrator could not have given an award contrary to the aforesaid express provisions of the contract. The Arbitrator had jurisdiction only to act in accordance with the contract which is also the principle enunciated in Continental Construction Company's case (supra). In that view of the matter the award passed by the Arbitrator in respect of this claim is set aside.

    19. Claim No. 8 is with regard to award of the Arbitrator with regard to grant of pre-suit interest. In view of various decisions of the Supreme Court and settled principles of law granting such a discretion to the Arbitrator to allow interest to the petitioner for the pre-suit period, the objection of respondent No. 1 in respect of the aforesaid award of the Arbitrator granting pre-suit interest has no merit and the same accordingly, stands rejected. The award of the Arbitrator in respect of this claim stands upheld.

    20. With the aforesaid findings the only other issue that survives for consideration is with respect to the award of the Arbitrator in Counter Claim No. 3. Counter Claim No. 3 relates to claim of respondent No. 1 for an amount of Rs. 1,28,246/- on account of levy of compensation under Clause 2 of the agreement. It was held by the Arbitrator that since it was established that performance or the contract was delayed due to the respondents and the parties through their conduct had given a go-by and did not maintain time as essence of the contract the levy of compensation by respondent No. 1 under the provisions of Clause 2 of the agreement was not justified.

    21. An objection has been filed as against the aforesaid award on the ground that the Arbitrator was not competent to give his award in respect of the aforesaid claim since levy of compensation under the contract was an excepted matter inasmuch as Clause (2) of the agreement stipulated that the work throughout the stipulated period of the contract would be proceeded with all due diligence and that the contractor would pay as compensation an amount equal to 1% or such other amount as the Superintending Engineer of Delhi Development Authority might decide on the amount of the estimated cost and the said decision of the Superintending Engineer in writing would be final. It is stated that since the Superintending Engineer in the instant case took a decision for levy of compensation on the petitioner because of the delay in carrying out the work, his decision was final and binding and the Arbitrator could not have given an award on the aforesaid levy of compensation. Similar clause came to be interpreted by this Court in the case of Sudhir Brothers (supra) and also Vishwanath Sood v. Union of India, (1989) 1 SCC 657 at 658. In the said decision it was held that such a clause contains a complete machinery for determination of compensation and that the decision of the Superintending Engineer is in the nature of considered decision and therefore, the question of awarding compensation under Clause 2 is outside the purview of the Arbitration and such levy of compensation could not be called in question before the Arbitrator. The petitioner however, placed reliance on a decision of this Court in Bhartiya Construction Ltd. v. Delhi Development Authority, (1997) 2 Arb. L.R 369 for the proposition that if the levy of the compensation by concerned Engineer is subsequent to reference, the Arbitrator shall be competent to decide the same. The petitioner pointed out that here also the reference was earlier and determination of the compensation was later. In my considered opinion there can be no reference of an admitted excepted matter as the Arbitrator has no jurisdiction to adjudicate such matter. Merely because a reference is made wrongly the Arbitrator cannot assume jurisdiction which is not vested on him.

    22. In the light of the aforesaid decision of this Court as also of the Supreme Court the issue with regard to justification for levying compensation under Clause 2 is outside the purview of the Arbitrator and the compensation awarded under Clause 2 would not be capable of being called in question before the Arbitrator. Reading Clauses 2 and 25 it must be held that the amount of compensation chargeable under Clause 2 is a matter which is to be adjudicated in accordance with that clause and the same could not have been referred to in Clause 25 and the Arbitrator was also not competent to give any award on the aforesaid claim. Thus the award passed by the Arbitrator with regard to the aforesaid claim stands set aside.

    23. Thus the award passed by the Arbitrator, save and except for the award against Claim No. 4 and Counter Claim No. 3 are made Rule of the Court. The award passed by the Arbitrator in respect of Claim No. 4 and Counter Claim No. 3 stands set aside. The petitioner shall also be entitled to interest @ 15% per annum from the date of payment till realisation on the part of award passed by the Arbitrator and made a Rule of the Court. There shall be no order as to costs.

    Award except against Claim No. 4 and Counter Claim No. 3 made Rule of Court.
    Use AI to get other relevant cases.

    Comments

    M.L. Mahajan v. Delhi Development Authority
    (Sep 23, 1998)